i) That the Draft York Central Historic Core Conservation Area Appraisal be approved for public consultation. 1. ii) That approval be given to the proposed consultation methods outlined in paragraphs 14 to 16 of the report subject to the addition of social media eg. Twitter and Facebook in an effort to engage with hard to reach groups. 2. iii) That the Chair, Vice Chair and Councillor Merrett be delegated authority to agree any outstanding changes to the Appraisal and oversee the final document. 3. REASON: i) The document has adopted a rigorous approach to the assessment of the York Central Historic Core Conservation Area, and is in accordance with relevant guidance documents; ii) The boundary review has been carried out in accordance with the Planning (Listed Buildings and Conservation Areas) Act 1990 and the latest guidance documents from English Heritage; iii) The document has been subject to intensive peer review through the key stakeholder group; iv) The proposed consultation process is based on previous best practice.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Assistant Director City Strategy (Planning and Sustainable Development)
York Central Historic Core Conservation Area Appraisal: Consultation Draft Summary 1. Conservation areas are ‘areas of special architectural or historic interest the character or appearance of which it is desirable to preserve or enhance’. To enable City of York Council to better discharge its statutory responsibilities in this regard Alan Baxter Associates were appointed to undertake a detailed appraisal of the York Central Historic Core Conservation Area; including analysis of key strategic long distance and local views, in December 2010. The appraisal is jointly funded by English Heritage and City of York Council and is an important component of the evidence base for the City of York Local Development Framework. The draft document has benefited from detailed input from a key stakeholder group, and has now reached the stage of a public consultation draft. Members are asked to approve the York Central Historic Core Conservation Area Appraisal – Consultation Draft - (Annex 4) for public consultation.
Background 2. The York Central Historic Core Conservation Area was first designated in 1968 and extended in 1975 following public consultation. The boundaries have not been reviewed since that time and no detailed appraisal of character and special interest has been carried out.
3. Section 69 of the Planning (Listed Buildings and Historic Areas) Act 1990 requires local planning authorities to designate as conservation areas any ‘areas of special architectural or historic interest the character or appearance of which it is desirable to preserve or enhance’. In addition, authorities are required to carry out periodic reviews of the conservation areas under their control.
4. Section 71 of the same Act requires local authorities to formulate and publish proposals for the preservation and enhancement of conservation areas and to submit them to a public meeting for consideration. Following designation the local authority, in exercising its planning powers, must pay special attention to the desirability of preserving or enhancing the character or appearance of a conservation area (Section 72 of the Act).
5. The lack of an appraisal of the York Central Historic Core Conservation Area was identified as a key weakness of the evidence base for the Local Development Framework to inform the policies and proposals of the City Centre Area Action Plan and other Development Plan Documents and Supplementary Planning Documents.
6. York’s Central Historic Core Conservation Area is a large and complex conservation area. Completing a comprehensive appraisal is a significant undertaking and has required a significant commitment by the council. The appraisal has to go beyond mere description in capturing the very essence of the special character and interest of the area and explaining its value and significance.
7. Funding for this work was formally secured in February 2010 including a 50% grant from English Heritage.
8. Following a detailed tender process, Consultants Alan Baxter Associates were appointed in December 2010 to undertake the appraisal. Work commenced immediately.
9. The project is managed through the Renaissance Team by the Heritage Renaissance Officer reporting to a Project Management Team including English Heritage and Officers from Design, Conservation and Sustainable Development.
10. The Appraisal is divided into two parts. Part one deals with understanding the City, including a detailed assessment of twenty-four character areas and an analysis of key views and building heights. Part two deals with management recommendations setting out informed proposals for further work and action.
11. An Executive Summary is provided with this report as Appendix 1.
12. The most significant and immediate of the reports recommendations include suggestions for
a. Changes to the Conservation Area boundary at seven locations, five extensions and two reductions;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.