(i) That the risks set out in Annexes A and B and in paragraph 5 of the report be noted and agreed. REASON: To provide assurance that risks to the Council are continuously reviewed and updated. (ii) That it be recommended that the Economic Downturn risk (LCR 0012) be replaced by the Government spending policy risk (KCR 0022) and that a new Corporate Performance risk be added to the KCRs and taken to the Executive for approval. 1 REASON: To provide assurance that key risks are being regularly reviewed and updated to reflect the constantly changing environment in which the Council operates. (iii) That a more detailed risk report in respect of Fairness and Inclusion be brought to the Committee in September 2010. 2 REASON: To provide assurance that key corporate strategy is being delivered and embedded across the organisation.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present to Audit & Governance Committee (A&G) the current position of the risks associated with the Key Corporate Risks (KCRs) as at the end of June 2010.
Background
2. The KCRs are reported to both Audit & Governance Committee (A&G) and CMT on a quarterly basis as part of the council’s overall governance arrangements. The KCRs are regularly reviewed at Corporate Leadership Group (approximately every two years) and on an ongoing basis as part of the quarterly monitoring sessions at A&G and CMT.
3. CMT as part of this process have identified the requirement to add a new KCR in respect of the current Government spending policy and this has been included at Annex B along with comments on the current key risk position at paragraph 5. The inclusion of this new risk allows for the removal of KCR 0012 (Effects of the Economic Downturn). A further new risk has also been highlighted in relation to corporate performance and this is set out in more detail at paragraph 7.
Monitor One
4. Annex A provides a new summary sheet, which highlights the changes in the risks reported under each of the KCR focus areas since the last monitor. The position of the KCRs as at the end of June 2010 are set out at Annex B and confidential Annex C of this report. The monitor is complete in terms of accurately reflecting the information recorded in the council’s risk register (Magique) however, there is an on-going requirement for risk owners to ensure their risks are accurate, complete and up-to-date.
5. Whilst A&G can review the monitor (Annex B & C) in its entirety the 5 Critical risks and an update on the administrative accommodation planning risk are set out below with the risk owners up to date views on the situation:
KCR 0003 Waste Management Strategy Partnership
Termination of the project
"The City of York Council and North Yorkshire County Council will be presenting a report to Members in September / October which will provide Members with the opportunity to award a contract to build a facility that can deal with the authorities waste over the next 25 years. At this point it will be possible to review the status of this particular risk."
KCR 0016 Capital Programme
Failure to deliver York Sports Village
"The York Sports Village project has now been approved by the both the University and the Council’s Executive. It is intended that the project starts on site in early 2011. This is subject to full Council agreeing the allocation of an additional £1m of capital to the project in order to complete the necessary funding package. Principal risks remaining will then be associated with i) obtaining planning approval, and ii) meeting the external funding body's criteria in order that the £1m of external funding allocated to the project in principle can be released."
Failure to obtain funding for Access York Phase 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.