(i) That the progress made on the More for York Programme be noted. (ii) That the work undertaken to date on identifying the Sustainability benefits from the programme be noted. (iii) That the Income Collection proposals set out in paragraphs 42-67 of the report be approved, in particular. · the proposal to introduce the Allpay facility · the closure of the cashiering function in the banking hall and · the provision of a residual cashiering facility at 9 St Leonard’s. (iv) That the production of an additional Blueprint for work on Children’s Social Care, as set out in paragraphs 69-73, be approved. (v) That the production of an additional Blueprint for work on Finance Performance and associated support, as set out in paragraphs 74-77, be approved. REASON: To help enable the Council to deliver service improvements and create efficiency savings of £15m over the next three years and to redesign services enabling a more customer focused, locally based service delivery model. (i) That the progress made on the More for York Programme be noted. (ii) That the work undertaken to date on identifying the Sustainability benefits from the programme be noted. (iii) That the Income Collection proposals set out in paragraphs 42-67 of the report be approved, in particular. · the proposal to introduce the Allpay facility · the closure of the cashiering function in the banking hall and · the provision of a residual cashiering facility at 9 St Leonard’s. 1 (iv) That ... view the full minutes text for item 127.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 15th December 2009
Report of the Corporate Management Team
MoreforYork Update – Income Collection and Sustainability Review
Summary 1. This report sets out a general update on work on the 8 agreed moreforYork workstreams, provides a review of the sustainability impacts of the programme, sets out further proposals for member decision regarding the provision of community based cash collection and proposes commencement of 2 further blueprints, for inclusion in the programme.
Background 2. The moreforYork Programme has been established to transform City of York Council into a more effective organisation that delivers
o More for our customers o More for our employees
o More for our money 3. The scope of the programme was agreed by Executive in July 09 and in October 09 Executive agreed the detailed proposals for 8 of the 10 workstreams. Two further blueprints are presented on this agenda (Organisation Review and Adult Social Care).
4. This report provides
Section 1 – An update on progress made on each of the 8 agreed blueprints
Section 2 – A review of the Sustainability impacts of the programme
Section 3 – Further detailed proposals for community based income collection
Section 4 – A summary of 2 additional recommended Blueprints
Section 1 – Progress report
Programme Office
5. These 8 blueprints were agreed by members on October 20th 2009 and implementation work began immediately. Detailed plans are being drawn up for each workstream with an overall Programme Plan outlining the dependencies between streams, and detailing the supporting workstreams such as IT HR and Finance. This is supplemented by directorate views of the plan setting out directorate specific workstreams and the impact of cross-cutting workstreams which enable each directorate to plan and co-ordinate their programme effort. Risk and Issue Logs, and mechanisms for tracking financial and performance benefits have also been developed.
6. Equalities Impact Assessments (EIAs) have been carried out for initiatives which will impact in the current financial year and feedback has been incorporated into relevant workstreams e.g. Provision of recycling containers. Further EIA events are planned to gain valuable input into all initiatives.
7. Consultation with staff and unions has commenced both at Joint Consultative Committees and directly with affected groups of staff.
8. Below are some of the highlights of this early work in each stream which may be of interest to members. This does not attempt to set out a comprehensive assessment of progress. This will be done in a milestone review in the next moreforYork Update report in the early Spring
Housing
9. Good progress has been made and early savings have been identified from the Gas Maintenance area and from a deal to allow the University to source material from Jewsons via the Eco Depot. Productivity improvements have been achieved and a pilot of mobile working in Housing Repairs will commence in the New Year. A solution will shortly be procured for tracking vehicles to enable improved and more cost effective work allocation to teams working in the field.
Neighbourhood Services
10. Waste and Neighbourhood Pride service - Major is work ongoing in order to optimise utilisation of waste and Neighbourhood crews and vehicles. A pilot of mobile technology will support the business in December and January. The provision of new containers is now being achieved in 5 days (down from 10 days). Recycling is now rolled out to 91% of the city.
11. Customer Services – Work is ongoing to streamline income collection in parking. Work is in progress to improve the end to end process, including major improvements to the YCC in April next year. This will make contact easier for the customer and will provide the necessary information to allow NS to continually and significantly improve the levels of service.
12. Highways - Work is ongoing on Highways maintenance contracts to enable them to work smarter with suppliers and neighbouring authorities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.