Resolved
That the progress made in implementing the audit recommendations, as set out in the report, be noted. REASON: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
Audit and Governance Committee noted this item on Monday 26 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress made in implementing the audit recommendations, as set out in the report, be noted. REASON: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
Audit and Governance Committee 26 April 2010
Report of the Assistant Director of Customer & Business Support Services (Customer Service & Governance
Follow Up of Internal Audit Recommendations
Summary 1. This report sets out the progress made by directorates in implementing those agreed audit recommendations which were due to have been implemented by 1 March 2010.
Background 2. Internal audit follow up reports are brought to the committee twice a year, setting out the progress made by service departments in implementing agreed internal and external audit recommendations; together with details of any outstanding recommendations that require referral to the committee for further action. This report is based on follow up work by the council’s internal audit service provider, Veritau Limited.
3. All recommendations are reviewed once their agreed implementation date has passed. The review is carried out using a combination of questionnaires completed by departments, risk assessment, and by further detailed examination by internal audit where appropriate. The last report was presented to this committee in December 2009 and therefore the summary of follow up work below is for a period of only four months rather than the usual six.
Consultation 4. Details of the findings of follow up work have been discussed with the relevant service managers and chief officers.
Follow Up of Internal Audit Recommendations 5. A total of 86 recommendations were followed up as part of this review. A summary of the priority of these recommendations is included in figure 1, below. Figure 1: Recommendations followed up as part of the current review Priority of No. of Recommendations Recommendations Followed Up 1 (High) 3 2 (Medium) 23 3 (Low) 60 Total 86
6. Figure 2 below provides an analysis of the recommendations which have been followed up, by Directorate. Figure 2: Recommendations followed up by Directorate No. of Recommendations Followed Up by Directorate Priority of Chief City HASS LCCS Resources Neighbourhood Recommendations Executives Strategy Services 1 (High) 0 0 1 1 1 0 2 (Medium) 1 1 7 10 4 0 3 (Low) 2 0 10 31 7 10 Total 3 1 18 42 12 10
7. Of the 86 recommendations, 12 (14% of total) had been superseded (for example by business developments or because of cessation of service). Of the remaining recommendations, 63 (73% of total) had been satisfactorily implemented.
8. In a further 11 cases (13% of total) the agreed recommendations had not been implemented by the due date. In all these cases satisfactory explanations for the delays were received from the relevant service departments (e.g. unexpected difficulties or the action being dependent on new systems being implemented). Following this, revised implementation deadlines have been agreed. These will be followed up again after the revised deadline, and if necessary will proceed to the approved escalation procedure.
Follow Up of Audit Commission Recommendations
9. In December 2009, the committee requested that information on whether work on the Sure Start grant claim is on track to meet submission deadlines be included in this report. Following further follow up, assurance has been given by the responsible finance manager that the grant claim is on track to meet the submission deadline.
10. A follow up of the recommendations made by the Audit Commission in relation to financial planning is being undertaken as part of a current internal audit review in this area. Work is ongoing and an update will be included as part of the next follow up report due in September. The progress made by management to implement the recommendations contained in the Audit Commission’s reports on Grant Claims Certification and Asset Management will be assessed and also reported to this committee in September.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Follow Up of Internal Audit RecommendationsReport | 88 KB | DownloadRead as text |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.