(i) That the progress made in implementing internal and external audit recommendations, as reported in paragraphs 4-15 of the report, be noted. REASON: In accordance with the Committee’s role in providing independent assurance on the Council’s control environment. (ii) That the process for monitoring and reporting on on-going progress in implementing the Audit Commission’s recommendations, as set out in paragraph 15, be approved. 1 REASON: To ensure that a consistent approach is adopted to monitoring and reporting progress on the implementation of external audit recommendations.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director of Resources (Customer Service and Governance)
Follow Up of Audit Recommendations
Summary 1. This report sets out the progress made by the council in implementing agreed internal audit recommendations. It also summarises the progress made to address recommendations raised by the external auditor.
Background 2. Internal audit reviews the implementation of agreed recommendations on an ongoing basis, once target implementation dates for recommendations become due. A summary of the outcome from this work is reported to this committee every six months together with details of any outstanding recommendations that require referral to the committee for consideration. This report covers recommendations with target dates up to 28 February 2009.
3. In addition, following a request by this committee in September 2008, a review of progress made to implement recommendations raised by the external auditor has also been carried out. An overview of progress was reported to the committee in January 2009. The current report contains further details about the findings of the follow up review, which is summarised below. For the future it is intended that this work will be carried out on an ongoing basis and the results included as part of the regular six monthly follow up report.
Follow Up of Internal Audit Recommendations 4. All internal audit recommendations are reviewed once their agreed implementation date has passed. The review is carried out using a combination of questionnaires completed by departments, risk assessment, and further detailed review by internal audit where appropriate.
5. A total of 133 recommendations were followed up as part of this review. A summary of the priority of these recommendations is included in figure 1, below. Figure 1: Recommendations followed up as part of the current review Priority of No. of Recommendations 1 Recommendations Followed Up 1 4 2 62 3 67 Total 133 1 The priorities run from 1 (high risk issue) to 3 (lower risk)
6. Figure 2 below provides an analysis of the recommendations which have been followed up, by directorate.
Figure 2: Recommendations followed up by directorate No. of Recommendations Followed Up by Directorate Priority of Chief City HASS LCCS Resources N’hood Recommendations Executives Strategy Services 1 0 2 1 0 0 1 2 9 7 4 26 15 1 3 7 2 5 30 21 2 Total 16 11 10 56 36 4
7. Of the 133 recommendations, 2 (1.5%) had been superseded (for example by business developments or because of cessation of service). Of the remaining recommendations, 102 (76.7%) had been satisfactorily implemented.
8. In one case (0.8%) the recommendation had not been implemented fully although some progress had been made. This issue is being followed up in detail as part of the current annual audit of the service area.
9. In a further 25 cases (18.8%) the recommendations had not been implemented, however, satisfactory explanations for the delays in implementation have been received (for example unexpected difficulties or issues dependent on new systems being introduced). In these cases a revised implementation deadline has been agreed. The issues will be followed up again after the revised deadline and will be escalated if unsatisfactory progress is found to have been made.
10. In three cases (2.3%) the reasons given for not progressing the recommendation were considered unsatisfactory, and these issues are now being escalated1. None of these recommendations is yet at the stage for referral to the Audit & Governance Committee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.