A19/A1237 Roundabout Improvements - Consultation Results and Detailed Design
AgreedExecutive5 papers
Decision Session - Executive Member for City Strategy agreed this item on Tuesday 2 February 2010. Below is the council's own wording, with the papers it was decided on.
That the Executive Member agrees to: i) Note the comments raised by the public, Councillors and interested organisations. ii) Note the Officer’s response to the comments and the proposed amendments to the design. iii) Approve the further development of the scheme in line with the amended layout subject to the removal of the rumble strips on Shipton Road, as part of the necessary resurfacing works, to enable the improvements to be tendered and constructed in the summer/autumn of 2010. iv) Approve the inclusion of a total allocation of £1.5m in the City Strategy Capital Programme to construct the proposed scheme. v) Authorise the removal of the minimum amount of vegetation from the A1237 West landscaped bund in February, to allow the main works to proceed later in the year to minimise the impact on nesting birds. REASON: To reduce journey times for travellers in the A19/A1237 area whilst maintaining safe crossing points for pedestrians and cyclists. That the Executive Member agrees to: i) Note the comments raised by the public, Councillors and interested organisations. ii) Note the Officer’s response to the comments and the proposed amendments to the design. iii) Approve the further development of the scheme in line with the amended layout subject to the removal of the rumble strips on Shipton Road, as part of the necessary resurfacing works, to enable the improvements to be tendered and constructed in the summer/autumn of 2010. 1. ... view the full minutes text for item 81.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session – Executive Member for City 2 February 2010 Strategy
Report of the Director of City Strategy
A19/A1237 Roundabout Improvements – Consultation Results and Detailed Design
Summary 1. This report provides the results of the consultation undertaken on the proposed improvements to the A19/A1237 roundabout. It also updates the Executive Member on the changes which have been made to address the comments and accommodate constraints identified during the design period. The report identifies that, subject to approval, the amended scheme can be constructed within a revised budget allocation in the summer/autumn of this year.
Recommendations 2. The Executive Member is recommended to:
• Note the comments raised by the public, Councillors and interested organisations.
• Note the Officer’s response to the comments and the proposed amendments to the design.
• Approve the further development of the scheme in line with the amended layout to enable the improvements to be tendered and constructed in the summer/autumn of 2010.
• Approve the inclusion of a total allocation of £1.5m in the City Strategy Capital Programme to construct the proposed scheme.
• Authorise the removal of the minimum amount of vegetation from the A1237 West landscaped bund in February, to allow the main works to proceed later in the year to minimise the impact on nesting birds.
Reason: To reduce journey times for travellers in the A19/A1237 area whilst maintaining safe crossing points for pedestrians and cyclists. Background Overview 3. The 2008 Outer Ring Road study confirmed that travellers on the A19 to A59 section of the A1237 Outer Ring Road experience some of the worst journey delays on the entire route. The upgrade of the A59 roundabout is included in the Access York Phase 1 scheme planned for delivery in 2011/12 subject to DfT funding approval. The works proposed in this report will reduce journey times in the A19 area.
4. The Executive Member approved the delivery of improvements to the A19/A1237 roundabout using the additional funding from the Regional Funding Allocation at the 21 July 2009 City Strategy Decision Session.
5. The outline layout of the improvements was approved at the 20 October City Strategy Decision Session to enable the scheme to be put out for consultation.
Consultation 6. Following further preparatory work after the confirmation of the preferred option a consultation exercise was undertaken between 27 November and 18 December to ensure the views of the adjacent population, external stakeholders and users of the roundabout were identified to allow incorporation into the final design where possible. The consultation leaflet and layout drawings are included in Annex 1 and 2.
7. The consultation included the following elements:
• Distribution of a leaflet to all households in the Skelton, Clifton Without and Rawcliffe Ward area. (approx. 6,000) • Displays at Clifton Library, 9 St. Leonard’s Place and Rawcliffe Bar Park & Ride site. • A staffed exhibition at the Rawcliffe Bar Park & Ride site on 10 December (9:00 to 20:00) • Attendance at the Rawcliffe Parish Council Meeting on 14 December • Erection of road signs on the approaches to the roundabout. • City of York Council Website • Creation of an A19 Roundabout email address • Press Release • Internal Consultation with Council departments • External Consultation with interest groups and the Emergency services 8. The following responses were received:
Source Number Email 93 Clifton Library Display 4 9, St Leonards Place 3 Display Rawcliffe Bar P&R 4 Display Rawcliffe Bar Exhibition 4 (22 attendees) Letters 7 Telephone Calls 4
9. The responses included over 270 comments with approximately 30 unique items. A more detailed list of comments and officer responses is included in Annex 3. The items in order of number of times raised are listed in the following table.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.