Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 15 December 2009. Below is the council's own wording, with the papers it was decided on.
(i) That the demolition of the buildings at the former Lowfields site, and the funding of this work from the capital receipt resulting from the sale of the site, be approved. (ii) That approval be given to use the property services revenue budget, as required, to: a)fund the finance costs incurred as a result of the timing differences between the demolition costs being incurred and the capital receipt being realised or b) fund the demolition costs from the surplus property fund budget if the site is not sold. REASON: To eliminate a target for vandalism, arson and anti-social behaviour, resulting in savings on security and maintenance costs, a reduction in nuisance to local neighbours and a reduction in the drain on police and fire service resources. (i) That the demolition of the buildings at the former Lowfields site, and the funding of this work from the capital receipt resulting from the sale of the site, be approved. 1 (ii) That approval be given to use the property services revenue budget, as required, to: a)fund the finance costs incurred as a result of the timing differences between the demolition costs being incurred and the capital receipt being realised or b) fund the demolition costs from the surplus property fund budget if the site is not sold. 2 REASON: To eliminate a target for vandalism, arson and anti-social behaviour, resulting in savings on security and maintenance costs, a reduction in nuisance to local neighbours and a reduction in the drain on police and fire service resources.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Background
2. On 31st December 2008 York High School vacated the buildings at the Lowfields site on completion of the new York High School at Cornlands Road.
3. Following vacation the buildings were secured, services disconnected and security patrols put in place.
4. It had been originally intended that the site would be marketed for disposal as soon as the High School moved. However, with the economic downturn the best capital receipt would not have been achieved and therefore, the property remains in the ownership of the Council.
5. A development brief is currently being prepared by the City Development Team, which will be completed by April 2010, with a view to possibly marketing the property later in 2010/early 2011, to be sold in the 2010/11 financial year This will depend on market conditions at the time. The cost of demolition will potentially be recouped by way of increased capital receipt to reflect the fact that the property is a cleared site, and will also speed up the sale process.
6. Inevitably the buildings have become a target for vandalism and the buildings have been broken into on several occasions. This has including arson on two occasions, with resultant costs and inconvenience to the fire service and local residents, despite the security measures in place. 7. Clearly the only way to stop the problems associated with the site is to demolish the buildings, which are not suitable for any form of re-use.
8. Work has been going on now for several months to carry out all the necessary surveys and health and safety assessments prior to obtaining formal quotations for the demolition work. The tenders have now been obtained. This is set out later in the report.
9. Should the Executive approve the recommendations, work will start on site in January 2010 and the work is expected to take 12 weeks to complete.
Consultation
10. This report has been prepared in consultation with the Corporate Asset Management Group.
Options
11. Approve or reject the recommendations.
Analysis
12. Approve the recommendations
Advantages: a. The buildings can be demolished leaving a cleared site, which is no longer a target for vandalism. The demolition work will result in an increased capital receipt being received. b. Vastly reduced costs of security and maintenance, which will result in a saving that can be transferred to support the surplus property budget. c. A more attractive site for developers on disposal.
Disadvantages: a. The cost of the demolition work will ultimately be funded from the increased capital receipt received from the sale of the cleared site. However, any financing costs incurred as a result of the timing differences between the costs of the demolition and the capital receipt being received will be funded from property services revenue budgets. b. If the site is not sold then the demolition costs will need to be written off to revenue and funded from property services revenue budget.
13. Reject the recommendations
Advantages a. No need for prudential borrowing. b. No requirement for the surplus property budget to fund the demolition costs if the site is not sold.
Disadvantages a. The buildings continue to be a target for vandalism and arson. b. Ongoing costs of security and maintenance to be picked up by the surplus property fund. c. Continuing inconvenience and disturbance to local residents, the fire service and police.
Corporate Priorities
14. The successful delivery of this scheme will help to achieve a number of the themes of the Corporate Strategy 2009/10 including:
(a) Sustainable City – improve the local environment
(b) Safer City – reduced vandalism and anti-social behaviour
Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
Hear about the next one first
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.