Decision Session - Executive Member for Transport - Expired approved this item on Monday 21 May 2012. Below is the council's own wording, with the papers it was decided on.
That Option B, to adopt a more up to date and evidence-based network and scheme prioritisation method with future schemes better prioritised against set criteria be agreed. REASON: To help achieve an effective future cycling network, to ensure future developments take into account and contribute towards it, and to shape future Transport Capital Programmes. That Option B, to adopt a more up to date and evidence-based network and scheme prioritisation method with future schemes better prioritised against set criteria, be approved. REASON: To help achieve an effective future cycling network, to ensure future developments take into account and contribute towards it, and to shape future Transport Capital Programmes.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired
Summary
1. This report presents a draft revised strategic cycling network and prioritised list of strategic cycle schemes for consideration, and if approved, adoption by the council. Once adopted the list would be used to inform the future years’ cycling infrastructure component of the transport capital programmes.
2. Although not a completely exhaustive list it is a living document that aims to address the majority of the key missing links in the network and address major safety concerns of users. Recommendations 3. The Cabinet Member is asked to consider:
1) Putting out to consultation the revised strategic cycling network map, the cycling scheme prioritisation methodology and prioritised list of schemes and to then feed the resulting post- consultation proposals into the Local Development Framework Allocations Document. Reason: to help to achieve an effective future cycling network, to ensure future developments take it into account and contribute towards it, and to shape future Transport Capital Programmes
Background
4. In the late 1980s a proposed network of cycle routes was adopted by the former York City Council as part of its first Cycling Strategy. This network sought to link up as many journey origins and destinations as possible to make travel by cycle a viable alternative to other modes for all journeys within the city boundary and between the city and its surrounding suburbs and villages. 5. In 1996, following Local Government Reorganisation, the proposed network was further expanded into the surrounding parish areas which formerly came under the jurisdiction of Harrogate, Ryedale, East Riding of Yorkshire and Selby councils. This was then adopted by the City of York Council as a blueprint for future network development and included in the Local Plan Deposit Draft. 6. This proposed network has since greatly influenced transport capital programmes and has also enabled development management to secure, through the planning process, other sections of route or connections from developers.
7. The proposed network is now over 15 years old and a great deal has changed in the intervening period both in terms of new developments and also through land use changes, for these reasons a decision was taken to update the proposed network to better reflect current land use patterns and planned developments. 8. A group of officers was put together to identify those routes which should be included on the revised network. This group’s main remit was to design a network to connect the various sections of existing cycle route and to link journey origins such as residential areas to key destinations such as employment sites, schools, shops and leisure facilities. 9. This revised network, shown in Annex A, fills the gaps in the current network and provides continuous routes across and around the city for all types of journey purpose whether it be commuting, attending school, shopping or for leisure purposes. The network also reflects work which has been done in preparing the LDF and major site supplementary planning documents. Examples of the latter include:
• Cycle / footbridge between the former British Sugar site and York Business Park
• Cycle / footbridge parallel with the inadequate Scarborough Bridge to link the York Central site to the city centre
• Cycle facilities on the proposed Chancery Rise and Water End accesses into the York Central site • Routes parallel with the A1237 Outer Ring Road to link Haxby and Wigginton to Clifton Moor and to Strensall Road
• Cycle / footbridge across the River Foss at the Castle Piccadilly site
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.