East Area Planning Sub-Committee, Thursday 14 January 2010 at 2.00pm

56 Tang Hall Lane

Approved Planning 2 papers

East Area Planning Sub-Committee approved this item on Thursday 14 January 2010. Below is the council's own wording, with the papers it was decided on.

Item44b

Resolved

That the application be approved subject to the conditions listed in the Officers report and the following additional conditions: Condition 16 – Prior to the commencement of the development, full details (including cross sections) shall be submitted to and approved in writing by the Local Planning Authority indicating the relationship of the proposed development to the turning head within Hornby Court. The submitted details shall indicate how the difference in levels between the development site and Hornby Court are to be resolved. The development shall be carried out in accordance with the approved details. REASON – In order that the difference in levels can be resolved and to ensure an acceptable form of development. Condition 17 – Development shall not begin until details of foul and surface water drainage works have been submitted to and approved in writing by the Local Planning Authority, and thereafter the development shall be carried out in accordance with the approved details. REASON – So that the Local Planning Authority may be satisfied with these details for the proper drainage of the site to comply with guidance contained within Planning Policy Statement 25 (Development and Flood Risk) and that provision has been made to maintain the proposed drainage system. REASON: In the opinion of the Local Planning Authority the proposal subject to the conditions listed in the officers report and above, would not cause undue harm to interests of acknowledged importance, with particular reference to design and landscape, highways and impact on residential amenity. As such the proposal complies with Policies GP1, H4a, GP10 of the City of York Development Control Local
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to East Area Planning Sub-Committee

COMMITTEE REPORT

Committee: East Area Ward: Heworth Date: 14 January 2010 Parish: Heworth Planning Panel

Reference: 09/02027/FUL Application at: 56 Tang Hall Lane York For: Dwelling in rear garden with access from Hornby Court By: [name removed] Type: Full Application Target Date: 5 January 2010

1.0PROPOSAL

1.1This a full planning application for the erection of a detached two bedroomed house within the rear garden area of 56 Tang Hall Lane. Access to the property is proposed from Hornby Court.

1.256 Tang Hall Lane is a semi-detached property split into two flats. The site is located within the rear garden area of 56 Tang Hall Lane. The land has a frontage to Hornby Court, a small cul de sac to the south of Tang Hall Lane. The site area extends to 0.0188 hectares.

1.3The proposal is to erect a two bedroomed house. The property is designed with a frontage to Hornby Court. Access to the dwelling will be from Hornby Court with parking spaces provided to the front of the property and cycle parking in a small attached building to the front of the dwelling. The main bulk of the building stands 3.8 metres to eaves and 6.8 metres to apex.

1.4The application is supported by a Drainage Assessment, Sustainability Statement and Design and Access Statement.

1.5The application has been called to Committee by Councillor Ruth Potter on the grounds of overdevelopment of the site and loss of garden to number 56 Tang Hall Lane.

Planning History

1.6The relevant planning history of the site is as follows:- - Permission was granted in February 2005 for extension to the side of 56 Tang Hall Lane (04/03722/FUL). One application was withdrawn and another refused before the third consent was granted. - Planning permission was granted for the erection of housing development at Hornby Court in 2005. (Ref: 05/01627/FULM) - Permission for the erection of a garage to serve 56 Tang Hall Lane with access from Hornby Court was granted in December 2008. (Ref 08/ 02510/FUL)

Application Reference Number: 09/02027/FUL Item No: 4b Page 1 of 12 2.0 POLICY CONTEXT

2.1Development Plan Allocation:

City Boundary York City Boundary 0001

DC Area Teams East Area (1) 0003

2.2Policies:

CYH4A Housing Windfalls

CYGP10 Subdivision of gardens and infill devt

CYGP1 Design

CYGP4A Sustainability

CYGP9 Landscaping

3.0CONSULTATIONS

INTERNAL

Highways Network Management - Hornby Court is not a publicly adopted highway as the section 38 agreement has yet to be signed. According to the section 38 agreement the land fronting Hornby Court is shown as a possible children's play area. A street light on the frontage of the site would need to be relocated. A previous application for the erection of a double garage on the site was not objected to on highway grounds. No objections subject to conditions.

Environmental Protection - no objections, an informative is requested to remind the developer of their obligations with regard to environmental safeguards.

Application Reference Number: 09/02027/FUL Item No: 4b Page 2 of 12 Lifelong Learning and Leisure - as there are no on site amenity facilities a commuted sum is required.

Structures and Drainage - No objections in principle subject to additional information added to drawings showing schematic drainage proposals

EXTERNAL

Heworth Planning Panel - supports the application

One letter of objection has been received covering the following points :-

- The proposal will overshadow view from the living room and kitchen window of 58 Tang Hall Lane - The proposal will be like looking out at a 20 ft. wall - The building will not enhance future sale of the property

PUBLICITY

The application has been advertised by means of neighbour consultation letters.

4.0APPRAISAL

4.1Key Issues

- Principle of residential development on the site - Design and Landscaping - Highways, access and parking - Impact on surrounding properties - Sustainability - Open Space - Drainage

Policy Background

4.2This planning application is for the erection of a single detached dwelling.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09 02027 FUL: map: tanghallPlan 235 KB Download
PDF
56 Tang Hall LaneReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
KH
Councillor Keith HymanChair, present
RC
Councillor Richard CreganVice-Chair, present
HD
Councillor Helen DouglasCommittee Member, present
PF
Councillor Paul FirthCommittee Member, present
CF
Councillor Christina FunnellCommittee Member, present
KK
Councillor Ken KingCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
KO
Councillor Keith OrrellCommittee Member, present
DT
Councillor Dave TaylorCommittee Member, present
SW
Councillor Sian WisemanCommittee Member, present

On this subject at York

Search all
  1. 56 Tang Hall LaneThis decision
  2. Tang Hall Cp School Sixth Avenue York YO31 0UT [24/00857/FULM] (5.42 pm)Approved
  3. Proposed Long Term Lease - Tang Hall Community CentreAgreed
  4. Burnholme: the sale of land to facilitate the development of a Care Home; agreement to management arrangements for the Community & Library facilities; disposal of the Tang Hall Library siteAgreed
  5. Tang Hall Area Asset Management Plan Ad-hoc Scrutiny Committee – Final ReportNoted
  6. Tang Hall Area Asset Management PlanApproved

More from York East Area Planning Sub-Committee

All decisions
MeetingDecisionOutcome
2 May 2013 MinutesThat the minutes of the East Area Planning Sub-Committee held on 11 April 2013 be approved and signed by the Chair as... Approved Open
2 May 2013 96 Dodsworth Avenue, York. YO31 8UD (13/00001/FUL)That the application be deferred and brought back to Committee once the additional noise levels had been received. RE... Deferred Open
2 May 2013 Biology Department, Wentworth Way, Heslington, York. YO10 5DD (13/00571/FULM)That the application be approved with the following additional conditions; 1. All demolition and construction works a... Approved Open
2 May 2013 18 Alma Grove, York YO10 4DH (13/00657/FUL)That the application be approved. REASON: In the opinion of the Local Planning Authority the proposal, subject to the... Approved Open
11 Apr 2013 Exclusion of Press and PublicThat the Members of the Press and Public be excluded from the meeting during the consideration of Annexes to agenda i... Decided Open