Decision Session - Executive Member for City Strategy agreed this item on Tuesday 6 July 2010. Below is the council's own wording, with the papers it was decided on.
That the Executive Member agrees to: i) Note the progress made on the delivery of the Haxby Station scheme. ii)Progress Option 1 to deliver the station in accordance with standard procedures but defer commencement of further work, until the availability of funding for the delivery of the scheme is clarified REASON: To enable a high value for money scheme to be progressed whilst minimising the risk of abortive expenditure. That the Executive Member agrees to: i) Note the progress made on the delivery of the Haxby Station scheme. ii)Progress Option 1 to deliver the station in accordance with standard procedures but defer commencement of further work, until the availability of funding for the delivery of the scheme is clarified. 1. REASON: To enable a high value for money scheme to be progressed whilst minimising the risk of abortive expenditure.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session 6 July 2010 – Executive Member for City Strategy
Report of the Director of City Strategy
Haxby Station Update
Summary 1. This report provides an update on the progress of the Haxby Station project and the need for a further Line Speed Improvement Study prior to Network Rail providing the necessary support for the scheme. The report also recommends that the delivery of the project should be suspended until the availability of funding is clarified.
Recommendations 2. The Executive Member is recommended to:
• Note the progress made on the delivery of the Haxby Station scheme.
• Progress Option 1 to deliver the station in accordance with standard procedures but defer commencement of further work, until the availability of funding for the delivery of the scheme is clarified.
Reason: To enable a high value for money scheme to be progressed whilst minimising the risk of abortive expenditure.
Background 3. The provision of a station at Haxby has been an aspiration of the Council for many years. It is included in the 2nd Local Transport Plan as a scheme to progress through a bid for funding to the Department for Transport (DfT).
4. The station, located on the TransPennine network, with trains running to Scarborough, York, Leeds and Manchester, has been the subject of extensive feasibility and investigation work over a number of years. Whilst having significant local benefits of providing a fast alternative route into York for the residents of the area, the principal benefit is sub-regional, allowing a 3km catchment population of approximately 22,000 direct access to Scarborough, Leeds and Manchester. The transfer of these longer commuting/leisure trips, many of which are currently undertaken by car, would reduce congestion levels, particularly on the A1237 Outer Ring Road and the A64.
5. Following a feasibility study undertaken by Network Rail the further development of a conventional (opposing platform) station approximately 230m south of the Station Road level crossing adjacent to the existing allotments was approved in principle by the Executive Member at the 16 March 2009 Executive Member Advisory Panel. To establish the practicality of providing the station in railway infrastructure terms an outline layout has been developed. This proposal comprised 2 platforms, a footbridge (with ramp or lift access), a small station building, a car park and the provision of an access off Station Road. The proposal would be subject to consultation and detailed design before the submission of a planning application (including an updated Transport Assessment).
6. To enable a station to be constructed Network Rail have to be satisfied that the proposal is practical to deliver and the Train Operating Company for the route (First TransPennine) need to be assured that there is an acceptable business case for the facility. In particular the train operator must be confident that sufficient new passengers will use the service to cover the additional maintenance, supervision and station access charges. In the case of the station at Haxby separate approvals are required as it is proposed to fund the scheme from Network Rail and DfT resources.
7. The funding from the DfT is currently allocated by the region to a list of prioritised transport schemes through the Regional Transport Advisory Board. The availability of funding for the station within the Regional Funding Allocation was confirmed by the Minister of Transport on 22 July 2009. However, the role of the Region in determining funding allocations is subject to review as part of the introduction of the proposed Decentralisation and Localism Bill. In addition the entire Major Scheme process was suspended on 10 June 2010 until the spending review in the autumn is complete. It is not anticipated that the funding will be clarified until after the review has been completed and a new major scheme process has been developed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.