Future Operation of Bus Route 55

Agreed Executive 2 papers

Decision Session - Executive Member for City Strategy agreed this item on Tuesday 6 July 2010. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

That the Executive Member agrees the proposal to maintain the present operation of route 55 until the expiry of the existing contract in 2011. REASON: This will provide sufficient time for officers to assess the effects on the bus network in York resulting from the changes to the commercially operated routes and investigate and propose alternatives that best meet the requirements of the local transport plan and the residents of York. That the Executive Member agrees the proposal to maintain the present operation of route 55 until the expiry of the existing contract in 2011. 1. REASON: This will provide sufficient time for officers to assess the effects on the bus network in York resulting from the changes to the commercially operated routes and investigate and propose alternatives that best meet the requirements of the local transport plan and the residents of York.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for City Strategy

Decision Session 6 July 2010 – Executive Member for City Strategy Report of the Director of City Strategy

FUTURE OPERATION OF BUS ROUTE 55 Summary 1. This report draws attention to the unsatisfactory financial performance and poor patronage of bus route 55, which is procured by the Council under competitive tender. Officers have examined the reasons for this and have identified areas where the route duplicates more frequent commercial services as being the main cause for concern.

2. As a result, an investigation has been undertaken to identify actions to improve the route’s overall performance, including timetable amendments and revisions to the routeing. Several options had been prepared for consideration by the Executive Member but in the intervening period between preparation of a report containing recommendation and the date of this decision session, officers were made aware of major changes to be implemented to the commercial network that directly impact upon the existing route. In the light of this, it is considered preferable that any prospective amendments to the route be deferred until such time as the effects on the bus network in York can be further examined.

3. Members will be consulted on future options prior to the commencement of the tendering exercise for services whose contracts expire in September 2011.

Recommendations 4. That the Executive Member for City Strategy is recommended to:

5. Agree the proposal to maintain the present operation of route 55 until the expiry of the existing contract in 2011.

6. Reason: This will provide sufficient time for officers to assess the effects on the bus network in York resulting from the changes to the commercially operated routes and investigate and propose alternatives that best meet the requirements of the local transport plan and the residents of York. Background 7. Bus route 55 has operated in its current form since April 2009, as a bi- directional, circular route operating City Centre, Huntington Road, Monks Cross Shopping Centre, York University, Fulford, City Centre and vice-versa. The contract, which is due to expire in September 2011, receives support from the Council of £60,560 per annum, although the University of York provides the Council with a subsidy of £5000 per annum in recognition of the service to and from the University. However, except between Monks Cross and Fulford the route is little used, leading to the average passenger loading per bus hour (that is the total number of passengers carried divided by the total number of hours operated by every bus providing the service) as of May 2010 being only 8.06. Council criteria state that this figure should not be less than ten and any route where the figure continually fails to reach this target should be reviewed to consider its viability. In the case of route 55, as stated in the summary above, for much of its length, the route mirrors other, more frequent commercial services, all of which are operated by the same company and on whose buses alone popular day tickets can be used. The tender for operation of route 55 was awarded to another operator, so these day tickets are not valid on this service.

Consultation 8. Ward members affected have outlined broad support for the proposal to maintain the current operation in the light of existing circumstances.

Options 9. The following, nil cost options are presented for consideration by the Executive Member:

• To continue with the current route unchanged until the contract expires, despite this operation failing to meet the Council’s own criteria.

• Withdraw the route completely without replacement.

• Replace route 55 with a new, more frequent, end to end route (provisionally numbered 15) operating solely between Monks Cross Shopping centre and the Designer Outlet, St. Nicholas Avenue via Heworth, University of York, Fulford Broadway and the A19.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A existing route 55 timetable and mileageAppendix e 35 KB Download
PDF
Future Operation of Bus Route 55Report 99 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 4 attended
SG
Councillor Steve GallowayCabinet Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance
DH
Councillor David HortonAttendee, in attendance
RW
Councillor Richard WatsonAttendee, in attendance

On this subject at York

Search all
  1. Future Operation of Bus Route 55This decision
  2. Future operation of Rowntree Park Lodge and ParkApproved
  3. Future Operation of Rowntree Park Lodge and ParkApproved
  4. Future Operation of Bus Route 21Agreed

More from York Decision Session - Executive Member for City Strategy

All decisions
MeetingDecisionOutcome
1 Mar 2011 MinutesThat the minutes of the last Decision Session – Executive Member for City Strategy, held on 1 February 2011 be approv... Approved Open
1 Mar 2011 Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto... Decided Open
1 Mar 2011 Evening and Sunday Bus Services to Rawcliffe and SkeltonThat the Executive Member for City Strategy agrees: i) That the level of service proposed to the affected areas follo... Agreed Open
1 Mar 2011 A19 Fulford Road Corridor Improvements - Request for 20 mph Speed Limit fronting Fishergate and St George's SchoolsThat the Executive Member for City Strategy agrees to: i) Option 1 to implement the 20mph speed limit as proposed and... Agreed Open
1 Mar 2011 Traffic Arrangements at York Railway StationThat the Executive Member for City Strategy agrees to: i) Note the outcome of the discussions with East Coast and Net... Agreed Open