Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 16 March 2010. Below is the council's own wording, with the papers it was decided on.
(i) That the progress made on the Cycling City York programme be noted and that the programme’s aims and achievements continue to be supported. (ii) That a further update report be received in September. REASON: To ensure that the programme stays on track and delivers the measures necessary to increase levels of cycling and ensure that funding is allocated to schemes most likely to deliver the programme’s aim and further strengthen the case for future years’ funding. (iii) that Officers be requested to arrange a survey of public opinion, on the conclusion of the present Cycling City programme, aimed at assessing both the success of the new cycling facilities that have been provided and any changes to public attitudes on the use of cycles as a means of transport in the City. REASON: In order to gauge the effect of the programme to date. (i) That the progress made on the Cycling City York programme be noted and that the programme’s aims and achievements continue to be supported. (ii) That a further update report be received in September. 1 REASON: To ensure that the programme stays on track and delivers the measures necessary to increase levels of cycling and ensure that funding is allocated to schemes most likely to deliver the programme’s aim and further strengthen the case for future years’ funding. (iii) That Officers be requested to arrange a survey of public opinion, on the conclusion of the present Cycling City programme, aimed at assessing both the success of the new cycling facilities that have been provided and any changes to public attitudes on the use of cycles as a means of transport in the City. 2 REASON: In order to gauge the effect of the programme to date.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 16 March 2010
Report of the Director of City Strategy
CYCLING CITY PROGRAMME - PROGRESS REPORT 3 Summary 1. This is the third report to update Members on the progress of the Cycling City York (CCY) Programme, highlighting works in the programme over the last 6 months and the number of successes so far. This report also includes the proposals for 2010/2011 revenue arm of the programme (see Annex A).
Background 2. The overall aim of the programme is to encourage more people to cycle. The funding of £3.68m from Cycling England (CE) is match-funded by City of York Council (CYC) and this is broken down into two main streams of work, capital and revenue. Further information on this project can be seen in the reports listed in the background information at the end of this report.
3. We continue to be considered positively by CE who has been recommending other Local Authorities and Cycling Towns to contact York for advice. As a result a number of presentations and interviews have been given at various events on the York programme including the Centre for Public Policy Seminars, CTC award ceremony, TravelWise Smarter Choices conference and a regional business forum.
Strategy 4. Over the last year the programme has been shaped into what we will be delivering this next financial year, this has been achieved through feedback from the citywide questionnaire in December 2008, stakeholders and the public. See previous CCY progress reports for further information and Annex A for the 2010/11 revenue programme.
5. The Monitoring Project (the installation of cycling monitoring equipment to monitor cycling levels across the city) has completed the installation of over 30 Automatic Cycle Counters (ACC’s) and validation work is being finalised to make sure the data is accurate. This will be complimented by the quarterly counts undertaken by CYC. This project area will also be complimented by the CE monitoring and evaluation work to be done in the spring that will provide us very useful information on progress. The
Version 3.0 intervention diary (a record of events such as poor weather, road closures etc) will aid our understanding of peaks and troughs in the monitoring data.
Update on the programme Programme structure and updates
6. The second stakeholder meeting was held in October, and was combined into a Cycle Forum chaired by the York Cycle Campaign. Approximately 80 people attended from varying backgrounds all of whom contributed and provided positive feedback on the programme to the main theme of how to encourage more people to cycle. The CCY Steering Group will continue to help steer next year’s meetings including any future cycle forums.
Revenue 7. A call-off contract has been prepared with up to three suppliers is expected to be in place by mid-March allowing better delivery of the revenue element. This has gone through a CYC Procurement process and will allow Project Leaders to outsource more of this work, where appropriate, to assist with timely delivery of events, campaigns and so forth.
Events
8. Since the last report there has only been one event mainly due to the season, however the first Christmas cycle ride in York to Murton Christmas Park, proved very successful with approximately 40 people participating.
Marketing and Communications
9. This key area of the programme has been going very well and on schedule with at least one media release going out per week. There has been ongoing positive interest by the media with much pro-active engagement with CCY. This is ensuring the objective of proactive, consistent and positive approach to marketing the programme.
10. Procurement of service to develop the CCY website has been completed which will provide a one-stop-shop to all things cycling in York. The Facebook page we have developed is seeing a steady increase in its viewers and will compliment website. You are invited to view this and become a 'friend' http://www.facebook.com/group.php?gid=168751003949&ref=ts
Schools Group
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.