Water End Cycle Scheme Evaluation

Agreed Executive 4 papers

Decision Session - Executive Member for City Strategy agreed this item on Tuesday 1 June 2010. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That the Executive Member for City Strategy agrees to: i) Note the success of the scheme in achieving its main objective of delivering increased levels of cycling ii) Note that a road closure in the Westminster Road area would generate increases in traffic queues, and delay, at the Clifton Green junction and would potentially significantly impact on the operation of the junction and other parts of the network iii) Instruct officers to give further consideration to altering the signal timings during the AM peak and weekend operation iv) Instruct officers to give further consideration to linking the crossing points to optimise traffic flow heading towards the Clifton Green junction. v) Note the recommendations of the Scrutiny CCfA review to the Executive on 6 July and · Suggests to the individual members of the Scrutiny Committee that, in light of officer concerns about the limited options available to them, they should make it clear precisely what changes they would expect to see covered by their recommendation for “new, comprehensive proposals for the Water End junctions to improve the current junction and reduce greatly traffic flows in Westminster Road/The Avenue”? and · Endorses the following scrutiny recommendations: a. That the Council should, in future, use traffic models which incorporate side streets when assessing and designing junction improvements b. That the present policy of reviewing new highway schemes only after a period of twelve months should be modified to enable a review after three months when unforeseen consequences have arisen and when Ward Members request it. REASON:To retain the benefits of the cycle scheme without causing additional delay to the network and to alter the signal timings in order to improve traffic flow travelling towards and through the junction, which is intended to reduce the amount of traffic diverting through Westminster Road and The Avenue.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for City Strategy

Decision Session 1st June 2010 Executive Member for City Strategy Report of the Director of City Strategy

Water End Cycle Scheme Evaluation Summary 1. To advise the Executive Member of the outcome of the monitoring of the Water End cycle scheme and consider the effectiveness of the scheme in encouraging increases in cycling levels. The report considers the purpose of the scheme, the initial modelling that was undertaken and the traffic and cycle data that was collected pre-implementation and compares that with the current situation. It also considers the impacts of the scheme on other parts of the highway network, specifically Westminster Road and The Avenue and reviews the option contained in a previous report to implement a road closure with reference to the draft recommendations from the Councillor Call for Action Task Group.

2. The cycle data shows significant increase in cycle usage since implementation of the scheme and traffic data reflects the pre-scheme monitoring predictions that there would be longer queues overall once a level of redistribution on the network had taken place. Redistribution has not had a material impact on other radial routes or the Outer Ring Road. It is observed that traffic flows on Westminster Road/The Avenue have increased from 900 to 1774 vehicles (average weekday flows) and partly contribute to the effective operation of the junction. Accident data records three injury accidents since the implementation of the scheme, all resulting from a right turn manoeuvre into Westminster Road, an issue that has been raised by residents.

3. Traffic flows on Westminster Road were reported previously and considered along with results from the residents survey on a point closure and other options available for reducing traffic volumes. Whilst there was overall support for a closure there was no agreement as to where that closure should be. A comparison of traffic flows on other residential roads shows that flows on Westminster Road are lower than many other roads.

4. Additional modelling was carried out to identify the impact on Clifton Green junction of a point closure on Westminster Road. Modelling shows that a closure without any mitigation measures at least doubles the existing average traffic queues and would be significantly worse than double at the height of the peaks. Mitigation was modelled in the form of a partial reinstatement of the filter lane at Clifton Green, but it does not fully mitigate the increase in traffic queues or delay and the situation on Water End would be worse than currently experienced.

5. The scheme has been successful in delivering an increase in cycling and it was not considered appropriate to remove the cycle lane in order to reinstate a left turn filter. Options are considered within this report that would enable mitigation works to be undertaken whilst retaining the cycle lane. This involves considering how to increase the available carriageway width. The only remaining options for doing this are either the removal (or severe cutting back) of hedges of properties adjacent to the junction, removal of the cobbles or removal of part of the Clifton Green (which has village green status). All of these options were previously considered and rejected. The compromise lies between increased traffic queues and delay on Water End and the potential impact that has on other parts of the network, traffic flows on Westminster Road and removal of conservation features within a conservation area.

Recommendations 6. The Executive Member for City Strategy is recommended to:

a) Note the success of the scheme in achieving its main objective of delivering increased levels of cycling

b) Agree that additional increases in traffic queues and delay at the Clifton Green junction would significantly impact on the operation of the junction and other parts of the network

c) Instruct officers to give further consideration to altering the signal timings during the AM peak and weekend operation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Clifton Green May2010 OptionsAppendix G 832 KB Download
PDF
water End eval report: PDF Version of Draft Final Report Annexes for Water End CCfAAppendix H 1.3 MB Download
PDF
for Water End A: F Ruth_11052010Appendix es 1.2 MB Download
PDF
Water End Cycle Scheme EvaluationReport 189 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 4 attended
SG
Councillor Steve GallowayCabinet Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance
DH
Councillor David HortonAttendee, in attendance
TS
Councillor Tracey Simpson-LaingAttendee, in attendance

On this subject at York

Search all
  1. Water End Cycle Scheme EvaluationThis decision
  2. Consideration of results received from the consultation to extend R23 Residents Parking Zone to include Government House Road and a decision to be made on implementing restrictions on Water End slip road (11:04am)Approved
  3. Consideration of results received from the consultation to extend R23 Residents Parking Zone to include Government House Road and a decision to be made on placing limited waiting restrictions on Water End slip road (12:21pm)Deferred
  4. The Determination of a Section 18(3) (a) Application by Clifton Bridge Hotel Ltd. for a Premises Licence at Clifton Bridge Hotel, 23 Water End, Clifton, York, YO30 6LL (CYC-069581)Approved
  5. 12 Water End York YO30 6LP (15/00405/FUL)Approved
  6. 12 Water End, York, YO30 6LP (15/00405/FUL)Deferred

More from York Decision Session - Executive Member for City Strategy

All decisions
MeetingDecisionOutcome
1 Mar 2011 MinutesThat the minutes of the last Decision Session – Executive Member for City Strategy, held on 1 February 2011 be approv... Approved Open
1 Mar 2011 Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto... Decided Open
1 Mar 2011 Evening and Sunday Bus Services to Rawcliffe and SkeltonThat the Executive Member for City Strategy agrees: i) That the level of service proposed to the affected areas follo... Agreed Open
1 Mar 2011 A19 Fulford Road Corridor Improvements - Request for 20 mph Speed Limit fronting Fishergate and St George's SchoolsThat the Executive Member for City Strategy agrees to: i) Option 1 to implement the 20mph speed limit as proposed and... Agreed Open
1 Mar 2011 Traffic Arrangements at York Railway StationThat the Executive Member for City Strategy agrees to: i) Note the outcome of the discussions with East Coast and Net... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies