That the application be approved subject to the conditions listed in the report and the amended and new conditions below. Amended Condition 3 Notwithstanding the application details hereby approved , full details of the fencing, landscaping, including a planting schedule and phasing and bunding , including, spot heights, details of material and sections shall be submitted to and approved in writing by the Local Planning Authority within 28 days of the date of this permission. The development shall thenceforth be undertaken in strict accordance within 56 days of the date of this permission. Reason:- To protect the openness and visual amenity of the Green Belt and to secure compliance with York Development Control Local Plan Policies GB1 and GB11. Amended Condition 4 The turning area hereby authorised and illustrated on Drawing Ref:- BS2870-02 Rev F shall be provided within 56 days of the date of this permission and shall be kept free from obstruction at all times thereafter. Reason:- To protect the openness of the Green Belt and to secure compliance with Policies GB1 and GB11 of the York Development Control Local Plan. New Condition 5 At times when the depot is not in operation no more than 4 HGVs or associated trailers shall be parked within the area hatched to the south west of the building complex illustrated on Plan Ref:-BS2870-02 Rev F and no other external parking shall take place other than within the yard area directly adjacent to and to the north east of the building complex. Reason:- To secure the openness of the Green Belt and to secure compliance with Policies GB1 and GB11 of the York Development Control Local Plan. REASON: The proposal, subject to the conditions listed in the report and the amended and new conditions above, would not cause undue harm to interests of acknowledged ... view the full minutes text for item 16.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 9 August 2012 Ward: Osbaldwick Team: Major and Parish: Murton Parish Council Commercial Team
Reference: 12/01259/FULM Application at: House of James Stamford Bridge Road Dunnington York YO19 5LN For: Erection of extension to cover existing loading area (retrospective) By: House of James Transport Application Type: Major Full Application (13 weeks) Target Date: 21 August 2012 Recommendation: Approve
1.0PROPOSAL
1.1House of James comprises a substantial profiled steel clad warehouse building lying in an open countryside location within the York Green Belt to the east of the City Centre and accessed from the A166. The building is presently used as an intermediate storage facility for a major component supplier for Jaguar/ Land Rover cars. Planning permission is presently sought for retention of a loading bay extension at the centre of the site. Planning permission, ref:-12/00473/FULM had previously been refused in respect of the retention of a lorry park at the front of the site linked to the loading and unloading operation taking place at the site.
2.0POLICY CONTEXT
2.1Development Plan Allocation:
City Boundary GMS Constraints: York City Boundary 0001
3.1Structures and Drainage Engineering Consultancy object to the proposal on the grounds that insufficient information has been submitted with the proposal in order to assess its impact upon the local surface water drainage network.
EXTERNAL:-
3.2Murton Parish Council object to the proposal on the grounds of its retrospective nature and its impact upon the open character of the Green Belt.
4.0APPRAISAL
KEY CONSIDERATIONS:-
4.1KEY CONSIDERATIONS INCLUDE:-
* Impact upon the open character and purposes of designation of the Green Belt; * The need to support local employment and economic growth.
IMPACT UPON THE GREEN BELT:-
4.2Policy GB 1 of the York Development Control Local Plan sets out a firm policy presumption that within the Green Belt planning permission will only be granted where the scale and location of development would not detract from the open character of the Green Belt, it would not conflict with the purposes of including land within the Green Belt and it would be for one of a limited range of purposes felt to be appropriate within the Green Belt. This generally follows Central Government planning guidance in respect of Green Belts outlined in paragraphs 80 to 89 of the NPPF. Any development deemed to be inappropriate within the Green Belt is by definition harmful to it and a clear case to demonstrate "very special circumstances must be advanced in order to overcome the usual presumption against such development. Furthermore any development which is permissible within the Green Belt must also demonstrate that it would safeguard the openness of the Green Belt”.
4.3The development relates to a substantial profile steel clad extension to provide a covered, secure loading bay infilling a semi open , east facing area within the building complex. The profiled steel cladding of the extension matches that of the existing building as does its scale and massing. However the development as being for employment, albeit a relatively low intensity employment use, is by definition inappropriate within the Green Belt. The applicant has submitted a detailed case in respect of "very special circumstances" for the erection of the development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.