Economic Development and Transport Policy and Scrutiny Committee approved this item on Tuesday 8 December 2009. Below is the council's own wording, with the papers it was decided on.
That the Committee: i) Approve the draft extended scope and timetable at paragraph 4 of the report subject to the addition of “and the policy implications of such actions, if any” after the word “layout” at the end of point (iii) 15.12.2009. ii) Note the work undertaken by the Task Group to date. REASON: In order to progress this review.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Economic Development and Transport Policy and Scrutiny Committee
Economic & City Development Overview & 8th December 2009 Scrutiny Committee
Interim Report of the Water End Task Group
Summary 1. The purpose of this report is to present Members of the Committee with a draft extended scope and timetable for the review. It also presents Members with background information and work undertaken by the Task Group to date.
Background 2. In coming to a decision to review this topic, the Economic & City Development Overview & Scrutiny Committee recognised certain key objectives and the following remit was agreed:
Aim
To determine the best solution for the problems local residents are experiencing and to look at what lessons can be learnt in order to inform the implementation of similar schemes within the city.
Key Objectives
i. To establish whether local concerns still exist in the light of the Executive Member’s decision1
ii. To explore whether further improvements can be made to address the current traffic issues
iii. From experience to date, identify those measures or actions that can be taken to assist in the smooth implementation of similar schemes in the city.
iv. To understand the context of the Land Compensation Act 1973 in relation to this CCfA
1 It was agreed at the last full meeting of the Committee that key objective (i) be put on hold until after the Executive Member for City Strategy had received his next report. The Task Group would concentrate on objectives ii, iii, & iv of this remit. Members of the entire Committee would be asked their views on the report going to the Executive Member. Consultation 3. To date, consultation has mainly taken place with relevant technical officers within the Council. There are plans to hold a public event in the future and this is detailed in the scope and timetable below.
Scope & Timetable for the Review 4. The Task Group met informally on 22nd October 2009 to draft the scope and timetable for the review. This is set out in the table below.
Key Possible Date Action Objective Attendees
22.10.2009 All Scoping & timetabling of Task Group & review scrutiny officer
18.11.2009 All Site visit at peak time Task Group, (approx 5pm) scrutiny officer & relevant technical officers
08.12.2009 All Approval of scoping & Full Committee timetabling of review
15.12.2009 i Ø For background Task Group, purposes – To receive scrutiny officer, previous reports on this relevant area, in particular the technical officers report to the Executive Member for City Strategy on 20th October 2008 (Water End – proposed improvements for cyclists)
Ø For Background purposes - To receive & understand the available technical reports/modelling data [including looking at ‘before’ & ‘after’ traffic survey data and any forecasts made to substantiate the case for the improved junction proposals]
Ø For background purposes - To receive & understand information on York’s cycling infrastructure, in particular the Orbital Cycle Route, the rationale of the scheme & how the works in the Water Lane area fit with this.
15.12.2009 Ii & iii Ø To receive & Task Group, understand a scrutiny officer & breakdown of the cost relevant technical of the works at Water officer(s) End/Clifton Green to date
Ø To receive information on & understand the possibility, viability & the cost of restoring the road to its original layout
15.12.2009 iv Ø To receive & Legal Services understand the context of the Land Compensation Act 1973 in relation to this CCfA
Ø To receive information on any relevant case- law precedents
TBC All Public Event Task Group, scrutiny officer, Ø To meet with local technical officers residents, cyclists & & members of other users of the the public roadway in this area to hear their views. [This event is likely to start with a short presentation given by the Chair of the Committee and/or the scrutiny officer to present the information found to date. There would then be time for the public to feed in their views – a time limit for each speaker may be set for this dependent on how many attendees there are]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.