Resolved
That the progress made in implementing internal audit agreed actions as reported be considered. Reason: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
Audit and Governance Committee agreed this item on Wednesday 20 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress made in implementing internal audit agreed actions as reported be considered. Reason: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
1. This is the biannual report to the committee setting out progress made by council departments in implementing actions agreed as part of internal audit work.
2. Where weaknesses in systems are found by internal audit, the auditors discuss and agree a set of actions to address the problem with the responsible manager. The agreed actions include target dates for issues to be dealt with. The auditors then carry out follow up work to check that the issue has been resolved once these target dates are reached. The follow up work is carried out through a combination of questionnaires completed by responsible managers, risk assessment, and by further detailed review by the auditors where necessary. Where managers have not taken the action they agreed to, issues are escalated to more senior managers, the Governance, Risk and Assurance Group (GRAG) and ultimately may be referred to the Audit and Governance Committee.
3. A summary of the findings from follow up work is presented to this committee twice a year with the last report being presented in May 2017.
4. Details of the findings of follow up work are discussed with the relevant service managers and chief officers. Follow up of internal audit agreed actions
5. A total of 67 actions have been followed up since the last report to this committee in May 2017. A summary of the priority of these actions is included in figure 1, below.
Figure 1: actions followed up as part of the current review Number of actions Priority of actions* followed up 1 0 2 21 3 46 Total 67 * The priorities run from 1 (high risk issue) to 3 (lower risk)
6. Figure 2 below provides an analysis of the actions which have been followed up, by directorate.
Figure 2: actions followed up by directorate Priority of actions CCS EP CEC HHASC 1 (High) 0 0 0 0 2 13 6 2 0 (Medium) 3 (Low) 27 0 19 0 Total 40 6 21 0
7. Of the 67 agreed actions 55 (82%) had been satisfactorily implemented and 4 (6%) were no longer needed1.
8. In a further 8 cases (12%) the action had not been implemented by the target date, but a revised date was agreed. This is done where the delay in addressing an issue will not lead to unacceptable exposure to risk and where, for example, the delays are unavoidable (e.g. due to unexpected difficulties or where actions are dependent on new systems being implemented). These actions will be followed up after the revised target date and if necessary they will be raised with senior managers in accordance with the escalation procedure. Figure 3 below shows the priority of these actions.
1 For example because of other changes to procedures or because the service has ended or changed significantly. Figure 3: priorities of actions with revised implementation dates
Priority of actions CCS EP CEC HHASC 1 (High) 0 0 0 0 2 1 0 0 0 (Medium) 3 (Low) 3 0 4 0 Total 4 0 4 0
9. One P2 action had an implementation date revised by more than six months during the period. Further details are included in annex 1.
Conclusions
10. The follow up testing undertaken confirms that in general good progress has been made by council departments to rectify weaknesses in control identified through internal audit work. This is an ongoing process and progress in implementing agreed actions will continue to be monitored and reported as required through the escalation procedure. There are no specific issues that need to be brought to the attention of the Audit and Governance Committee at this time.
11. Not relevant for the purpose of the report.
Analysis
12. Not relevant for the purpose of the report.
Corporate Priorities
13. This report contributes to the council’s overall aims and priorities by helping to ensure probity, integrity and honesty in everything we do. It also contributes to all the improving organisation effectiveness priorities. Implications
14. There are no implications to this report in relation to:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Follow UpsAppendix 1 | 1 pages | Download |
PDF |
Internal Audit Follow Up ReportReport | 5 pages | DownloadRead as text |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.