Resolved
That the report be noted. REASON: To update the scrutiny committee of the latest finance and performance position.
Economic Development and Transport Policy and Scrutiny Committee noted this item on Tuesday 5 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. REASON: To update the scrutiny committee of the latest finance and performance position.
1. This report provides details of the 2010/11 forecast outturn position for both finance and performance in City Strategy and Housing Services.
Analysis
Finance – forecast outturn overview General Fund
2. The current outturn position within the City Strategy Directorate is a projected overspend of £+588k on a total net budget of £8,214k. The Housing General Fund has a budget of £1,513k and is expected to underspend by £-30k. Service Plan Variations by service plan are shown below:
Net Projected Variance Budget Outturn £'000 £'000 £'000 City Strategy Directorate City Development & Transport 4,254 4,165 -89 Planning & Sustainable Development 1,358 1,593 +235 Director’s Group -347 103 +450 Economic Development 2,205 2,125 -80 Property 600 816 +216 Reserve transfer 400 0 -400 More for York savings target -256 0 +256 Total 8,214 8,802 +588 Housing Services Housing General Fund 1,513 1,483 -30
Note: ‘+’ indicates an increase in expenditure or shortfall in income ‘-‘ indicates a reduction in expenditure or increase in income
3. Details of the main variations by service plan are detailed in the following paragraphs.
City Development and Transport (£-89k)
4. Car Parking income is forecast to be £+308k below budget which is made up of £+79k short stay, £+207k standard stay, £+27k on-street offset by net £-5k surplus on Respark and season tickets. 5. There is an underspend of £-69k on employee costs within School Crossing Patrols and Transport Planning where a number of posts were unfilled in the first part of the year, £52k savings within Network Management, mainly due to additional income from utilities, and a further £-23k from a vacancy in Emergency Planning.
6. There are expected to be £+5k additional consultation costs in preparing the LTP3, however this is offset by £-12k saving in new residents parking zone due to low demand, £-150k saving on concessionary fares, £-60k saving in public transport and £-30k capital scheme funding.
Planning and Sustainable Development (£+235k)
7. The economic downturn has continued to have a significant impact income within the Planning Service. The planning income projected shortfall is £+130k due to low numbers of major scheme applications, but an improvement on the £+500k reduction in income reported last year. This is offset by £-17k staff saving due to restructuring the team and £-35k legal costs.
8. Income from building control is projected to be a further £+230k below budget and there is £21k More For York cost of mobile working, offset by £-63k staff savings. Income from local searches is expected to be £+45k below budget due to low activity in the housing market, also offset by £-44k staff savings.
9. Design & Conservation have £-10k staff saving and £-10 saving in maintenance
Director’s Group (£+450k)
10. The primary reason for this projected overspend is the lower than expected dividend from Yorwaste (£+400k) due to a continuing difficult trading conditions and also the need to write-off a failed investment. In addition, there are additional costs (£+119k) incurred in delivering the Waste Project with North Yorkshire County Council. This is offset by £-69k staff saving across the service area.
Economic Development (£-80k)
11. Officers have carried out a detailed review of markets and city centre budgets and have realigned the budgets accordingly. Income has improved and a surplus of £-40k is expected together with £-40k saving in salaries and overheads. Other budgets for Science City, Tourism and Inward Investment relate to guaranteed contributions to partner organisations that deliver the service.
Property Services (£+216k)
12. The main variation within Property Services is that Commercial property income is expected to be £+181k below budget, linked to not receiving wayleave income at Harewood Whin and from lost income due to property sales.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter 3 Monitoring ReportReport | 89 KB | DownloadRead as text |
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 May 2017 | MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... | Approved | Open |
| 10 May 2017 | Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... | Noted | Open |
| 10 May 2017 | Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. | Noted | Open |
| 10 May 2017 | Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... | Noted | Open |
| 10 May 2017 | Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.