Key Corporate Risk Monitor 4.

Noted Finance 5 papers

Audit and Governance Committee noted this item on Tuesday 19 April 2011. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

(i)That Members considered the risks set out at Annex B and C and paragraph 8 of the report. (ii)That the following risks be reviewed in more detail at the next meeting, particularly in relation to target dates: · Risk Ref 1796, 1798 and 1799. 1 (ii)That Members noted the risks reports presented in respect of Bullying and Harassment, York Community Stadium, Administrative Acccomodation Project and iTrent Payroll System. REASON: (i)To provide assurance that risks to the council are continuously monitored. (ii)To provide assurance that risks to the council are continuously monitored (iii)To provide assurance that key risks to the council are being properly managed.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

1. The purpose of this paper is to present to Audit and Governance Committee (A&G) the current position of the risks associated with the Key Corporate Risks (KCRs) as at the end of February 2011.

Background

2. The KCRs are reported to both the A&G and Corporate Management Team (CMT) four times a year as part of the council’s overall governance arrangements. The KCRs are regularly reviewed and updated at CMT, A&G and also at Directorate Management Teams (DMT’s).

Risk Overview

3. Since monitor 3 the key changes to note is that under the KCR “Financial Pressures” the risk in relation to “Reduction in Revenue Budgets” has had its score increased to Critical (Paragraph 8 of this report provides some high level context in relation to this risk). Within the detailed risk register itself (Magique) there are further associated risks at Directorate level that provide some of the more operational challenges including the scale of the savings required to be met within the Directorates, the financial risk due to the reliance on high income from a few service areas, and external environmental issues including the increase in fuel costs and the tough market conditions for the council’s externally traded services.

4. At the same time there is more positive news in relation to key risks including Fairness & Inclusion, Waste Strategy and the Local Government Pension scheme where the council is successfully managing and reducing the level of risk. More background from the relevant risk owners is provided at Paragraph 10.

5. At monitor 3 the critical risk in relation to the York Sports Village was removed as the University had set a date for starting the project, outline planning permission had been received and the funding was in place. As full planning permission has now been formally received the two remaining risks have been removed at monitor 4. In addition the risk in relation to the Barbican has also been removed as refurbishment work is underway and the opening is planned for the third week in May 2011.

6. The risks in relation to the More for York programme reported as KCR 0017 within the monitor are undergoing a fundamental review and are not included in Annex B at monitor 4.

Monitor Four

7. Annex A provides a summary sheet, which highlights the movement in the risks reported under each of the KCR focus areas since the last monitor. The position of the KCRs as at the end of February is set out at Annex B and confidential Annex C of this report. The monitor is complete in terms of accurately reflecting the information recorded in the council’s risk register (Magique) however, there is an on-going requirement for risk owners to ensure their risks are accurate, complete and up-to-date.

8. Whilst A&G can review the monitor (Annex B & C) in its entirety the three Critical risks are set out below with the risk owners’ up to date views on the position:

KCR 0016 Capital Programme

Failure to obtain funding for Access York Phase 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 51 KB Download
PDF
v3Appendix B 101 KB Download
PDF
LA Anti-bullying policyAppendix D 716 KB Download
PDF
Abusive parents policy LA versionAppendix E 89 KB Download
PDF
Key Corporate Risk Monitor 4.Report 109 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
RM
Councillor Richard MooreAttendee, in attendance
BW
Councillor Brian WatsonChair, present
JB
Councillor Jenny BrooksVice-Chair, present
PF
Councillor Paul FirthCommittee Member, present
KH
Councillor Keith HymanCommittee Member, present
DS
Councillor David ScottCommittee Member, present
CV
Councillor Christian VassieCommittee Member, apologies
JG
Councillor Julie GunnellCommittee Member, present

On this subject at York

Search all
  1. Key Corporate Risk Monitor 4.This decision
  2. Key Corporate Risk Monitor 1 (18:03)Noted
  3. Key Corporate Risks monitor 4 (17:51)Noted
  4. Key Corporate Risks monitor 3 (18:54)Noted
  5. Key Corporate Risks monitor 2 (17:54)Noted
  6. Key Corporate Risks monitor 1 (17:45)Decided

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies