CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive - for meetings from 03/06/00 to 26/04/11, Tuesday 15 December 2009 at 2.00pm

More for York Update - Income Collection and Sustainability Review

Noted Executive 3 papers

Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 15 December 2009. Below is the council's own wording, with the papers it was decided on.

Item127

Resolved

(i) That the progress made on the More for York Programme be noted. (ii) That the work undertaken to date on identifying the Sustainability benefits from the programme be noted. (iii) That the Income Collection proposals set out in paragraphs 42-67 of the report be approved, in particular. · the proposal to introduce the Allpay facility · the closure of the cashiering function in the banking hall and · the provision of a residual cashiering facility at 9 St Leonard’s. (iv) That the production of an additional Blueprint for work on Children’s Social Care, as set out in paragraphs 69-73, be approved. (v) That the production of an additional Blueprint for work on Finance Performance and associated support, as set out in paragraphs 74-77, be approved. REASON: To help enable the Council to deliver service improvements and create efficiency savings of £15m over the next three years and to redesign services enabling a more customer focused, locally based service delivery model. (i) That the progress made on the More for York Programme be noted. (ii) That the work undertaken to date on identifying the Sustainability benefits from the programme be noted. (iii) That the Income Collection proposals set out in paragraphs 42-67 of the report be approved, in particular. · the proposal to introduce the Allpay facility · the closure of the cashiering function in the banking hall and · the provision of a residual cashiering facility at 9 St Leonard’s. 1 (iv) That ... view the full minutes text for item 127.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 15th December 2009

Report of the Corporate Management Team

MoreforYork Update – Income Collection and Sustainability Review

Summary 1. This report sets out a general update on work on the 8 agreed moreforYork workstreams, provides a review of the sustainability impacts of the programme, sets out further proposals for member decision regarding the provision of community based cash collection and proposes commencement of 2 further blueprints, for inclusion in the programme.

Background 2. The moreforYork Programme has been established to transform City of York Council into a more effective organisation that delivers

o More for our customers o More for our employees

o More for our money 3. The scope of the programme was agreed by Executive in July 09 and in October 09 Executive agreed the detailed proposals for 8 of the 10 workstreams. Two further blueprints are presented on this agenda (Organisation Review and Adult Social Care).

4. This report provides

Section 1 – An update on progress made on each of the 8 agreed blueprints

Section 2 – A review of the Sustainability impacts of the programme

Section 3 – Further detailed proposals for community based income collection

Section 4 – A summary of 2 additional recommended Blueprints

Section 1 – Progress report

Programme Office

5. These 8 blueprints were agreed by members on October 20th 2009 and implementation work began immediately. Detailed plans are being drawn up for each workstream with an overall Programme Plan outlining the dependencies between streams, and detailing the supporting workstreams such as IT HR and Finance. This is supplemented by directorate views of the plan setting out directorate specific workstreams and the impact of cross-cutting workstreams which enable each directorate to plan and co-ordinate their programme effort. Risk and Issue Logs, and mechanisms for tracking financial and performance benefits have also been developed.

6. Equalities Impact Assessments (EIAs) have been carried out for initiatives which will impact in the current financial year and feedback has been incorporated into relevant workstreams e.g. Provision of recycling containers. Further EIA events are planned to gain valuable input into all initiatives.

7. Consultation with staff and unions has commenced both at Joint Consultative Committees and directly with affected groups of staff.

8. Below are some of the highlights of this early work in each stream which may be of interest to members. This does not attempt to set out a comprehensive assessment of progress. This will be done in a milestone review in the next moreforYork Update report in the early Spring

Housing

9. Good progress has been made and early savings have been identified from the Gas Maintenance area and from a deal to allow the University to source material from Jewsons via the Eco Depot. Productivity improvements have been achieved and a pilot of mobile working in Housing Repairs will commence in the New Year. A solution will shortly be procured for tracking vehicles to enable improved and more cost effective work allocation to teams working in the field.

Neighbourhood Services

10. Waste and Neighbourhood Pride service - Major is work ongoing in order to optimise utilisation of waste and Neighbourhood crews and vehicles. A pilot of mobile technology will support the business in December and January. The provision of new containers is now being achieved in 5 days (down from 10 days). Recycling is now rolled out to 91% of the city.

11. Customer Services – Work is ongoing to streamline income collection in parking. Work is in progress to improve the end to end process, including major improvements to the YCC in April next year. This will make contact easier for the customer and will provide the necessary information to allow NS to continually and significantly improve the levels of service.

12. Highways - Work is ongoing on Highways maintenance contracts to enable them to work smarter with suppliers and neighbouring authorities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MFY: Income Collection & SustainabilityAppendix 1 135 KB Download
PDF
MFY: Income Collection & SustainabilityAppendix 2 47 KB Download
PDF
More for York Update: Income Collection and Sustainability ReviewReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present

On this subject at York

Search all
  1. More for York Update - Income Collection and Sustainability ReviewThis decision
  2. Delivering More Affordable Housing in York - Castle MillsAgreed
  3. Delivering More Affordable Housing in York – Update on the Housing Delivery ProgrammeApproved
  4. Leveraging more retrofit investment into York - Energy Company Obligation Wave 4 and Great British Insulation Scheme LA Flex Arrangement (3:52pm)Approved
  5. Delivering More Affordable Housing in York – update on the Housing Delivery Programme (19:07)Decided
  6. Playing Field, Sycamore Terrace, York [19/02347/FUL]Approved

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open