i. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictions required by all design options; ii. Noted the Executive Members preference for scheme A; iii. Officers were requested to expand the scope of the project to include the traffic signals, particularly for cyclists, at the junction of Hospital Fields Road and Fulford Road. iv. Officers were asked to review how the cycle lane interfaces with the advance stop line especially for cyclists going straight on from Hospital Fields Road. v. Development of the scheme to be brought back to a future decision session before progressing to a detailed design stage. Reason: To respond to the comments made by the public to improve safety. i. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictions required by all design options; ii. Noted the Executive Members preference for scheme A; iii. Officers were requested to expand the scope of the project to include the traffic signals, particularly for cyclists, at the junction of Hospital Fields Road and Fulford Road. iv. Officers were asked to review how the cycle lane interfaces with the advance stop line especially for cyclists going straight on from Hospital Fields Road. v. Development of the scheme to be brought back to a future decision session before progressing to a detailed design stage. Reason: To respond to the comments made by the public to improve safety.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 20 pages
Summary
1. In February 2022, The Executive Member of Transport approved the proposed Hospital Fields Road project outline as part of the Active Travel Programme, refer to Annex K.
2. A further report was taken to Executive in November 2022 (refer to Background Paper 1), which approved the prioritisation of phase 1 projects within the Active Travel Programme, this included Hospital Fields Road.
3. The objective for the Hospital Fields Road scheme is to investigate the potential for segregated cycle facilities between the off-road path at the western end and the Fulford Road junction at the eastern end.
4. Four preliminary designs have been prepared to deliver segregated cycle facilities on Hospital Fields Road between the Millennium Bridge - New Walk (off-road path) and Fulford Road / Barracks off-road path to University of York).
5. A public consultation took place between November and December 2022.
6. This Executive report summarises the findings received in the public consultation period. An analysis of the public consultation has been undertaken.
7. This report proposes options for delivery of the scheme and requests a decision to confirm which proposal will be delivered. Recommendations
9. The Executive Member is asked to:
a. Select a preliminary scheme to proceed to detailed design stage and construction of the scheme as detailed within this report, and in line with the preliminary designs included within the Annex taking into consideration the reduction of the footpath width, introduction of parking restriction and the impact the scheme has on protected characteristics identified in the Equalities Impact Assessment.
Reason: To deliver the schemes aims and objectives within the available budget.
b. Approve the advertisement of amendments to the Traffic Regulation Order (TRO) to extend ‘No Waiting at any time’ restrictions to cover both sides of Hospital Fields Road for the full length.
c. Delegate authority to Director of Environment, Transport and Planning to approve Detailed Design of the scheme selected by The Executive Member for Transport.
Reason: This will provide the necessary approval to advertise proposal to remove parking and follow the Statutory Consultation TRO process. Any objections received to the Statutory Consultation to be reported back to Executive Member for Transport Decision Session.
Background
10. The Active Travel Programme consists of 24 no. individual projects focussed on improvements to pedestrian and cycling provision in the city, as part of the Council’s wider commitment to enhancing sustainable travel in the city and addressing the climate emergency.
11. In February 2022, the Executive Member of Transport approved the Hospital Fields Road project outline, refer to Annex K.
12. A further report was taken to Executive in November 2022. The report provided a summary of the Active Travel Programme and prioritised projects for delivery. 13. The Hospital Fields Road project outline is to investigate the potential for segregated cycle facilities between the off-road path at the western end and the Fulford Road junction at the eastern end.
14. Hospital Fields Road forms an important part of the East-West cycle route and currently has minimal facilities for cyclists. The introduction of segregated cycle facilities will fill a key gap on this important strategic route which links the University of York to the Millennium Bridge.
15. The scheme meets the York Council priorities of “getting around sustainably” and “provide a greener and cleaner city”.
16. The Hospital Fields Road scheme is capital funded by City of York Council.
17. The 4 no. proposed preliminary drawings are as follows:
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.