City of York Council
Executive, Tuesday 6 September 2011 at 5.30pm

Access York Phase 1 Best & Final Bid submission

Approved Executive 3 papers

Executive approved this item on Tuesday 6 September 2011. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

( i ) That Staffing & Urgency Committee be recommended to approve: a) The progression of Option 2b ( Askham Bar & Poppleton Bar), with approx. 30% local contribution. b) The funding approach identified in Option 2b in Table 1 in Annex 2. c) The allocation of £3.305m from within the Council’s existing capital programme. d) An increased allocation of LTP grant funding (up to £0.7m) to the scheme as part of the local contribution, with the expectation that additional developer contributions will be used when received. e) The use of £2.2m from the New Homes Bonus and / or prudential borrowing, with the actual split to be determined at a later date, with a commitment to fund any shortfall in funding prudential borrowing, and to meet any consequent revenue implications that arise. f) The use of the £350k value of the Sim Hills tip site as part of the Council’s contribution. (ii) That Staffing & Urgency Committee be recommended to note: a) the additional risk to the Council, such as funding all cost over-runs, which result from the changes to the DfT funding processes and b) the increase revenue risk from operating additional Park & Ride services. REASON: To maximise the likelihood of a successful bud for funds from the DfT. (iii) That Cabinet record its commitment to achieve the future development of the Clifton Moor site for Park & Ride, separately from the Access York bid process. REASON: In view of the importance of this site. (i) That Staffing & Urgency Committee be recommended to approve: a) The progression of Option 2b (Askham Bar & Poppleton Bar), with approx. 30% local contribution. b) The funding approach identified in Option 2b in Table 1 in Annex 2. c) The allocation of £3.305m from within the Council’s existing capital programme. d) An increased allocation of LTP grant funding (up to £0.7m) to the scheme as part of the local contribution, with the expectation that additional developer contributions will be used when received. e) The use of £2.2m from the New Homes Bonus and / or prudential borrowing, with the actual split to be determined at a later date, with a commitment to fund any shortfall in funding prudential borrowing, and to meet any consequent revenue implications that arise. f) The use of the £350k value of the Sim Hills tip site as part of the Council’s contribution. (ii) That Staffing & Urgency Committee be recommended to note: a) the additional risk ... view the full minutes text for item 36.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. This report requests that Cabinet recommends for approval by the Staffing Matters and Urgency Committee the submission of the ‘Best and Final Bid’ for the Access York Project to the Department for Transport (DfT) on 9th September 2011. 2. Phase 1 of the Access York project to enhance the Park & Ride network is critical for the future economic prosperity and environmental wellbeing of the city. In recognition of the reduced national budget available and to maximise the likelihood of bid being successful it is considered necessary to make changes to the scope, programme or funding arrangements of the project. 3. Owing for the need to amend the Council’s Capital Programme and the 9 September deadline final approval of the proposed submission needs to be by the Staffing and Urgency Committee. 4. Members are provided options to package the sites and alternative funding options to meet projected 20% and 30% target local contribution levels.

• Option 1 -- 3 Site Option with additional £6m of Council Funding (Total £9.7m)

• Option 2 – 2 Site Option (Askham Bar and Poppleton Bar) with additional Council funding of £0.7m or £2.9m (Total £4.4m or £6.6m)

• Option 3 – 2 Site Option (Poppleton Bar & Clifton Moor) with additional funding of 1.0m or £2.7m (Total £3.7m or £5.4m)

5. Funding sources for the 3 options are identified and Members are requested to recommend approval of one of these options and the provisional funding allocations to the Staffing and Urgency Committee to enable the bid to be submitted by 9th September.

Background 6. Expanding the Park & Ride network is a key Council Plan priority under the ‘Get York Moving’ banner. Additional Park & Ride capacity will

• Provide a high quality alternative to the car • Address congestion which is seen as the key constraint on York’s growth – a consistent and prominent message from businesses • Reduce emissions and address air quality issues in the city • Build on the success of the current P&R provision which currently caters for 4.3m passenger boardings each year (3 million pure P&R boardings) and removes over 1 million cars per year from the city centre network

7. The existing Park & Ride service has insufficient capacity to keep pace with York’s buoyant and growing economy. The full Access York Phase 1 project involves:

• the construction of 3 new Park & Ride sites at Askham Bar, A59 near Poppleton and Clifton Moor, • a major upgrade to the A59/A1237 Outer Ring Road roundabout, • associated bus priority measures, • procurement of the Park & Ride operator. 8. The number of Park & Ride sites in the City would be increased from 5 to 7 with over 40% more parking spaces. It is anticipated that an additional half a million cars per annum will be removed from York’s road network reducing Carbon emissions by over 2000 tonnes per year.

9. The project has a long approval history:

• Submission to Regional Transport Board --February 2008 • Approval of Regional Transport Board – April 2008 • Submission of Major Scheme Bid to DfT – Feb 2009 • Approval of DfT (Programme Entry) – March 2010 10. The coalition government suspended the Major Projects process in June 2010 with the scheme confirmed to be in the ‘Development Pool’ of 45 Major Schemes in October 2010. An Expression of Interest was submitted by the Council in January 2011 confirming the continued commitment to the project. 11. Planning consent has been obtained for all of the sites and the acquisition of the land secured. Owing to the funding uncertainties detailed design work has been suspended on all of the sites except Askham Bar.

12. A Best and Final bid must now be submitted to the DfT by 9th September with an expectation that a decision will be received by the end of 2011.

The Original Bid 13. The key facts for the original Major Scheme Bid to the DfT for all 3 sites were:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Access York Annex 1Appendix 57 KB Download
PDF
Access York Annex 2 fvAppendix 45 KB Download
PDF
Access York Phase 1 Best & Final Bid submissionReport 136 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
RP
Councillor Ruth PotterCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
BW
Bill WoolleyOfficer, expected

On this subject at York

Search all
  1. Access York Phase 1 Best & Final Bid submissionThis decision
  2. Healthwatch York Reports: GP Surgeries in York: Accessibility Audit Findings and GP Practice Websites in York: Audit Findings (6:19pm)Decided
  3. York Christmas Market 2024 and Blue Badge AccessNoted
  4. Healthwatch York Report: Accessible Information Update ReportDecided
  5. Joint Report from Healthwatch North Yorkshire & Healthwatch York: Accessible Information (17:53)Decided
  6. Access Way Between 4 And 6 Howard Street, York [21/01085/FUL]Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies