Audit and Counter Fraud Mid-Term Monitor

Noted Finance 5 papers

Audit and Governance Committee noted this item on Monday 26 April 2010. Below is the council's own wording, with the papers it was decided on.

Item79

Resolved

That the results of the audit and fraud work undertaken to date in 2009/10 be noted. REASON: To confirm that Members have considered the implications of audit and fraud findings. Note: Cllr Scott left the room during the discussion on music tuition fees in respect of this item, having declared a prejudicial interest as recorded under Minute 68.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee

Audit and Governance Committee 26 April 2010

Report of the Assistant Director of Customer & Business Support Services (Customer Service & Governance)

Audit and Counter Fraud Mid-Term Monitor

Summary 1 This report provides details of the progress made in delivering the internal audit and counter fraud work plan for 2009/10.

Background 2 The work of internal audit is governed by the Accounts and Audit Regulations 2003 (as amended) and the CIPFA Code of Practice for Internal Audit in Local Government. In accordance with the code of practice, the 2009/10 audit and fraud plan was approved by the Audit and Governance Committee on 29 June 2009. The plan included a programme of audit reviews and details of planned counter fraud activities. The total number of planned audit days was 1,420. The counter fraud activity plan was based on the resources available to the fraud team. The total number of days allocated to counter fraud activities in 2009/10 was 1,282.

3 It was also recognised that changes might need to be made to the audit plan through the year as a result of new or changed priorities and/or if new risks were identified. To reflect the new contractual relationship between the council and Veritau, all proposed variations to the agreed audit plan arising as the result of emerging issues and/or requests from management are subject to a change control process. Where the variation exceeds 5 days then the change must be authorised by the Assistant Director (Customer Service and Governance) who is the client manager for the service. All agreed variations will then be communicated to the Audit and Governance Committee for information.

4 The counter fraud activity plan included details of:

• planned activities, including fraud detection and investigation; • fraud awareness and training; • proactive fraud work; • joint working with other counter fraud agencies; • resource allocation.

2009/10 Internal Audit Plan – Progress to Date 5 Two of the priorities for Veritau are to deliver at least 90% of the audit plan and to ensure that the service continues to operate to recognised professional standards (as determined by the Code of Practice). These are the minimum requirements necessary to achieve a good score for internal control as part of the Use of Resources assessment process.

6 Internal audit successfully delivered 94.2% of the 2008/09 audit plan. 80% of the 2009/10 audit plan had been completed by 23 March 2010. This figure is however based on reports issued and does not take into account further audit fieldwork which is either complete or in progress. Based on the current work programme it is anticipated that the 90% target will be achieved. Details of the audits completed and the reports issued since the last progress report to this committee (on 21 December 2009) are given in annex 1.

7 As noted in paragraph 3 above, it has been necessary to make a number of variations to the audit plan to accommodate a shortfall in resources and changes in priorities. Details of the audit plan variations approved by the client manager since the last report to this committee in December 2009 are given in annex 2.

2009/10 Counter Fraud Activity Plan – Progress to Date 8 Counter fraud work has been undertaken in accordance with the approved plan. Annex 3 provides details of the investigations completed and provides a summary of the work undertaken. Additional work undertaken in 2009/10 (shown in the annex) includes the following.

• A fraud awareness survey of council managers and supervisors. This has highlighted a number of issues and an action plan to address these is currently being prepared.

• A project to investigate housing tenancy related fraud, for which a major publicity campaign is currently in progress.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit and Fraud MonitorAppendix 1 86 KB Download
PDF
Audit and Fraud MonitorAppendix 2 59 KB Download
PDF
Audit and Fraud MonitorAppendix 3 70 KB Download
PDF
Audit and Fraud MonitorAppendix 4 37 KB Download
PDF
Audit and Counter Fraud Mid-Term MonitorReport 96 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
BW
Councillor Brian WatsonChair, present
JB
Councillor Jenny BrooksVice-Chair, present
DB
Councillor Denise BowgettCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, apologies
DS
Councillor David ScottCommittee Member, present
MK
Councillor Madeleine KirkCommittee Member, apologies
RW
Councillor Richard WatsonCommittee Member, apologies
PF
Councillor Paul FirthSubstitute, present as substitute
KH
Councillor Keith HymanSubstitute, present as substitute
JG
Councillor Julie GunnellAttendee, in attendance
RM
Councillor Richard MooreAttendee, in attendance

On this subject at York

Search all
  1. Audit and Counter Fraud Mid-Term MonitorThis decision
  2. Internal Audit & Counter Fraud Progress Report (18:29)Noted
  3. Audit and Counter Fraud Progress Report (6:52 pm)Decided
  4. Annual Report of the Head of Internal Audit and Counter Fraud Annual Report (7:28 pm)Noted
  5. Internal Audit and Counter Fraud Work Programmes 2024/25 (5:42 pm)Approved
  6. Audit & Counter Fraud Progress Report (7:49 pm)Noted

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open