City of York Council
Executive, Tuesday 3 November 2026 at 4.30pm

Capital Programme Monitor Update 2 Report (4:47pm)

Noted Executive 3 papers

AI summaryCity of York Council Executive unanimously recommended a £2.584m reduction to the 2026/27 capital budget and noted a revised total of £105.398m. [D] [P17] It also approved £2 million in MEND funding and agreed an open market disposal at The Glen at Ousecliffe Gardens. [D] [P14]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital budget £105.398m; museum and disposal approvals [D] [P17]
Money£2.584m reduction proposed [D] [P17]Budget £105.398m; museum £2 million; Council contribution £140k [D] [P17] [P14] [P83]
What happens nextNot stated
Who it affectsNot stated

What was decided

Executive unanimously recommended to Full Council adjustments that reduce the 2026/27 budget by £2.584m. It noted the revised budget of £105.398m and the restated capital programme for 2026/27 to 2029/30. Report P10, P17, P20

Executive agreed to dispose of The Glen at Ousecliffe Gardens on the open market. It noted Willmott Dixon and Cityheart as the Strategic Delivery Partner and the funding allocated for scheme development. Report P12, P14, P67, P68

Executive approved the Council accepting £2 million in MEND funding from ACE as the direct recipient, with York Museums Trust procuring and delivering the scheme, and approved a 20 year Deed of Covenant, title restrictions for the Yorkshire Museum and Museum Gardens, a Certificate of Title where the Council can properly provide one, and a Collaboration Agreement with York Museums Trust. It noted a revised Council match funding contribution of £140k and delegated authority to finalise and execute documents to the Director of City Development, in consultation with the Director of Governance and Director of Finance. It also delegated approval and execution of changes or extensions that are not material, with the Director of Governance and Chief Finance Officer, provided financial and legal exposure would not materially increase. Report P14, P82, P83

Why

The budget changes are intended to support effective management and monitoring of the capital programme. Report P11

The property sale is intended to dispose of surplus property under the asset management strategy and reduce the Council's financial obligations. Report P13

Accepting the museum funding with legal, financial and governance safeguards is intended to let the Yorkshire Museum Capital Scheme proceed. Report P15

What happens next

Full Council will consider the recommended budget adjustments, which produce a £2.584m reduction and a revised £105.398m budget. Report P10, P17

The Council will dispose of The Glen at Ousecliffe Gardens on the open market. The housing partnership will progress Ordnance Lane and Willow House through RIBA Stage 4, with full business cases considered in early 2027. Report P12, P68

York Museums Trust will procure and deliver the scheme. The Council will pass the MEND funding to York Museums Trust, monitor delivery and submit quarterly claims to ACE. The Director of City Development, in consultation with the Director of Governance and Director of Finance, will finalise and execute the documents. Report P14, P82

The money

  • £2.584m Recommended reduction in the 2026/27 capital budget Report P17
  • £105.398m Revised 2026/27 capital budget Report P17
  • £457.722m Revised five year capital programme Report P20, P21
  • £2 million ACE MEND funding for the Yorkshire Museum scheme Report P81, P82
  • £140k Revised Council match funding contribution for the first museum phase Report P83
  • £1,440K Maximum housing capital expenditure for the two initial housing schemes Report P68
  • £193.901m External funding for the revised five year capital programme Report P21
  • £263.821m Internal funding for the revised five year capital programme Report P21

Options considered

  • Chosen: Reduce the 2026/27 capital budget by £2.584m. To support effective management and monitoring of the capital programme. Report P11, P17
  • Chosen: Dispose of The Glen at Ousecliffe Gardens on the open market. To dispose of surplus property and reduce the Council's financial obligations. Report P13
  • Chosen: Accept £2 million MEND funding directly, with York Museums Trust delivering the scheme. To allow the scheme to proceed with appropriate legal, financial and governance safeguards. Report P15, P82

Implications

  • Financial: The revised capital programme for 2026/27 to 2029/30 totals £457.722m. It is funded by £193.901m of external funding and £263.821m of internal funding. Report P21
  • Legal: The Council will enter a 20 year Deed of Covenant and a title restriction for the Yorkshire Museum and Museum Gardens. Report P82
  • Financial: The Council's revised contribution for the first museum phase is £140k. Report P83
  • Risk: Changes to museum documents must not materially increase the Council's financial or legal exposure. Report P14
  • Financial: The capital programme involves significant Council borrowing, which affects revenue expenditure. Delivery depends on external funding, inflation levels and interest rates. Report P6
  • Other: York Museums Trust will procure and deliver the museum scheme and will be responsible to the Council for compliance. The Council will monitor the scheme and submit quarterly claims to ACE. Report P82
  • Financial: The open market disposal is intended to reduce the Council's financial obligations. Report P13
  • Equalities: Capital spending covers schools, housing, transport and regeneration, including disabled home adaptations and accessible walking and cycling routes. Report P5, P38, P105

Who and where

  • City of York Council Report P10
  • Full Council Report P10
  • York Museums Trust Report P82
  • Arts Council England Report P82
  • Willmott Dixon and Cityheart Report P67
  • People needing disabled home adaptations Report P38, P47
  • Pupils needing specialist school facilities Report P29, P30
  • People needing affordable housing Report P67

Timeline

  • 12 February 2026: Council approved the 2026/27 capital programme with a budget of £112.990m. Report P15
  • 9th September 2026: Monitor 1 reduced the budget by £5.008m to £107.982m. Report P16
  • October 2026: The Council entered a Development Agreement with its new Strategic Delivery Partner for an initial ten year partnership. Report P67
  • early 2027: Full business cases for the two initial housing schemes are expected for Executive consideration. Report P68
  • next round of available funds: YMT plans a further bid for urgent museum roof works, requiring a further £300K match fund if successful. Report P83
  • 3 November 2026: Executive made the capital programme, property and museum funding decisions. Report P1
  • end of January 2027: The digital switchover deadline is revised to this date. Report P41
  • during 28/29: York Outer Ring Road Phase 1A construction is expected to start and finish by the end of 29/30. Report P140

Plain English for the jargon

  • MEND: Museum Estate and Development Fund [P14]
  • ACE: Arts Council England [P14]
  • YMT: York Museums Trust [P14]
  • HRA: Approved housing capital programme resources used for scheme development [P68]
  • RIBA Stage 4: The stage before construction starts, covering design, technical advice and development management [P68]
  • YORR: York Outer Ring Road [P138]
  • BSIP: Bus Service Improvement Plan [P94]
  • WHLG: Warm Homes Local Grant [P54]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item51

Resolved

Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adjustments resulting in a reduction in the 2026/27 budget of £2.584m as detailed in the report. · Noted the 2026/27 revised budget of £105.398m as set out in paragraph 9 and Table 2 of the report. · Noted the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1 of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme. ii. In relation to The Glen at Ousecliffe Gardens: · Agreed to the disposal of the property on the open market, outlined at paragraphs 166–169 of the report. Reason: To dispose of surplus property in accordance with the asset management strategy and reduce the council’s financial obligations as appropriate. iii. In relation to the Housing Delivery Programme: · Noted the appointment of the Strategic Delivery Partner and the allocation of funding for scheme development. iv. In relation to the Yorkshire Museum Capital Scheme: · Approve the Council accepting £2 million Museum Estate and Development Fund (MEND) funding from Arts Council England (ACE) for delivery of the Scheme, noting that the Council will become the direct recipient of the funding, with York Museums Trust (YMT) procuring and delivering the Scheme; · Approve the Council entering into the funding and security arrangements required by ACE, including, subject to the conditions below, a 20-year Deed of Covenant, an appropriate restriction against the registered title to the Yorkshire Museum and Museum Gardens and such Certificate of Title as the Council is able properly to provide; · Approve the Council entering into a Collaboration Agreement with YMT governing the onward application of the MEND funding and YMT's procurement and delivery of the Scheme; · Note the revised Council match-funding contribution of £140k for this phase of the Scheme and the Council entering into the necessary funding arrangements with YMT; · Delegate authority to the Director of City Development, in consultation with the Director of Governance and Director of Finance, to finalise and execute the documents necessary to implement recommendations (i) to (iv), including any necessary ancillary documentation. · Delegate authority to the Director of City Development, in consultation with the Director of Governance and Chief Finance Officer, to approve and execute any non-material amendments or extensions necessary to deliver the Scheme, provided that they do not materially increase the Council's financial or legal exposure. Reason: To enable the Yorkshire Museum Capital Scheme to proceed while ensuring that the Council's acceptance of the MEND funding and associated funding, security and delivery arrangements are subject to appropriate legal, financial and governance safeguards.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Meeting: Executive Meeting date: 3 November 2026 Report of: Debbie Mitchell, Director of Finance Portfolio of: Councillor Katie Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equalities and Inclusion

