Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 9 September 2008. Below is the council's own wording, with the papers it was decided on.
(i) That the position on the interim waste contract be noted. (ii) That Option 2 be agreed (undertake additional feasibility work in 2008/09) and that a one-off sum of £35,000 be allocated from contingency to fund further design work on the new west of York recycling centre to be located at Harewood Whin. REASON: To progress the provision of improved recycling facilities in the west of the City, building on the success of Hazel Court in the east, without further delay. (i) That the position on the interim waste contract be noted. (ii) That Option 2 be agreed (undertake additional feasibility work in 2008/09) and that a one-off sum of £35,000 be allocated from contingency to fund further design work on the new west of York recycling centre to be located at Harewood Whin. 1 REASON: To progress the provision of improved recycling facilities in the west of the City, building on the success of Hazel Court in the east, without further delay.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 9 September 08
Report of the Director of City Strategy
WASTE UPDATE Purpose of report 1. To provide and update to Members on the relocation options for Beckfield Lane HWRC requesting funding for additional feasibility work and to update on negotiations on the interim contract for waste disposal.
Background – Beckfield Lane HWRC 2. As part of the policy prospectus for 07/08, members via the groups leaders agreed that options relating to Beckfield Lane HWRC should be considered largely because of the position of the site within a residential area and the traffic congestion associated with the site.
3. A full analysis of the options available was undertaken in May 07 taking into account work undertaken by external consultants; this was considered by Corporate Management Team. It was clear there was no option that provided an ideal solution, because of the criteria considered.
4. Following further consultation, the options analysis was narrowed to considering 3 options. Initial feasibility work has been undertaken on these options, funded from within existing budgets. However in order to progress this work to the position where members have sufficient information to make a decision it is estimated that a further £35,000 is required to cover preliminary design work, specifications, topographical surveys and further analysis of planning issues around the short listed options.
5. Members are therefore requested to consider the priority of this work in the current financial year. In order to fund the additional feasibility work which will be carried out by the engineering design team, supported by external advisors as appropriate, a funding request will be required, as no funds are currently allocated to this work. If Members consider this work to be a priority a request can be made by Executive to full Council for the release of funds from reserves. Alternatively a growth bid can be made for funding from 09/10 budgets.
6. If Members are minded to support the work, a capital growth bid will need to be submitted for future years capital expenditure. Background – Interim Waste Disposal Contract 7. As Members are aware the Council has entered into an Inter Authority Agreement with NYCC to provide long term waste disposal facilities through the PFI scheme. Until this contract is operational there is a potential LATS liability in target years (please refer to report to Executive on 27 March 2007) and consequently the two authorities have been working together to find an interim solution to cover the period until the PFI contract is operational in 2013/14.
8. It had been anticipated that the outcome would have been known at this stage, enabling a recommendation to be put to members on whether CYC should participate in joint arrangements with NYCC. However negotiations have not yet been completed and a report will be brought back for members consideration when the evaluation has been completed
9. Members are therefore asked to note the latest position.
Options on HWRC relocation 10. Option 1 Do nothing. This would involve continuing to use the facilities available at Beckfield Lane for the foreseeable future, and is not recommended because of ongoing anti-social behaviour issues, traffic congestion and proximity to residential housing
11. Option 2 Undertake additional feasibility work in 08/09. This would inform members on preferred options and estimated costs and would enable an accurate bid to be submitted for capital funding in 09/10
12. Option 3 – Request Council to prioritise funding for the feasibility work identified as part of the 09/10 budget process, with associated estimated capital costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.