City Strategy Capital Programme - 2011/12 Monitor 2
ApprovedExecutive4 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 5 January 2012. Below is the council's own wording, with the papers it was decided on.
(i) That the adjustments to scheme allocations set out in Annexes 1 to 3 of the report be approved. (ii) That the reduction to the 2011/12 City Strategy capital budget be approved, subject to the approval of Cabinet. REASON: To enable the effective management and monitoring of the council’s capital programme. (i) That the adjustments to scheme allocations set out in Annexes 1 to 3 of the report be approved. (ii) That the reduction to the 2011/12 City Strategy capital budget be approved, subject to the approval of Cabinet. REASON: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired
Decision Session – Cabinet Member for City 5 January 2012 Strategy
Report of the Director of City Strategy
City Strategy Capital Programme – 2011/12 Monitor 2 Report Summary
1. The purpose of this report is to set out progress to date on schemes in the 2011/12 City Strategy Capital Programme, including budget spend to the end of November 2011.
2. The report also proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections. It is proposed to reduce the overprogramming to approximately £190k to ensure that the programme is kept within budget at outturn.
Background 3. The City Strategy Capital Programme budget for 2011/12 was confirmed as £1,999k at Full Council on 24 February 2011. The programme was finalised on 26 July 2011 when the Cabinet Member was presented with the Consolidated Capital Programme, which included all work that had carried over from 2010/11.
4. A number of amendments were made to the programme at the Monitor 1 report, which was presented to the Cabinet Member at the November Decision Session meeting. 5. As a result of these adjustments, the current approved budget for the City Strategy Planning & Transport Capital Programme is £3,368k, which includes £1,601k of Local Transport Plan funding, plus other funding from the RFA Supplementary Grant, developer contributions, Local Sustainable Transport Fund grant funding, other grant funding, and council resources. This represents the budget available to spend, and is therefore net of the overprogramming built into the Local Transport Plan element of the programme. Overprogramming is used as a means to ensure the available funding is fully spent in each year. 6. The City Strategy Planning & Transport capital programme also includes £134k of funding from council resources for the maintenance of the City Walls. 7. The Accommodation Review and the Stadium schemes being progressed by the City Strategy Directorate are reported separately. 8. Table 1 shows the current approved capital programme.
Table 1: Current Approved Capital Programme Gross External Capital Budget Funding* Receipts £000s £000s £000s Original City Strategy Capital 1,999 1,849 150 Programme Variations approved at +1,211 +1,167 +44 Consolidated Report (July) Variations approved at Monitor +158 +158 1 Report (November). Current Approved City 3,368 3,174 194 Strategy Capital Programme *External funding refers to government grants, non government grants, other contributions, developer contributions and supported capital expenditure.
9. The Chancellor announced an additional one off allocation of £50m for Integrated Transport Schemes in the Autumn Statement on 29 November. York has received £258k in 2011/12. Subject to a decision by Council the funding could be used to support a number of projects including Reinvigorate York and Access York Phase 1 start up. Further updates will be provided at the Decision Session meeting if available.
Summary of Key Issues
10. At this stage of the year, feasibility and outline design has been completed for most of the schemes in the City Strategy capital programme, which has allowed more accurate cost estimates to be prepared. 11. The current spend to the end of November is £1,481k, which represents 44% of the total budget allocation (ie: the programme minus overprogramming). This is a higher spend than at this time in 2010 (36% of the total budget allocation), which is mainly due to the number of carryover schemes that have already been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.