Capital Programme – Monitor 2 2026/27

Subject of Report 1. The purpose of this report is to set out the projected outturn position for 2026/27 including any under/overspends and adjustments, along with requests to re-profile budgets to/from current and future years.

2. The Capital Monitor report is one of a number of reports taken to Executive on a regular basis to provide details of expenditure and how that impacts the financial standing of the council.

Benefits and Challenges 3. The capital programme is key in delivering the Council Plan. Members are able to prioritise capital expenditure to deliver improvements across all service areas notably Schools, Housing, Transport and Regeneration as well as supporting Climate Change ambitions.

4. The programme does involve significant levels of council borrowing which impacts the level of revenue expenditure. The cost of delivering the capital programme is therefore dependent on levels of external funding, inflation levels and interests rates. Policy Basis for Decision

5. The Capital Budget is set as part of the Council’s budget setting in February 2026. The capital programme is set alongside decisions to deliver a balanced revenue position.

Financial Strategy Implications 6. The Finance and Performance Monitor 2 report elsewhere on this agenda again outlines the council’s financial position. The identification of slippage particularly in relation to Council funding will reduce council borrowing costs and support the annual revenue expenditure.

Recommendation and Reasons 7. Executive is asked to:

a) In relation to the overall programme:  Recommend to Full Council the adjustments resulting in a reduction in the 2026/27 budget of £2.584m as detailed in the report.  Note the 2026/27 revised budget of £105.398m as set out in paragraph 9 and Table 2.  Note the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1.

Reason: To enable the effective management and monitoring of the Council’s capital programme.

b) In relation to The Glen at Ousecliffe Gardens:  Agree to the disposal of the property on the open market, outlined at paragraphs 166 - 169.

Reason: To dispose of surplus property in accordance with the asset management strategy and reduce the council’s financial obligations as appropriate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitor 2 202627–202930Appendix 1 204 KB Download
PDF
Capital Programme Monitor Update 2 Report (4:47pm)Report 585 KB DownloadRead as text
PDF
View item 51. as HTML 313 KBReport 313 KB Copy on its way

At this meeting

Whole meeting

Who was there

0 of 9 attended
CD
Councillor Claire DouglasChair, expected
RW
Councillor Robert WebbVice-Chair, expected
JK
Councillor Jenny KentCommittee Member, expected
PK
Councillor Peter KilbaneCommittee Member, expected
KL
Councillor Katie LomasCommittee Member, expected
DM
Councillor Dave MerrettCommittee Member, expected
AP
Councillor Anna PerrettCommittee Member, expected
KR
Councillor Kate RaviliousCommittee Member, expected
LS
Councillor Lucy Steels-WalshawCommittee Member, expected

On this subject at York

Search all
  1. Capital Programme Monitor Update 2 Report (4:47pm)This decision
  2. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  3. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  4. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  5. Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor Two 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open
3 Nov 2026 Decision to Widen the Conditions Relating to the City Centre Public Space Protection Order (5:30pm)Resolved (unanimously) that Executive: · Commented on and approved the creation of a new City Centre Public Space Pro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies