Leisure, Culture and Social Inclusion and Advisory Panel noted this item on Tuesday 2 December 2008. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: (i) Note the updates to schemes as detailed in the report. (ii) Agree the scheme amendments and additions reported in the report and summarised in Annex A. (iii)Approve the revised capital programme as set out in Annex. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Summary
1 This report is to: • inform Members of the likely out-turn position of the 2008/09 Capital Programme based on the spend profile and information to the end of October 2008. • advise Members of changes to existing schemes to allow the more effective management and monitoring of the Capital Programme. • inform Members of any new schemes and seek approval for their addition to the Capital Programme.
Background
2 The original capital programme for the financial year 2008/09 was approved at Council on 21 February 2008. A number of amendments were then approved as part of the 2007/08 outturn report and at the first monitor. This has resulted in a current approved Leisure & Culture Capital Programme for 2008/09 which shows gross capital expenditure of £5.389m, with £1.645m of other funding which gives a net capital programme cost of £3.744m. The table below details the approved changes to the 2008/09 capital programme since the original programme was approved in February 2008.
Gross External Revenue Prudential Capital Spend Funding Contribs Borrowing Receipts £m £m £m £m £m Original Capital 6.943 0.100 - 1.784 5.059 Programme 2008/09 Slippage and Adjustments (1.300) 0.024 - - (1.324) from the 2007/08 Outturn report Monitor 1 Slippage and (0.254) (0. 020) 0.012 (0.255) 0.009 Adjustments
Current Approved Capital 5.389 0.104 0.012 1.529 3.744 Programme 2008/09 Consultation
3 The capital programme has been developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local councillors and residents in the locality of the individual schemes.
Scheme Specific Analysis
4 Each major scheme in the capital programme has been reviewed to provide an assessment of its current status. Annex A shows the current approved capital programme and the projected outturn position for 2008/09, together with any slippage that is required into future financial years. Updates are only provided for significant schemes, with progress and variations explained in the following paragraphs.
York Pools and Indoor Sports Provision (£6.567m) 5 Work continues on building the new pool on the York High site. Whilst the work on the new York High School comes to completion in December 2008 in order for occupation in January 2009, there is a requirement for some external work to be carried out in the school scheme which cannot be carried out until the pool and associated work is completed. It is therefore proposed to transfer £118k of external work from the school scheme into the pool scheme in 2009/10 so that this work can be carried out in conjunction with the final works on the pool.
6 The latest schedule of works show that the value of completed work and associated fees for 2008/09 will be £2.753m. It is therefore proposed to slip £1.700m into 2009/10.
Museum Service Heritage Lottery Bid (£1.900m) 7 There is an amount of £400k in the programme for 2008/09 to support three specific elements under the rolling programme of investment in the Museums Trust. Of this £400k, an amount of £200k has already been paid to the Trust to support work at the Art Gallery. A further £100k has been paid for work at the Castle Museum. The remaining £100k is set aside to fund work at the Yorkshire Museum. The release of this funding is dependent on plans for the Cultural Quarter.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.