That the Executive Member agrees to: · Approve the further development of the outline layout of the upgraded roundabout as indicated in Option B to address the road safety audit requirements and meet the concerns of local residents and users of the highway in the area, · Approve the proposed public consultation strategy on the outline layouts as detailed in the consultation section the consultation area to be agreed with the Ward Members, · Approve the progression of the detailed design of the proposal incorporating amendments to address the comments raised during the public consultation period (including the justification for a refuge on the A1237 east leg junction and a review of the options for continuing to provide a westbound lay-by on the A1237) and to allow a further report to the Executive Member to be submitted early in 2010 prior to tendering the scheme. · Authorise the removal of the minimum amount of vegetation from the environmental bund at an appropriate period in the year, in advance of the main contract if necessary, to allow the works to proceed without affecting nesting birds. REASON: To progress this upgrade scheme in accordance with the Local Transport Plan to increase the capacity of the roundabout and reduce journey times in the area.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Summary 1. This report sets out options for the outline design for the proposed improvements to the A19/A1237 roundabout to reduce delays at this location. The report also identifies the estimated cost, programme and consultation proposals to enable the scheme to be delivered in 2010/11.
Recommendations 2. The Executive Member is recommended to:
• Approve the further development of the outline layout of the upgraded roundabout as indicated in Option B to address the road safety audit requirements and meet the concerns of local residents and users of the highway in the area,
• Approve the proposed public consultation strategy on the outline layouts as detailed in the consultation section,
• Approve the progression of the detailed design of the proposal incorporating amendments to address the comments raised during the public consultation period and to allow a further report to the Executive Member to be submitted early in 2010 prior to tendering the scheme.
• Authorise the removal of the minimum amount of vegetation from the environmental bund at an appropriate period in the year, in advance of the main contract if necessary, to allow the works to proceed without affecting nesting birds.
Reason: To progress this upgrade scheme in accordance with the Local Transport Plan to increase the capacity of the roundabout and reduce journey times in the area.
Background Overview 3. The Executive Member approved the delivery of improvements to the A19/A1237 roundabout using the additional funding from the Regional Funding Allocation at the 21 July 2009 City Strategy Decision Session. 4. The A19/A1237 roundabout was originally constructed in the late 1980s with the remainder of the A1237 outer ring road. A major upgrade increasing the size of the roundabout and adding the Rawcliffe Bar Park & Ride access and subway was completed in 2001. Daily traffic numbers approaching the roundabout from the south west have increased by approximately 8% since 2002 to nearly 17,000 with maximum am and pm peak hour flows increased to approximately 1300 vehicles per hour. Morning flows have increased by approximately 10% whilst afternoon and evening flows have increased by nearly 30% since 2002.
5. The section of the ring road over the river Ouse is the busiest link of the entire route with a two way flow of 33,000 vehicles per day (am peak hour 2,600, pm peak 2,500). Delays at the A19/A1237 roundabout are exacerbated by the high crossing/joining movements from the A19 from the north and south. There are substantial delays on all main arms of the roundabout with the delays on the A1237 eastbound in the am peak and westbound in the pm peak particularly severe. In the evening peak westbound tail backs over the bridge from the A59 and Millfield Lane roundabout direction extend as far as the A19 preventing the free flow of traffic leaving the A19 roundabout.
6. The level of queuing on the Outer Ring Road encourages travellers to use alternative routes through the adjacent residential areas to avoid delays at the A19/A1237 roundabout. Traffic modelling predicts that the level of delays at the roundabout and number of trips through adjacent areas will increase in future years.
7. The following tables indicate the projected level of queuing and journey times from adjacent roundabouts on the A1237 and points a few hundred metres from the roundabout on the A19. Note: the 2026 projections assume that the developments proposed to meet the Regional Spatial Strategy allocations have progressed (inc. York Northwest), schemes included in the Access York Phase 1 project (3 P&R sites and A59 roundabout upgrade) have been implemented and the York Business Park roundabout has been upgraded.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.