CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Tuesday 17 July 2012 at 5.30pm

Economic Infrastructure Fund

Approved Executive 3 papers

Executive approved this item on Tuesday 17 July 2012. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

i ) That Cabinet approves the following allocations from the Economic Infrastructure Fund: · £200K for Reinvigorate York scheme · £80K for Targeting Growth in Key High Value Sectors · £50K for Tour de France campaign ii) That Cabinet approves in principle the following scheme, subject to sign off of the business case, governance, terms on the preferred site, and full due diligence being completed, to include a further detailed report back to Cabinet for final approval: · £1.4m for Digital, Media and Cultural Centre REASON: To support the Council Plan priorities of creating jobs and growing the economy and investing in the city’s economic future. i) That Cabinet approves the following allocations from the Economic Infrastructure Fund: · £200K for Reinvigorate York scheme · £80K for Targeting Growth in Key High Value Sectors · £50K for Tour de France campaign 1. ii) That Cabinet approves in principle the following scheme, subject to sign off of the business case, governance, terms on the preferred site, and full due diligence being completed, to include a further detailed report back to Cabinet for final approval: · £1.4m for Digital, Media and Cultural Centre 2. REASON: To support the Council Plan priorities of creating jobs and growing the economy and investing in the city’s economic future.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Cabinet 17th July 2012

Report of the Cabinet Leader Economic Infrastructure Fund – July Funding Decisions Summary 1. This report sets out proposals for the funding of four projects through the Economic Infrastructure Fund (EIF). Background

2. At its meeting of 3rd April, City of York Council agreed the governance and parameters for the Economic Infrastructure Fund, a fund of critical mass to enable projects of strategic importance to the city’s ambitions for creating jobs and growing the economy.

3. The Economic Infrastructure Fund (EIF) will seek to ensure we maintain and grow our successful economy. With the partial re- localisation of business rates, improvement in our overall business rate levy will bring potential direct financial reward.

4. There are five themes for the EIF which have been agreed by Cabinet to target the benefit of the fund: (1) Get York Moving, (2) Digital York, (3) Reinvigorate York, (4) Economic Inclusion, and (5) Sustainable Economy.

5. Projects are considered first by officers through internal programme management arrangements which bring together senior officers with responsibility for areas of activity related to this agenda, and by extension the aims of the EIF. Officers have reviewed the business cases and due diligence has either been undertaken or is underway.

6. Projects approved to date from the fund are as follows

• Park and Ride £2.5m • Better Bus Fund £1.665m • Core project team £0. 430

Total allocations from the fund approved to date are £4.595M. These are shown in Appendix 2 (see Table 6 for detail).

Rationale 7. The rationale for the projects presented is based on the potential for the Council to enable investment in creating economic growth and jobs. Projects will be deemed to be stronger where they lead to additional funding. Projects for consideration by July Cabinet

8. The projects under consideration by July Cabinet include one project under the Reinvigorate York theme and three under the Sustainable Economy theme. 9. The projects are recommended for funding by officers as providing strategic fit, deliverability and value for money, and to deliver against the above rationale.

10. A summary of these projects is provided below; the detail follows:

TABLE: Summary of July Funding Decisions

Gross Leverage Value (i.e. EIF Funding Jobs Added additional Impact (GVA) funding) Impact

EIF Theme: Reinvigorate York

Reinvigorate – Initial Match Package funding from £200,000 N/A £320,0001 private companies

1 Over ten years, based on multiplier produced by English Heritage (2010) Heritage Counts report. EIF Theme: Sustainable Economy

Digital Media 142 (direct) Cultural £1,400,000 £2,000,000 235 £6,200,000 Centre (loan) (indirect) Tour de Up to France £73,000,000 £50,000 c. £250,000 N/A2 Campaign (total)3

Targeting Growth in key £1,000,000 £80,000 N/A 150 (total) sectors (total)

11. The detail of the projects under consideration by Cabinet at its July meeting are included in Appendix 1. Full business cases have been considered by senior officers with responsibility for bringing forward, overseeing and managing delivery for the Economic Infrastructure Fund.

12. An overview of each of the projects is provided here: Reinvigorate York – Initial Package of Projects (under the Reinvigorate York theme) Funding requested: £200,000 (Grant) 13. The Reinvigorate York Initial Package of Projects proposes using EIF monies to provide the initial critical investment in city centre infrastructure that will unlock this further investment. This package creates a step change in the public realm, via eight specific projects for immediate auctioning.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EIF Financial Analysis: 7 July 2012: revAppendix 2 68 KB Download
PDF
EIF Appendix 1Appendix 168 KB Download
PDF
Economic Infrastructure FundReport 153 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present

On this subject at York

Search all
  1. Economic Infrastructure FundThis decision
  2. Economic Infrastructure FundApproved
  3. Economic Infrastructure Fund - May 2014 Funding DecisionsAgreed
  4. Economic Infrastructure Fund: Progress and New ProjectAgreed
  5. Economic Infrastructure Investment - Stimulating Development DeliveryAgreed
  6. Economic Infrastructure Fund - ProposalsAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies