Lendal Bridge Hub Station

Approved Executive 5 papers

Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 2 March 2010. Below is the council's own wording, with the papers it was decided on.

Item170

Resolved

Members considered a report which provided an update on progress made towards converting the former electricity sub-station at Lendal Bridge to a secure cycle path, and sought approval for funding to progress the project. On 12 June 2007, the Executive had agreed to lease the former sub-station to the Bike Rescue Project CIC for use as a secure cycle park, subject to them obtaining planning permission and sufficient grant funding. Planning consent had now been obtained and funding for the proposed alterations and building refurbishment was being allocated by the Council through its Cycling England award and Transport Planning budget. However, the lowest tender for this work had come in higher than the budget allocation of £270k. This would leave a funding shortfall of approximately £30k for implementation of the full scheme (including upper level cycle storage decking and hoist) or £15k for a pared down scheme providing a reduced storage capacity. As an alternative to Bike Rescue arranging a bank loan to cover the shortfall, it was suggested that the Council provide a loan, to a maximum of either £30k or £15k depending on which scheme was adopted, to be paid back over the initial years of the lease. Approval was also sought to release funding of £270k from the 2009/10 Capital Programme, to enable the project to proceed. In making their decisions, Members noted that the scheme represented significant expenditure but had the potential to create a city centre focal point for cycling and to help promote York as a progressive centre for sustainable transport. They stressed the importance of ensuring that the scheme would operate in co-operation with the cycle proposals for the Railway Station.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 2 March 2010

Report of the Director of City Strategy and the Corporate Landlord

Lendal Bridge Cycle Hub Station Executive Summary 1. The purpose of the report is to;

• update the Executive on the progress made towards converting the former electricity sub station to a secure cycle park, to bring into full use a redundant vacant building in the city centre.

• To obtain authority to release funds of £270,000 from the 2009/10 capital programme to be spent in 2009/10 and 2010/11.

• To consider making a supplementary loan of up to £30,000 to meet the funding shortfall identified.

Background 2. At the Executive meeting on 12 June 2007 members agreed to lease the former Lendal Bridge Sub-station shown in Annex 1, to The Bike Rescue Project CIC for use as a secure cycle park, subject to them obtaining planning permission and sufficient grant funding to fully convert the Sub-Station.

3. As a private community interest, non profit making company Bike Rescue were deemed to be in a better position than the City Council to obtain grant aid. If they were only successful in obtaining partial grant funding, then the Council was to match fund to a maximum of £50,000 from the Transport Planning Unit Capital Programme. The agreement to lease the Sub-Station and the terms and conditions of the lease were delegated to the Corporate Landlord.

4. The Bike Rescue Project CIC are existing tenants of the Council at the Parkside Commercial Centre, and specialise in recycling bicycles and parts which have been donated or recovered from the waste stream, and repairing cycles. For more information see their Business Plan in Annex 2.

5. Several Applications for grant funding were made by Bike Rescue and they received expressions of interest from EON and the Reaching Communities Fund, subject to the scheme receiving Planning Consent and being fully costed. However none of the applications so far have resulted in offers of funding. They have a continuing strategy to pursue further funding and have a number of applications in the pipeline.

6. This process has overlapped with the Council’s successful bid for Cycling City status in which Bike Rescue were involved, and actively assisted. The Hub- Station project was an integral part of the Cycling City bid and was proposed to be funded using the Local Transport Plan and Cycling City grant. An allocation of £270,000 is included within the 2009/10 City Strategy Capital Programme for the provision of the Cycle Hub Station with the source of funding for the scheme split evenly between the Cycling City grant and the Local Transport Plan. The actual funding apportionment at the end of the financial year will be dependent on the progress of other cycling city projects.

7. This scheme will help meet a growing need for a secure repository for residents and visitors cycles. It should help lower the amount of cycle thefts in the city and encourage more people to visit the centre on their cycles in the knowledge that a secure facility is available. It is located in close proximity to the City Centre, en route from the Rail Station, and sits on one of the main national and local cycle routes which increases its potential use and viability. It will enable businesses in the vicinity to promote its use by their employees as a means of achieving targets for carbon reduction, corporate social responsibilities and staff welfare. Cascading benefits would be a lowering of vehicle congestion and environmental impact through more people choosing to cycle.

8. It meets the Cycling City York (CCY) programme goal to encourage more people to cycle and Cycling England have recognised this by endorsing it and providing funding towards the scheme. It is one of the first of such schemes in the country, and Interestingly the term “Cycle Hub” now used around the UK has come from this work. In taking this new initiative to encourage cycling, especially through a partnership arrangement, York is demonstrating a bold and innovative approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lendal Bridge Hub StationAppendix 1 245 KB Download
PDF
Lendal Bridge Hub StationAppendix 2 354 KB Download
PDF
Lendal Bridge Hub StationAppendix 3 51 KB Download
PDF
Lendal Bridge Hub StationAppendix 4 996 KB Download
PDF
Lendal Bridge Hub StationReport 113 KB DownloadRead as text

At this meeting

Whole meeting
167MinutesApproved 169Executive Forward PlanOn the agenda
170Lendal Bridge Hub StationThis decision

Who was there

7 of 7 attended
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present

On this subject at York

Search all
  1. Lendal Bridge Hub StationThis decision
  2. Lendal Bridge Major Refurbishment (10:08am)Noted
  3. Lendal Bridge TrialNoted
  4. Lendal Bridge Repayment ProcessAgreed
  5. Lendal Bridge Repayment Process Deadline ExtensionApproved
  6. Scoping Report on Proposal for Scrutiny Review of Lendal Bridge ClosureNoted

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies