(i)That Members considered the risks set out at Annex B and C and paragraph 8 of the report. (ii)That the following risks be reviewed in more detail at the next meeting, particularly in relation to target dates: · Risk Ref 1796, 1798 and 1799. 1 (ii)That Members noted the risks reports presented in respect of Bullying and Harassment, York Community Stadium, Administrative Acccomodation Project and iTrent Payroll System. REASON: (i)To provide assurance that risks to the council are continuously monitored. (ii)To provide assurance that risks to the council are continuously monitored (iii)To provide assurance that key risks to the council are being properly managed.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present to Audit and Governance Committee (A&G) the current position of the risks associated with the Key Corporate Risks (KCRs) as at the end of February 2011.
Background
2. The KCRs are reported to both the A&G and Corporate Management Team (CMT) four times a year as part of the council’s overall governance arrangements. The KCRs are regularly reviewed and updated at CMT, A&G and also at Directorate Management Teams (DMT’s).
Risk Overview
3. Since monitor 3 the key changes to note is that under the KCR “Financial Pressures” the risk in relation to “Reduction in Revenue Budgets” has had its score increased to Critical (Paragraph 8 of this report provides some high level context in relation to this risk). Within the detailed risk register itself (Magique) there are further associated risks at Directorate level that provide some of the more operational challenges including the scale of the savings required to be met within the Directorates, the financial risk due to the reliance on high income from a few service areas, and external environmental issues including the increase in fuel costs and the tough market conditions for the council’s externally traded services.
4. At the same time there is more positive news in relation to key risks including Fairness & Inclusion, Waste Strategy and the Local Government Pension scheme where the council is successfully managing and reducing the level of risk. More background from the relevant risk owners is provided at Paragraph 10.
5. At monitor 3 the critical risk in relation to the York Sports Village was removed as the University had set a date for starting the project, outline planning permission had been received and the funding was in place. As full planning permission has now been formally received the two remaining risks have been removed at monitor 4. In addition the risk in relation to the Barbican has also been removed as refurbishment work is underway and the opening is planned for the third week in May 2011.
6. The risks in relation to the More for York programme reported as KCR 0017 within the monitor are undergoing a fundamental review and are not included in Annex B at monitor 4.
Monitor Four
7. Annex A provides a summary sheet, which highlights the movement in the risks reported under each of the KCR focus areas since the last monitor. The position of the KCRs as at the end of February is set out at Annex B and confidential Annex C of this report. The monitor is complete in terms of accurately reflecting the information recorded in the council’s risk register (Magique) however, there is an on-going requirement for risk owners to ensure their risks are accurate, complete and up-to-date.
8. Whilst A&G can review the monitor (Annex B & C) in its entirety the three Critical risks are set out below with the risk owners’ up to date views on the position:
KCR 0016 Capital Programme
Failure to obtain funding for Access York Phase 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.