City Strategy Capital Programme - 2009/10 Outturn Report
AgreedExecutive3 papers
Decision Session - Executive Member for City Strategy agreed this item on Tuesday 1 June 2010. Below is the council's own wording, with the papers it was decided on.
That the Executive Member agrees to: i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes to the report. ii) Approve the proposed carryovers as outlined in paragraphs 21 to 23 of the report, subject to the approval of the Executive. iii) Request an officer update on the options available for progressing the James Street link road scheme. REASON: To enable the effective management and monitoring of the Council’s Capital Programme. That the Executive Member agrees to: i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes to the report. ii) Approve the proposed carryovers as outlined in paragraphs 21 to 23 of the report, subject to the approval of the Executive. 1. iii) Request an officer update on the options available for progressing the James Street link road scheme. 2. REASON: To enable the effective management and monitoring of the Council’s Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session 1 June 2010 – Executive Member for City Strategy
Report of the Director of City Strategy
City Strategy Capital Programme – 2009/10 Outturn Report Report Summary 1. The purpose of this report is to:
• Inform the Executive Member of the outturn position for schemes in the 2009/10 capital programme, including budget spend to 31 March 2010, and the progress of schemes in the year;
• Inform the Executive Member of any variations between the outturn and budget, and seek approval for funding to be carried forward to 2010/11 subject to the approval of the Executive.
Recommendations 2. The Executive Member is requested to:
i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes. ii) Approve the proposed carryovers as outlined in paragraphs 21 to 23, subject to the approval of the Executive. Reason: to enable the effective management and monitoring of the council’s capital programme.
Background 3. The City Strategy 2009/10 transport base budget was confirmed at Full Council on 26 February 2009. Since then a number of amendments have taken place as reported to the Executive Member in the 2008/09 Capital Outturn report, the Consolidated report (July), the Monitor 1 report (September), and the Monitor 2 Report (December). The Peckitt Street Flood Scheme was added at Corporate Monitor 2, and additional grant is available from the Freeflow traffic management project.
4. These changes have resulted in a current approved capital programme for 2009/10 of £5,233k, financed by £4,978k of external funding, leaving a cost to the council of £255k. Table 1 illustrates the movements from the original budget to the currently approved position.
Table 1: Current Approved 2009/10 Capital Programme Gross External Capital Budget Funding* Receipts £000s £000s £000s Original Budget approved by 5,742 5,502 240 Council at 26 February 2009
Additions/reductions in 08/09 +44 -15 +59 outturn report Additions/reductions from 08/09 outturn report approved -516 -441 -75 at Monitor 1 Additions/reductions from 08/09 outturn report approved -125 -125 at Monitor 2
Peckitt Street Flood Scheme +62 +31 +31
Freeflow Project +21 +21
Misc. Contributions +5 +5
Current Approved Capital 5,233 4,978 255 Programme *External funding refers to government grants, non government grants, other contributions, developers contributions and supported capital expenditure.
Summary of Key Issues 5. Against the approved budget of £5,233k in 2009/10, there is an outturn of £4,737k, a net underspend of £496k (9.4%). The outturn spend comprises:
• Integrated Transport and Highway Maintenance Schemes: £4,625k spend against a budget of £4,947k (£322k underspend (6.5%)).
• City Strategy Maintenance Budgets: £51k spend against a £224k budget (£173k underspend).
• Peckitt Street Flood Defences: £62k spend against an original budget of £70k (reduced to £62k at outturn).
6. The overall spend is outside the target tolerance of +2.0%/-5% which is used to assess the performance of the management of the City Strategy Capital Programme. However the principal reason is the late confirmation that the £300k contribution to the Hopgrove Roundabout scheme was not required in 2009/10. If this single scheme is excluded then the spend is 3.5% below budget.
7. Over 110 schemes have been progressed in the year ranging from £1k up to over £900k in value, with 15 schemes accounting for approximately 75% of the programme value. For many schemes feasibility studies and other preparatory works had to be undertaken within the year, leading to an expectation that many of the projects would be delivered towards the end of the year. In fact almost 50% of the budget was spent in the final three months of the year despite the poor weather experienced in January and February.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.