Updates on Recommendations Arising from Previous Scrutiny Reviews
NotedScrutiny4 papers
Economic Development and Transport Policy and Scrutiny Committee noted this item on Tuesday 5 April 2011. Below is the council's own wording, with the papers it was decided on.
(i) That the report be noted. (ii) That the remaining recommendations from the Guidance for Sustainable Development scrutiny review be signed off as complete these being; 3,4,5,12,13,14,15,16,17, 19, 21 and 25 (iii) That the remaining recommendations 1(i),2 ,4(i), 4(ii), 5 and 5(i) from the Planning Enforcement scrutiny review be signed off as complete. REASON: To raise awareness of recommendations arising from previous scrutiny reviews.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Economic Development and Transport Policy and Scrutiny Committee
Economic & City Development Overview & 5th April 2011 Scrutiny Committee Report of the Assistant Director Governance & ICT
Update on Implementation of Recommendations of Previous Scrutiny Reviews
Summary 1. This report provides Members with updated information on the implementation of recommendations made as a result of previously completed scrutiny reviews on Guidance for Sustainable Development (Annex A) and Planning Enforcement (Annex B).
Background 2. In the past the Scrutiny Management Committee (SMC) had monitored the implementation of recommendations arising from Scrutiny Reviews. Under the new scrutiny structure responsibility for this falls with the individual scrutiny committees.
Consultation 3. Relevant officers have provided updated information on the recommendations arising from the reviews and will be in attendance at the meeting to answer any questions.
Options 4. With regard to Annexes A and B, Members may choose to do one, some or all of the suggestions below:
a. Sign off those recommendations where implementation has been completed
b. Request further updates to clarify any outstanding recommendations
Analysis 5. The review on Guidance on Sustainable Development was completed in October 2006. Members of SMC had signed off some of the recommendations already and this report presents updated information on those that are still outstanding. The update on the implementation of the recommendations is provided at Annex A to this report.
6. Members last considered this at a meeting on 28th September 2010 when they noted that the Guidance for Sustainable Development scrutiny review was intrinsically linked with the Local Development Framework. As work was still ongoing with this at that time, the Committee did not feel that they were in a position to sign any of the recommendations off and agreed to add this back to the work plan for reconsideration in 2011.
7. As part of the update on the Guidance for Sustainable Development scrutiny review (Annex A refers) the Head of Design, Conservation and Sustainable Development has also provided the following comments:
‘The scrutiny process is an invaluable part of the Council's governance arrangements and many useful improvements have been made to policy and practice through its operation. In this case though the queries date back to 2007 and whilst I appreciate that a number have already been signed off we need to see the remaining points in the following context:
o The final draft of the Local Development Framework (LDF) Core Strategy has now been completed (Feb 2011) o The Interim Planning Statement (IPS) on Sustainable Development is being used to inform Development Management decision making o We have a Renewable Energy Viability Study as part of the LDF evidence base o PPS 5 Planning for the Historic Environment includes Policy HE 1 on Climate Change and promotes appropriate adaptation of Historic Buildings. o The Council Executive / Without Walls Partnership Board have agreed a Climate Change Framework and Action Plan for the City which will be published in April 2011
All of these directly address the concerns identified by the scrutiny review - I wonder therefore whether it is possible to close or agree a timeframe for closing this particular review.’
8. The review of Planning Enforcement was completed in May 2009. This Committee has already signed off, as complete, several of the recommendations arising from the review. The update on the implementation of the remaining recommendations is provided at Annex B to this report.
Corporate Strategy 2009/12 9. The process of monitoring the implementation of approved recommendations helps us to be an ‘Effective Organisation’.
Implications 10. There are no known Financial, Human Resources, Equalities, Legal, ITT or other implications associated with the recommendations in this report. Risk Management 11. In compliance with the Council’s risk management strategy, there are no known risks associated with this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.