i ) That the key corporate risks as set out at paragraphs 5 and 6 of the report be received and noted. ii) That the directorate risks for City Strategy and Communities and Neighbourhoods as set out at Annexes A and B of the report be received and noted. REASON: i ) To provide assurance that risks to the council are continuously reviewed and updated. ii) To provide assurances that risks to the council are continuously reviewed and managed at directorate level.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present to Audit & Governance Committee (A&G) an overview of the risks associated with the councils Key Corporate Risks (KCRs) as at November 2011.
Background
2. The High and Critical KCRs are reported to A&G four times a year and at least twice a year to Corporate Management Team (CMT) as part of the council’s overall governance arrangements. The KCRs along with directorate level risks are also regularly reviewed at Directorate Management Teams (DMT’s).
Changes to the way risk are reported
3. As approved at A&G on the 26 July 2011 as well as providing an overview of High and Critically ranked KCRs each quarter the monitor now also provides directorates the opportunity to present an overview of their own High and Critical risks. This is being delivered on a rolling programme. CBSS & OCE delivered their risk reports at the last A&G committee in September 2011. The rest of the directorates will present their risks to A&G during the course of the year. The full year programme for 2011/12 is set out at Table 1 below. Table 1
A&G Committee Directorate Date
29 September 2011 - Customer & Business Support Services/Office of the Chief Executive 5 December 2011 - Community & Neighbourhoods/City Strategy 13 February 2012 - Adults Children & Education 4. T he two Directorates presenting their risk registers at monitor three are City Strategy (CS) and Communities and Neighbourhoods (CAN’s). Their overviews are set out at Annex A and B respectively.
Monitor 3
5. There has been no change in the number of critical KCRs since Monitor 2 2011/12. There are three critical risks corporately and the up to date risk owners comments are set out below:
KCR 0016 Capital Programme
Failure to obtain funding for Access York Phase 1
'The delivery risk for Access York Phase 1 is considered to be critical because the way that the government distributes funding for transport major schemes has significantly altered since the scheme obtained Programme Entry status in March 2010. The other key risks such as planning consent and land purchase have all been resolved satisfactorily but the availability of the principal funding source, confirmed by the previous administration, is now more uncertain.
To maximize the likelihood of funding being provided the project put forward to the DfT has been reduced in scope to the Askham Bar and Poppleton Bar sites and associated works only. In addition the funding allocation from the Council has been increased to £6.6m representing approximately 30% of the total £21.9m cost. A Best and Final Funding Bid for these two sites was submitted to the DfT on 9 September. 45 schemes valued at approx. £870m are bidding for £600m of funds. A decision is expected in December 2011. Alternative funding sources for the remaining site at Clifton Moor are being investigated.
If the Access York Phase 1 scheme is successful in obtaining funding, it is anticipated that the project would be completed and the Park & Ride sites operational, by summer 2014.’
KCR 0019 Safeguarding
Safeguarding
“In common with every other local authority this risk remains a constant. The controls in place are regularly reviewed and updated in line with emerging national guidance. Measures to review and strengthen the controls in place to manage this risk in the next quarter include, participation in an LGID Peer Review of our Local Safeguarding arrangements, implementation of our local action plan following the recent unannounced inspection of our contact, referral and assessment service, implementation of a new supervision policy for all children’s social care workers involved in child protection activity and improved case file auditing arrangements.”
KCR 0022 Financial Pressures
Reduction in Revenue Budgets
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.