Advice of the Advisory Panel That the Executive Member be advised: (i) That the capital programme forecast outturn for 2008/09, as shown in Annex A, be noted. (ii) That the additions and amendments to the capital programme, detailed in the report and summarised in Annex A, be approved. (iii) That the scheme reprofiling and slippage detailed in the report and summarised in Annex A be approved. (iv) That the scheme virements detailed in the report be approved, subject to the approval of the Executive. (v) That the revised capital programme, as shown at Annex A of the report, be agreed, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Summary
1 This report is to: • inform Members of the likely out-turn position of the 2008/09 Capital Programme. • advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme • inform Members of any slippage in budgets between financial years • inform Members of any new schemes and seek approval for their addition to the 2008/11 Capital Programme.
Background
2 The original capital programme for the financial year 2008/09 was approved at Council on 21 February 2008. Since then, a number of amendments to the programme have been approved as part of the 2007/08 out-turn report and the Monitor 1 and Monitor 2 reports. This results in a current approved Children’s Services capital programme for 2008/09 which shows gross capital expenditure of £33.145m with £26.910m of other funding which gives a net capital programme cost to the authority of £6.235m to be funded from capital receipts.
3 Table 1 details the approved changes to the 2008/09 capital programme since the original programme was approved in February 2008. Table 1- Current Approved Children’s Services Capital Programme 2008/09
Gross External Section Prudential Capital Spend Funding 106 Borrowing Receipts £m £m £m £m £m Original Capital Programme 45.103 37.322 0.337 1.641 5.803 2008/09 Slippage and Adjustments from (11.756) (12.016) 0.228 (0.400) 0.432 the 2007/08 Outturn report Monitor 1 Slippage and (0.130) (0.130) - - - Adjustments Monitor 2 Slippage and (0.072) (0.072) - - - Adjustments
Current Approved Capital 33.145 25.104 0.565 1.241 6.235 Programme 2008/09
Consultation
4 The capital programme has been developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local councillors and residents in the locality of the individual schemes.
Scheme Specific Updates
Devolved Formula Capital (Scheme Cost £18.385m) 5 This scheme represents the devolved capital which has been allocated to schools in 2008/09, net of any contributions which the schools have agreed towards LA led schemes elsewhere in the programme.
Fulford Secondary Targeted Capital (Scheme Cost £3.489m) 6 As reported at Monitor 2, the final payment on Phase 1 of this scheme has now been settled.
Huntington Secondary (Scheme Cost £5.674m) 7 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. The final retention has not yet been settled, but is expected to be within the remaining budget. However, it is now unlikely that this retention will be settled in 2008/09 therefore it is proposed to slip the unspent remainder of the budget (£100k) into 2009/10.
Integrated Children’s Centres (Overall Scheme Cost (£4.871m) 8 The five new Phase 2 Children’s Centres are now complete with only minor issues to resolve and retentions outstanding.
9 Knavesmire has now been identified as the site for the ninth Children’s Centre. In addition, some additional investment at Scarcroft Primary and St Clements Hall is also proposed to enable their use as outreach facilities. NDS Modernisation (Scheme Cost £17.053m) 10 This scheme addresses condition and suitability issues at a number of schools in the city. In order to maximise the resources available schools were invited to bid for this funding and encouraged to contribute their devolved capital to projects.
11 The most significant scheme within NDS Modernisation which is currently in progress is the Poppleton Road Primary Access works. Phase 1 and Phase 2 are now complete with only minor outstanding issues and retentions to be paid.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.