Advice of the Advisory Panel That the Executive Member be advised: (i) That the updates to schemes, as detailed in the report, be noted; (ii) That the scheme reprofiling and slippage detailed in the report and summarised in Annex A be agreed; (iii) That, subject to the latest budget position following the analysis of tenders, the decision on funding the expected budget shortfall on the York High Pool Scheme be referred to the Executive; (iv) That the remainder of the revised capital programme, as set out in Annex A, be approved. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Executive Member for Leisure and Culture and Advisory Panel 3 June 2008
Report of the Director of Learning Culture and Children’s Services and the Director of Resources
CAPITAL PROGRAMME OUT-TURN 2007/08 Summary 1 This report is to: • inform Members of the final outturn position of the 2007/08 Capital Programme. • advise Members of changes to existing schemes to allow the more effective management and monitoring of the Capital Programme. • inform Members of any slippage in budgets between financial years. • inform Members of any new schemes and seek approval for their addition to the 2008/09 to 2010/11 Capital Programme.
Background 2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. Since then a number of amendments to the programme have been approved both by the Executive Member and the Executive. This has resulted in a current approved Leisure & Culture Capital Programme for 2007/08 which shows gross capital expenditure of £2.951m, with £0.811m of other funding which gives a net capital programme cost of £2.140m. The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in February 2007.
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 4.477 0.825 3.652 Slippage and Adjustments from the 2006/07 0.115 0.077 0.038 Outturn report Monitor 1 Adjustments (1.591) 0.009 (1.600) Monitor 2 Adjustments (0.050) (0.100) 0.050
Current Approved Capital Programme 2007/08 2.951 0.811 2.140
Consultation 3 Not applicable
Options and Analysis
2007/08 Scheme Outturn 4 Each major scheme in the capital programme has been reviewed to provide an assessment of its current status. Annex A shows the current approved capital programme and the outturn position for 2007/08, together with any slippage that is required to and from future financial years. Updates have been provided for all schemes, with progress and variations explained in the following paragraphs.
York Pools and Indoor Sports Provision (Overall Scheme Cost £9.669m)
5 The separate schemes within the overall Pools programme reflect the amendments which were approved by the Executive on 23rd October 2007 and reported at Monitor 2.
6 The scheme to undertake repairs at Yearsley Pool has been completed successfully and the pool has now reopened. An additional £18k is required to be transferred from the contingency budget to fund a small overspend and this will need to be brought forward from 2009/10.
7 The detailed design for the new swimming pool on the York High site has now been completed. Tenders were due to be returned and analysed by the end of May, at which point the final price for the scheme will be established. A verbal update will be given at the meeting.
8 The latest cost estimates, however, show a budget shortfall of £0.5m. Reductions in the specification and removal of some elements has reduced this gap by £0.1m, but any further cuts would mean reducing the specifications in such a way that the lifespan of the building would be significantly reduced or taking out elements that would have a serious impact on the business plan for the Centre.
9 Any budget shortfall will be an issue for the Executive to consider in the context of the overall capital programme. Options available for the Executive to consider include: • Extending the prudential borrowing repayment period from 17 to 30 years, which is reasonable given the life expectancy of the facility (the annual repayments would remain at £130k, funded by the reduced running costs of the new facilities). This could provide an additional £470k. • Increasing the level of corporate capital resources allocated to the project, subject to the latest position on the overall council capital programme following the 2007/08 outturn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.