City of York Council
Executive, Thursday 15 March 2018 at 5.30pm

James House Temporary Homeless Accommodation - Approval for Budget Revisions and Authorisation to Appoint the Successful Contractor

Approved Executive

Executive approved this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.

Item150

Resolved

Recommended: That Council approve the revised budget of £12.4m for the James House project, financed from £2.451m Homes England grant and £9.949m from the Housing Revenue Account (investment reserve, capital receipts and commuted sums), thereby ensuring no increase in cost to the council). Reason: To enable the construction contract for the new homeless accommodation at James House to be awarded, £2.451m Homes England grant funding to be claimed, and a start on site achieved by 29 March 2018.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

7 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Cllr Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
PD
Councillor Peter DewCommittee Member, present
HD
Councillor Helen DouglasCommittee Member, apologies
KM
Councillor Keith MyersCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. James House Temporary Homeless Accommodation - Approval for Budget Revisions and Authorisation to Appoint the Successful ContractorThis decision
  2. James House Temporary Homeless Accommodation - Approval for Budget Revisions and Authorisation to Appoint the Successful ContractorAgreed
  3. James House, James Street [17/02657/GRG3]Approved
  4. House of James, Stamford Bridge Road, Dunnington, York. YO19 5LN (12/01259/FULM)Approved
  5. House Of James, Stamford Bridge Road, Dunnington, York, YO19 5LN (08/00785/FUL)Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies