Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 22 September 2009. Below is the council's own wording, with the papers it was decided on.
(i) That the progress made on the Cycling City York programme be noted and that the aims and achievements of the programme continue to be supported. (ii) That a further update report be received in March 2010, at the end of the second year. REASON: To ensure that the programme stays on track and delivers the measures necessary to increase levels of cycling, and to ensure that funding is allocated to schemes most likely to deliver the programme’s aim and thus strengthen the case for future years’ funding and the benefits that brings, including reducing congestion and air pollution and having a healthy population. (i) That the progress made on the Cycling City York programme be noted and that the aims and achievements of the programme continue to be supported. (ii) That a further update report be received in March 2010, at the end of the second year. 1 REASON: To ensure that the programme stays on track and delivers the measures necessary to increase levels of cycling, and to ensure that funding is allocated to schemes most likely to deliver the programme’s aim and thus strengthen the case for future years’ funding and the benefits that brings, including reducing congestion and air pollution and having a healthy population.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 22 September 2009
Report of the Director of City Strategy
CYCLING CITY PROGRAMME - PROGRESS REPORT 2 Summary 1. This is the second report to update Members on the progress of the Cycling City Programme, which provides Members with an update of the various works of the programme over the last 6 months and highlights a number of successes so far.
Background 2. The previous report highlighted the significant amount of work undertaken leading up to the end of the last financial year which resulted in York being the only city to submit and claim all the funding allocated to it, spending a total of £535K. Main schemes completed included the Clifton Bridge Scheme and a number of margin works from the capital programme and various others from the programme’s revenue side as previously reported. This has created a good start for the programme, which has received very positive feedback from Cycling England (CE) and is something the project will strive to maintain.
Strategy 3. Following the citywide consultation to better understand the barriers preventing residents cycling we have identified key concerns and priorities as well as the locations perceived as most dangerous for cyclists. The results have been used to steer and prioritise the programme, and been communicated to both stakeholders and the public. See annex B for a summary of the survey results, which was distributed to all residents in the spring.
4. To summarise the strategy and the programme, the aim is to encourage more people to cycle. The programme has been focused and prioritised accordingly: -
1) Revenue, this includes marketing, events, communications, and work to encourage an uptake in cycling including two main areas, schools and places of work. 2) Improvements to existing cycling infrastructure, such as signs and margin works.
3) New cycling infrastructure, for example the Clifton Bridge and Beckfield Lane schemes.
5. The target audience for this programme are new and lapsed cyclists, meaning those who haven’t cycled for a number of years. This may be for reasons of lack of confidence or lack of awareness of the benefits of cycling, or because they don’t know there is a cycle track near their home.
6. Whilst it is not possible to predict with any certainty the outcomes of the programme, a benefits index, cost-benefit database and design standards have been developed for the Council, which will be presented at Decision session for City Strategy in October. This will give Members and officers a greater degree of certainty regarding any cycle capital scheme identifying more clearly the cost and benefits of it. Due to the layout of the city, such as its narrow streets, there was a need to develop our own standards as well as take on board those from CE and DfT to make sure we have consistent standards across York for Cycle infrastructure. This will agree and give consistent design standards guidance to reflect a York standard along with a cost benefits index to show we are getting good value for money). The document includes what can be done for the narrow roads in York such as Lendal Bridge and Gillygate. This will be made public once agreed at Member level and provided to all departments and contractors, including consultants to ensure consistency across York for its cycle infrastructure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.