(i) That the contents of the report and the progress made during 2008/09 be noted. REASON: To be aware of progress made to date in respect of the risk management agenda and framework at the Council. (ii) That the evidence presented for management of the risks relating to child protection and the Waste PFI project be noted. (iii) That a further detailed risk report on the Administration Accommodation Project be provided to the Committee’s meeting in June 2009. 1 REASON: To ensure that key risks are being appropriately managed by the organisation.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director of Resources (Customer Service & Governance)
Risk Management Monitor Quarter 4 2008/09 Overview 1. This paper presents to members the corporate risk management monitor (Annex A) for the fourth quarter 2008/09. The risk monitor is reviewed by Council Management Team (CMT) on a quarterly basis and this report provides the opportunity for members to raise any questions or concerns they may have in relation to the risks contained within the monitor.
Background 2. At Audit & Governance Committee (A&G) on 24 September 2008 members approved recommendation b) of the Risk Management Mid- Term monitoring report to receive the corporate risk monitor on a quarterly basis. The purpose of this is to allow A&G members to make a judgement and gain assurance on how risks are being managed across the organisation.
3. Effective Risk Management is important to the council as it acts as an enabler by supporting well informed decision making and it can facilitate sustainable improvements in service delivery. It is fundamental to good management practice and should not be viewed as a separate discipline or be carried out in isolation.
Current Issues 4 The current economic downturn continues to make the headlines and since the last monitor to A&G in January the team have been coordinating an exercise aimed at identifying any associated risks and issues to the council. This work was requested by Executive in October 2008 and a detailed report on the risks and issues identified will be presented to Executive in April 2009. The work to complete this task is still ongoing and the outcomes will be reported to A&G as part of the 2008/09 outturn report in June 2009.
5 At A&G in January one of the topical risk issues highlighted was in relation to child protection following the death of Baby P in Haringey. The Quarter 3 report set out that ‘the overall performance for Children’s Services in York has been judged as outstanding.(Joint Area review 2008; Annual Performance Assessment 2008)’. The joint area review indicated that the risk at York seemed to be low but in the light of new more stringent regulations being introduced by government and the inherent risks of child protection A&G asked for some assurance that risks were being actively managed. Annex B to this report provides an extract from the relevant department’s risk register to assure A&G members that the risks are being well managed.
Quarter 4 Risk Monitor 6 The risk monitor at Annex A of this report sets out the position of the key corporate risks (KCRs) at the end of the fourth quarter 2008/09. The monitor is complete in terms of accurately reflecting the information recorded in the Council’s risk register (Magique) however, risk owners in some cases still need to consider describing their risks in more detail clearly setting out both existing controls and additional actions required to better manage them.
7 A&G commented in January that some of the risks seemed to be out of date and that risk control actions had passed beyond due dates without becoming formal controls. The current monitor attached at Annex A reflects the work undertaken by officers to update their risks. There is limited resource within risk management (1 FTE) to coordinate this work across the council as a whole and some risk control actions still remain out of date however these are now in the minority.
8 While A&G will need to review the monitor (Annex A) in full they may wish to consider in more detail the critical (red) risks, these include the following:
KCR 0001 Implementation of the new pay & grading structure
• Neighbourhood Services risk 9 (Legal Challenge)
KCR 0002 Unsuccessful delivery of accommodation review project
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.