City Strategy Capital Programme - 2011/12 Consolidated Report
AgreedExecutive3 papers
Decision Session - Executive Member for Transport - Expired agreed this item on Tuesday 26 July 2011. Below is the council's own wording, with the papers it was decided on.
That the Cabinet Member agrees to: i) Approve the carryover schemes and adjustments set out in Annexes 1 and 2 of the report. ii) Approve the increase to the 2011/12 City Strategy capital budget, subject to the approval of the Cabinet. REASON: To enable the effective management and monitoring of the council’s capital programme. That the Cabinet Member agrees to: i) Approve the carryover schemes and adjustments set out in Annexes 1 and 2 of the report. 1. ii) Approve the increase to the 2011/12 City Strategy capital budget, subject to the approval of the Cabinet. 2. REASON: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired
Decision Session – Cabinet Member for City 26 July 2011 Strategy
Report of the Director of City Strategy
City Strategy Capital Programme – 2011/12 Consolidated Report
Report Summary
1. This report identifies the proposed changes to the 2011/12 City Strategy Capital Programme to take account of carryover funding from 2010/11, and to include additional funding from the Local Sustainable Transport Fund (LSTF) and other sources. 2. The report also proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections. Further changes will be made at future Decision Sessions as the implications of the LSTF funding are confirmed and coordination with the maintenance programme is developed. Recommendations
3. The Cabinet Member is requested to: i) Approve the carryover schemes and adjustments set out in Annexes 1 and 2. ii) Approve the increase to the 2011/12 City Strategy capital budget, subject to the approval of the Cabinet. Reason: To enable the effective management and monitoring of the council’s capital programme. Background
4. The City Strategy Capital Programme budget for 2011/12 was confirmed as £1,999k at Full Council on 24 February 2011. This includes the Integrated Transport & City Walls schemes, and is funded through £1,549k of Local Transport Plan (LTP) funding, £300k funding from developer contributions, and £150k CYC funding.
5. The Accommodation Review and the Stadium schemes being progressed by the City Strategy Directorate are reported separately. 6. Table 1 shows the current approved capital programme.
Table 1: Current Approved Capital Programme Gross External Capital Budget Funding* Receipts £000s £000s £000s Planning & Transport 1,999 1,849 150 Current Approved City 1,999 1,849 150 Strategy Capital Programme *External funding refers to government grants, non government grants, other contributions, developer contributions and supported capital expenditure.
Summary of Key Issues
7. As stated in the 2011/12 Budget Report, the LTP Integrated Transport funding available for future years is significantly lower than previous allocations, with £1,549k available in 2011/12 compared to £2,986k at the start of 2010/11. 8. A number of schemes were not completed at the end of 2010/11, and need to be added to the 2011/12 programme. However, due to the underspend at the end of 2010/11, there is £721k of funding to be carried forward, which will be used to fund the completion of the carryover schemes from 2010/11. There is also £257k additional funding from developer contributions and grants, and £44k of additional CYC funding following a successful CRAM bid. 9. It was announced on 5 July 2011 that the council’s bid for additional funding from the Local Sustainable Transport Fund (LSTF) had been successful, and £4.645m has been awarded to improve sustainable transport in the city over the next four years. This includes both capital and revenue funding, and £189k of additional capital funding has been added to the 2011/12 capital programme. This will fund several public transport, walking, and cycling schemes in 2011/12. Development of the key projects planned for delivery later in the LSTF programme such as the provision of a new cycle route between Haxby Road and Clifton Moor will also be commenced in 2011/12. 10. A review of the proposed programme has been carried out to take account of the carryover schemes and funding, and details of the Safety Schemes programme and Safe Routes to School programme have been added. 11. The current approved budget and proposed adjustments are indicated in Table 2. Additional information, including details of the proposed changes to scheme allocations, is provided in the Annexes to the report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.