Resolved
That the report be noted. REASON: To update the Shadow Executive.
Shadow Executive noted this item on Wednesday 12 November 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. REASON: To update the Shadow Executive.
Shadow Executive 12th November 2008
Joint Report of the Assistant Director (Property Services) and Assistant Director (Leisure Services)
The Barbican – An Update Summary 1 This report is an update on the progress of the development of the Barbican’s component parts
Background 2 The Development of the Barbican site incorporates the following component parts:
a. The Barbican Auditorium
b. The residential development site
c. The 4* hotel development site
d. The Kent Street hotel site
e. The Kent Street car park
Information The Barbican Auditorium
3 Current position with Absolute Leisure Limited
4 Following meetings between CYC Officers and Absolute Leisure (ALL), that have dealt with outstanding planning and legal issues, their programme is now to complete the refurbishment and re-open the facility in August 2009
5 Absolute Leisure have committed to the Barbican Auditorium being used as a performance venue for public entertainment. The capacity of the facility will be for up to 1200 people and Absolute Leisure will look to provide a minimum of 50 performances per year with an attendance in excess of 800 people.
The residential development site 6 Persimmon owns the residential site and has a planning approved scheme to deliver apartments on the Barbican site. They have intimated that it is there intention to sell on the development site and are currently undertaking a marketing exercise.
The 4* Hotel Site
7 The hotel development site was purchased by WG Mitchell (Twelve) Limited, which simultaneously entered into a development agreement with Pilot Hotels to build a 4* star hotel by March 2012. In the sale transfer and by a separate deed both Mitchell and Pilot Hotels gave the above development covenants to the Council. The Whitbread Group has purchased Pilot Hotels and renamed the company Premier Inn Holdings Limited. Premier Inn Holdings informal offer is to provide a hotel under the Premier Inn brand, although this is not a classified 4* hotel, they say they would build a hotel as the consented scheme and incorporating both conference and public restaurant facilities. The council is still awaiting a written offer, sketch floor layouts and a development timetable.
Kent Street hotel site
8 The Council has a development contract to sell the Kent Street site to Indominto Properties subject to the developer receiving a satisfactory planning consent. The developer has reported however, additional development costs resulting from an archaeological investigations planning condition and therefore the developer may run an argument that a satisfactory planning consent has not been received.
Kent Street car park
9 Indominto Properties holds a long lease from the Council and in turn have they have Q Park as an operating tenant.
Options 10 None. This briefing note is for information only.
Consultation 11 Consultation and discussion continues between the officers of City Strategy, Property Services, Legal Services and the council’s external advisers to ensure the best solution possible from this development and protect the council’s interests.
Corporate Priorities 12 To improve economic prosperity
Implications 13 The following information is provided:
• Financial
There are no changes in the financial position of this development at this time.
• Human Resources (HR)
There are no HR implications. • Legal
Implications are included within the report.
• Crime and Disorder (C & D)
There are no C & D implications.
• Information Technology (IT)
There are no IT implications.
• Property
Potential impact from the recent downturn in the housing and construction market as a consequence of the ‘credit crunch’.
Risk Management 14 The current state of the property and construction market may increase the risk of not achieving an early completion of the outstanding parts of this development, or amendments to the development obligations, or realisation of the overage payment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
The Barbican: An UpdateReport | 42 KB | DownloadRead as text |
Follow Shadow Executive at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2009 | Exclusion of Press and PublicThat the press and public not be excluded from the meeting as there was no exempt information relating to briefings o... | Decided | Open |
| 14 Oct 2009 | MinutesThat the minutes of meetings of the Shadow Executive held on 2 and 16 September 2009 be approved and signed by the Ch... | Approved | Open |
| 14 Oct 2009 | Safer York Partnership: Crime and Disorder Reduction Partnership for the City of YorkThat the briefing report be noted. REASON: To inform and update the Shadow Executive and help shape the effectiveness... | Noted | Open |
| 16 Sep 2009 | Exclusion of Press and PublicThat the press and public not be excluded from the meeting as there was no exempt information relating to briefings o... | Decided | Open |
| 16 Sep 2009 | Safer York Partnership: Crime and Disorder Reduction Partnership for the City of YorkThat consideration of this briefing report be deferred to the Shadow Executive meeting on 14 October 2009. REASON: To... | Deferred | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.