TSAR Traffic Signal Refurbishment – Barbican Road/Paragon Street

Approved Executive 7 papers

Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 19 April 2022. Below is the council's own wording, with the papers it was decided on.

Item64

Resolved

i. Approved the proposed design option presented in Annex A of the report. Reason: To achieve the core aim of replacing the life-expired traffic signal asset to established TSAR programme standards such that it can continue operate and be repaired economically before it becomes unmaintainable. Additionally, the formalisation of the existing uncontrolled crossing facility over Barbican Road and the introduction of a new crossing of Paragon Street provides a significant improvement to pedestrian and cyclist safety at the junction and will assist in reducing existing levels of pedestrian/cyclist conflict at the south western corner of the junction which have previously been highlighted as an issue. i. Approved the proposed design option presented in Annex A of the report. Reason: To achieve the core aim of replacing the life-expired traffic signal asset to established TSAR programme standards such that it can continue operate and be repaired economically before it becomes unmaintainable. Additionally, the formalisation of the existing uncontrolled crossing facility over Barbican Road and the introduction of a new crossing of Paragon Street provides a significant improvement to pedestrian and cyclist safety at the junction and will assist in reducing existing levels of pedestrian/cyclist conflict at the south western corner of the junction which have previously been highlighted as an issue.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 16 pages

Summary

1. The traffic signalling equipment at this site is life expired, has become difficult and costly to maintain and needs to be replaced.

2. The TSAR (Traffic Signal Asset Renewal) programme is the means by which life expired traffic signal assets across the city are refurbished.

3. Although the programme is primarily about asset renewal, there is scope to take advantage of ‘easy wins’ whilst refurbishing the equipment. To that end, a design option which looks to include new signal controlled pedestrian and cyclist crossing facilities across the junction providing links with existing off carriage way pedestrian and cycling provision to the West of the junction has been put forward.

A decision is required to approve the proposed alterations.

Recommendations

4. The Executive Member is asked to:

Approve the proposed design option presented in Annexe A of this document

Reason:

This option achieves the core aim of replacing the life-expired traffic signal asset to established TSAR programme standards such that it can continue operate and be repaired economically before it becomes unmaintainable.

Additionally, the formalisation of the existing uncontrolled crossing facility over Barbican Road and the introduction of a new crossing of Paragon Street provides a significant improvement to pedestrian and cyclist safety at the junction and will assist in reducing existing levels of pedestrian/cyclist conflict at the south western corner of the junction which have previously been highlighted as an issue.

Background

5. The TSAR (Traffic Signal Asset Renewal) programme has been in place since 2015 and is responsible for the replacement of life expired traffic signal assets around York.

6. The focus is on replacing equipment that is liable to imminent failure, rather than seeking to improve congestion or achieve a similar transport improvement goal. However, where ‘easy wins’ can be achieved at the same time as replacing obsolete equipment, these will be taken advantage of.

7. To date, 42 sets of signals have been refurbished and a further 7 are proposed for completion in the 22/23 financial year.

8. Recent maintenance checks of the site indicate that some of the infrastructure is now classed as failing with the traffic signal controller and the majority of the signal poles being in excess of 20 years old. The junction also has no functioning vehicle detection capabilities as the loops previously installed in the carriageway have deteriorated significantly.

9. The junction lies on the York inner ring road and currently offers no controlled pedestrian crossing facilities at the site. An uncontrolled pedestrian refuge exists on the southern arm of Barbican Road however its size makes it problematic for users with pushchairs/cycles/wheelchairs etc.

10. Cycle provision at the junction is disjointed and this is particularly notable on the south-west corner of the site between Barbican Road south and Paragon Street where conflict between pedestrians and cyclists entering and exiting defined off road facilities has been highlighted as an issue. 11. A ward funded study was established in January 2020 to investigate potential pedestrian and cyclist improvements running along the extent of Paragon Street. This followed a request for removal of the drop cycle kerb at the south west corner of the junction to prevent cycle/pedestrian conflicts as cyclists transitioned from the carriageway at speed onto a defined section of off carriageway cycle path. The immediate removal of the drop kerb was not supported as an alternative access point for the off carriageway cycle facility could not be established however this is now possible under the design proposals put forward under this TSAR scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CYC_TST-YK2230-P-001 (P01) For Consultation drawingAppendix A 1 pages Download
PDF
Existing Option part 1Appendix B 1 pages Download
PDF
Existing Option part 2Appendix B 1 pages Download
PDF
Option A part 1Appendix B 1 pages Download
PDF
Option A part 2Appendix B 1 pages Download
PDF
TSAR Traffic Signal Refurbishment: Barbican Road/Paragon StreetReport 16 pages DownloadRead as text
PDF
View item 64. as HTML 95 KBReport 95 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. TSAR Traffic Signal Refurbishment – Barbican Road/Paragon StreetThis decision
  2. TSAR Traffic Signal Refurbishment – Junction of Malton Road / New LaneApproved
  3. TSAR Traffic Signal Refurbishment - Clifton Moorgate / Hurricane Way YK2239Approved
  4. TSAR Traffic Signal Refurbishment - Clifton Moorgate / Hurricane Way YK2239Deferred
  5. TSAR Traffic Signal Refurbishment - Wigginton Road / Crichton Avenue YK2221Approved
  6. TSAR Traffic Signal Refurbishment - Hull Road/Osbaldwick Link RoadApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies