Leisure, Culture and Social Inclusion and Advisory Panel noted this item on Tuesday 2 December 2008. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: Restoration of the Bowls Pavillion – Ark in the Park: (i) To note the current situation (ii) To offer support to the efforts of the Friends to develop the proposed Ark in the Park (iii)To ask officers to draw up a funding bid for the 2010/11 capital programme, including investigation of external funding. Flood Management: (i) That Officers investigate a bid to the venture fund to self finance any works. Goose Management: (i) To note the current situation and carry on with the current management regime (ii) To commission a city wide study and report back to EMAP on any possible changes to the existing management scheme. (ii) To welcome any support from Micklegate Ward Committee Funding towards establishing best practice in Goose Management. Decision of the Executive Member:
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Meeting of the Executive Member for Leisure and 2 December 2008 Culture, and Social Inclusion, and Advisory Panel
Report of the Assistant Director (Lifelong Learning and Culture)
Rowntree Park- Ongoing development Summary 1. This report updates members on the three main ongoing development issues for Rowntree Park. Members are asked to give guidance on the way forward for each of the issues. The report will be accompanied by a presentation by the Friends of Rowntree Park.
Background 2. Rowntree Park is the city’s Premier park serving both the local communities of Clementhorpe, South Bank and Fishergate and a wider city audience. Opened in 1921 as a memorial to those who fell and suffered in the First World War it has undergone several changes over the years. Most recently, between 2000 and 2003 it was largely restored to its former glory with the help of a £1.3m grant from the Heritage Lottery Fund Urban Parks Programme and the work of the Friends of Rowntree Park.
3. Since then the Park has been awarded a Civic Trust Green Flag award each year since 2004, and in 2005 was runner up in the Street design award Urban Green Space category. Despite these accolades work continues to improve the park for residents and visitors. Physical works have concentrated on improving and rebuilding the tennis courts to modern competitive standards. The Friends have also continued to develop with the establishment of the Young Friends and the Very Young Friends, which compliment the work of the Parks and Open Space Community Officers and undertake activities in their own right.
4. A number of key challenge remain: Restoration of the bowls pavilion – Ark in the Park Flood management Goose management
Consultation 5. This paper has been prepared in consultation with the Friends of Rowntree Park who will also be speaking at the EMAP. The issues highlighted have been the subject of an ongoing discussion with the Friends, local communties and Green Flag judges over a number of years. Development issues 6. Restoration of the bowls pavilion – Ark in the Park. Improvement and refurbishment of the bowls pavilion was an omission from the 1996 HLF bid and, following the improvements to the tennis courts, remains the one item left in the park in need of restoration. (See Annex 1 where the building is marked “pavilion and tickets”). Originally designed as a bowls pavilion in the 1970s, the main use of the pavilion over the last few years has been as a home for the Friends’ activities and the parks team’s Education programme. It is not especially suitable for any of these uses being too small, having the wrong internal layout and most importantly not being flood proof. When the park floods the building gets inundated with water and mud. Even when cleaned, it is left feeling damp and smelly. Since its double immersion (to date) in 2008 it is currently unusable as a base for park activities.
7. In 2006 the Friends set up a working group comprising Friends and council staff, with a view to canvassing opinion on how to resolve this situation. Following several rounds of public consultation the Friends, with the Council’s support, submitted a bid for funding under the Big Lottery Fund's Community Buildings programme. The bid was for an eco-friendly building, on the same site as the current pavilion, with level access and with the innovative feature that it would rise up and float when the park floods, protecting the contents from damp and damage. The building would be used as a community space, classroom, changing rooms for sport and performance and an office for the park keepers. Unfortunately this bid was not successful but it has left a strong desire to see such a building in the park.
8. For the scheme to progress the Friends will soon be seeking planning permission which, if granted, would help in seeking funding for the project. They would also require a lease for the building or for this part of the park from the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.