Young People's Services: Service Asset Management Plan
DeferredCommittee2 papers
Children and Young People's Services and Advisory Panel deferred this item on Thursday 12 March 2009. Below is the council's own wording, with the papers it was decided on.
That this item be deferred. REASONS: (i) The plan was to be updated in the light of current discussions around the Myplace bid. (ii) The Plan was to be broadened to consider the wider assets for which the department and partners were responsible.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Meeting of the Executive Member for Children 12 March 2009 and Young People’s Services and Advisory Panel
Report of the Corporate Landlord
Young People’s Services: Service Asset Management Plan
Purpose of Report 1 This report seeks the Executive Member’s approval to the proposed Young People’s Services Service Asset Management Plan (SAMP). The SAMP is attached at Annex A.
Background 2 Service Asset Management Plans are one of the documents which Property Services use to deliver the principles of Asset Management Planning across the council.
3 The revised Corporate Asset Management Plan was approved by the Executive in July 2007. This is the strategic document which uses Asset Management Planning principles to set the framework for the council’s ownership and use of buildings and land to deliver the council vision and corporate aims.
4 This strategy needs to be translated to a service level so that the property which any service occupies enables that service to deliver its aims and vision in the best possible way, meeting the needs and expectations of customers and staff.
5 Extensive work had recently been done in looking at the future for Young People’s Services in York as a result of:-
• The merger of Connexions and the Youth Service to form Young People’s Services.
• The need to accommodate a new central team of up to 15 staff and to identify hot desking capacity at the three locality hubs: Fulford, Moor Lane and Kingswater.
6 Young People’s Services were therefore keen to produce a Service Asset Management Plan so they could translate the findings of their reviews into ensuring that:-
• The property needs of the service to deliver its “vision” could be identified. • The current portfolio of Youth Centre buildings could be analysed and audited against the identified needs.
• Options and priorities to close the gap between future needs and current provision could be appraised.
• A way forward that would deliver the changes needed to meet the services property needs taking into account cost, funding streams and opportunities.
Consultation 7 A SAMP can only be produced if it is a result of joint working between Property Services and the relevant council service.
8 A number of meetings and discussions have taken place between, officers from Young People’s Services and Asset and Property Management, and other staff. In particular this consultation has included:-
• Analysis of key Young People’s Services documents which are also a result of extensive consultation with key stakeholders including the public.
• Meeting with the Head of Young People’s Services and other key officers.
• Involvement of Youth Centre managers on the suitability of the buildings to deliver the service.
• Discussion with other council services and non-council building owners on the range of options for the location of future space through the Corporate Asset Management Group.
9 The SAMP has been produced jointly between Young People’s and Property Services.
10 The plan has been approved by the Corporate Asset Management Group.
Young People’s Services Asset Management Plan 11 Annex A contains the final draft of this SAMP for approval by Members. There are a number of annexes to the SAMP and these will be available at the meeting together with other background information.
12 The SAMP is set out in the following sections:-
1. Introduction
Brief explanation of the purpose and advantages of the SAMP.
2. Vision
This section contains the vision for Young People’s Services following the merger of Connexions and Youth Service that has taken place and sets out the aims and objectives of the service. It also highlights 4 key property areas which will need to be taken into account.
• Accessibility • Location
• Delivery
• Cost
3. Audit
Analysis of the current portfolio in meeting the current and future needs of the service are detailed in this section, in particular looking at
• Running Costs
• Outstanding Repairs
• Accessibility
• Suitability
• Property and Service PI’s
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
Service Plan and Budget Monitor 3Advice of the Advisory Panel (i) That the Executive Member be advised to note the performance of services within the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.