Advice of the Advisory Panel That the Executive Member for City Strategy be advised to: (i) Note the contents of the report and its annexes; (ii) Agree the revised proposals for the section of corridor between Hospital Fields Road and the property boundary of 193 Fulford Road and 3 Main Street, as shown on Annexes A1 to A3; (iii) Agree the proposed off-road shared-use pedestrian and pedal cycle facility on the eastern side between Hospital Fields Road and Heslington Lane; (iv) Defer a decision on the on-road improvements shown on Annex A4; (v) Note that no objections were received to the proposed bus lane on a section of Selby Road and agree to the scheme as shown on Annex B2. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City Strategy 16 March 2009 and Advisory Panel Report of the Director of City Strategy
A19 FULFORD ROAD CORRIDOR UPDATE
Summary 1. The purpose of this report is to advise members of progress developing the proposals to improve the section of corridor between Hospital Fields Road and Heslington Lane and to provide a Bus Lane on part of Selby Road. The report summarises comments received when further consultation on these improvement schemes was carried out and the associated traffic orders advertised. It makes recommendations on how to progress these schemes and seeks approval to those recommendations.
Background 2. At the meeting on 29th October 2007, members considered a report outlining the results of a multi-modal transport feasibility study of the A19 Fulford Road corridor, covering the length from Skeldergate Bridge and Tower Street in the north to the Designer Outlet (just south of the A19 / A64 interchange) in the south together with the associated feeder roads.
3. That report noted that the corridor was already congested at peak periods and that air pollution in Main Street, Fulford has been monitored as breaching health based air quality objectives. Without intervention there would be a significant worsening of conditions and a need to declare a further Air Quality Management Area (AQMA). Members agreed that the package of improvement measures proposed in the report should form the basis of the improvement strategy for the corridor and be taken forward for public consultation.
4. Subsequently a wide-scale public consultation was carried out on this package of measures. There was good support for the main principles of the improvement strategy with strong support for some of the proposed measures. The responses indicated that the proposed improvements would be likely to encourage walking, cycling and use of public transport along the corridor. The consultation identified some areas of concern where the proposals would need to be reviewed and possibly revised as they are developed.
5. At the meeting on 17th March 2008, members considered a report summarising the results of the consultation and reviewing the proposals for the corridor in the light of those results. Members agreed the recommendations on how to progress the proposed improvement measures, taking account of the consultation findings.
6. At the meeting on 8th December 2008, members considered a report advising of progress developing the improvement proposals. Members agreed that priority should be to improve the corridor between Cemetery Road and Heslington Lane where pedestrians, cyclists and public transport users would all benefit from the proposed improvements. Members agreed to revised proposals for the section of corridor between Cemetery Road and Hospital Fields Road; the proposed pedestrian refuge island crossing on Main Street Fulford; and the proposed extensions of the 30mph zone and associated gateway treatments and improvement measures at Naburn.
7. Members also agreed to an inbound bus lane on Selby Road heading north from the A64 interchange for approximately 200m, subject to consultation and advertising of the appropriate Traffic Order, and that any proposed bus lanes on the corridor should be 24 hour operation similar to other existing bus lanes in York. In addition they agreed that further investigation of other proposals south of Germany Beck be deferred until potential funding to implement those improvements could be identified.
Hospital Fields Road to Heslington Lane 8. The initial proposals for this section of corridor have been reviewed, further traffic monitoring and modelling work has been carried out, and a revised scheme developed for consultation as described below and shown on plans at Annexes A1 to A4.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.