Resolved
That the forecast outturn information report be noted. REASON: To update the Scrutiny Committee of the latest financial and performance position.
Economic Development and Transport Policy and Scrutiny Committee noted this item on Tuesday 8 December 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
That the forecast outturn information report be noted. REASON: To update the Scrutiny Committee of the latest financial and performance position.
1. This report provides details of the 2009/10 forecast outturn position for both finance and performance in City Strategy, Housing Services and Licensing and Regulation within Neighbourhood Services.
Analysis
Finance – forecast outturn overview General Fund 2. The current outturn position within the City Strategy Directorate is a projected overspend of £+239k (£+163k) on a total net budget of £7.8m, Housing General Fund has a projected overspend of £+52k (£nil) on a net budget of £1,407k, and Licensing and Regulation has a net saving of £- 16k (£nil) on a budget of £-21k. Service Plan Variations by service plan are shown below:
Net Projected Monitor 2 Monitor 1 Budget Outturn Variance Variance £'000 £'000 £’000 £'000 City Strategy Directorate City Development & Transport 3,638 3,702 +64 +175 Planning & Sust. Development 1,364 1,520 +156 +169 Resource & Business Management 94 165 +71 +69 Economic Development 2,717 2,715 -2 - Remedial Action Proposed -50 -50 -250 Total 7,813 8,052 +239 +163 HASS Directorate Housing General Fund 1,407 1,459 +52 0 Neighbourhoods Directorate Licensing & Regulation -21 -37 -16 0
Note: ‘+’ indicates an increase in expenditure or shortfall in income ‘-‘ indicates a reduction in expenditure or increase in income
3. Details of the main variations by service plan are detailed in the following paragraphs. City Development and Transport £+64k (£+175k)
4. Car Parking income is forecast to be £+133k below budget which is made up of £+61k short stay, £+53k standard stay, £+37k on-street offset by £-18k surplus on Respark and season tickets.
5. There is an underspend of £-90k on employee costs within Network Management where a number of posts were unfilled in the first part of the year and £-15k underspend on new Respark schemes. This is offset by £+40k shortfall in income from new highway schemes.
6. There has been additional costs of £+216k compared to budget in issuing bus tokens and bus pass reimbursements to operators. The North Yorkshire Concessionary Fare partnership will reduce costs by bringing in revised reimbursement rates on 1st December 2009. This is offset by £-220k savings in road safety, speed camera trial, park & ride operations and other staff savings within the service area.
Planning and Sustainable Development £+156k (£+169k)
7. The economic downturn has continued to have a significant impact income within the Planning Service. The planning income projected shortfall is £+500k, a 46% reduction in income on the previous year following a sharp reduction in major scheme applications. Income from building control is projected to be a further £+125k below budget but offset by £-15k staff savings. There is a further saving of £-14k from reduced activity in Land Charges.
8. The government is reviewing the distribution of Housing and Planning Delivery Grant for 2009/10 and 2010/11. The total 2008/09 distribution was £101m and this increases to £135m and £200m respectively. York would receive an additional -£440k in 2009/10 based on a similar proportion of funding.
Resource & Business Management £+71k (£+69k)
9. The primary reason for this projected overspend is the lower than expected dividend from Yorwaste (£+130k) due to reduced tonnages and reductions in recyclates prices. There is additional financial, technical and legal costs incurred on the Waste PFI project (£+56k) but this is offset by an underspend on staffing (£-44k) due to a staff vacancy. Elsewhere, there are (£-71k) staff savings within finance and performance and from the Director covering Chief Executive post.
Economic Development £-2k (£+0k)
10. Latest projections are that the net shortfall in market income of £+32k will be offset by £-34k savings due to a staff vacancy, reduced Key Cities contribution and a freeze on overheads. Remedial Action
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2009/10 Finance and Performance Monitor 2 ReportReport | 95 KB | DownloadRead as text |
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 May 2017 | MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... | Approved | Open |
| 10 May 2017 | Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... | Noted | Open |
| 10 May 2017 | Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. | Noted | Open |
| 10 May 2017 | Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... | Noted | Open |
| 10 May 2017 | Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.