Neighbourhood Services Capital Programme - Monitor 2
ApprovedCommittee1 paper
Neighbourhood Services and Advisory Panel approved this item on Thursday 4 December 2008. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: (a) Approve the 2008/09 revised budget of £0.619m as set out in table 2. (b) Approve the net slippage of £0.325m into future years. (c ) Approve an additional £15,000 in respect of the Air Quality grant provided by DEFRA which was approved by the Executive Member for Neighbourhood Services and Advisory Panel on 4 September 2008. The revised Capital Programme would therefore be £634,000 Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Neighbourhood Services and Advisory Panel
Meeting of the Executive Member for 4th December 2008 Neighbourhood Services and Advisory Panel
Report of the Director of Neighbourhood Services
NEIGHBOURHOOD SERVICES CAPITAL PROGRAMME MONITOR 2 Summary 1. The purpose of this report is to:
• Inform Members of the likely outturn position of the 2008/09 Capital Programme based on the spend profile and information to October 2008/2009;
• To seek approval to any resulting changes to the programme;
• Inform Members of any slippage and seek approval for the associated funding to be slipped between the relevant financial years to reflect this.
Background 2. The 2008/09 – 2010/11 capital programme was approved by Council on 21st February 2008. Since then a number of amendments have taken place as reported to Executive Members in the 2007/08 Capital Outturn report. These changes have resulted in a current approved capital programme for 2008/09 of £0.944m, financed by £0.414m of external funding, leaving a cost to the Council of £0.530m. Table 1 illustrates the movements from the original budget to the currently approved position.
Gross Budget External Capital Receipts £m Funding* £m £m
Original Budget 0.370 0 0.370 Approved by Council at 21 Feb 2008 Additions to 08/09 0.172 0.015 0.157 from 07/08 outturn report Re-profiling to 0 0 0 09/10 & 10/11 from 07/08 outturn report Additions / 0.402 0.399 0.003 Reductions
Current Approved 0.944 0.414 0.530 Capital Programme
*External funding refers government grants, non government grants, other contributions, developers contributions and supported capital expenditure. Table 1 Current Approved Capital Programme
3. The capital receipts column above implies receipts generated from the sale of Council assets will be used to fund the difference between the gross budget less all other specified funding sources. Due to the current economic climate not being favourable to achieving maximum receipt value from asset disposals, consideration will be given to the use of prudential borrowing to fund the capital programme as a temporary measure. When the economic climate returns to a more favourable state assets will be sold with the receipts being applied to finance the programme thus replacing the temporary borrowing.
Consultation 4. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 5. Against the current approved budget of £0.944m, there is a predicted outturn of £0.619m, a net decrease of £0.325m.
6. The net decrease is comprised of: • Re-profiling current year budget into future years of £325k
7. Table 2 highlights scheme specific information:
Gross Neighbourhood 2008/09 2009/10 2010/11 Total Para Services Capital Ref Programme £m £m £m £m Current Approved Capital 0.944 0.361 0.133 1.438 Programme Re-profiling: Silver Street Toilets (0.075) 0.075 0 0 15 Waste Infrastructure (0.250) 0.250 0 0 18
Revised Capital 0.619 0.686 0.133 1.438 Programme
Table 2 Capital Programme Forecast Outturn 2008/09 – 2010/11
8. The main highlights of this report are:
• Slippage of £75k in to 2009/10 on the Silver Street Toilet Scheme • Slippage of £250k into 2009/10 on the Waste Infrastructure Capital Grant • All other schemes are expected to complete on target
9. The total budget of £172k was carried forward from 2007/08. There is no new capital funding in 2008/09 as it was agreed that all ward committee schemes will be funded from revenue.
10. All schemes are expected to complete on target.
Annual Highway Maintenance ReportAdvice of the Advisory Panel That the Executive Member be advised to: (i) note the performance and success in 2008/09...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.