(i) That the response to the recent consultation with residents and relevant user groups be noted. (ii) That Option A, to agreed to fund the central section of the route from the Council’s Transport Capital Programme be agreed. REASON: To acknowledge the wide support for the scheme and also enable the scheme in its entirety to be constructed thus enabling as much external funding as possible to be made available. (i) That the response to the recent consultation with residents and relevant user groups be noted. (ii) That Option A, to agreed to fund the central section of the route from the Council’s Transport Capital Programme be approved. REASON: To acknowledge the wide support for the scheme and also enable the scheme in its entirety to be constructed thus enabling as much external funding as possible to be made available.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired
Decision Session – Cabinet Member for 19 November 2012 Transport, Planning & Sustainability
Report of the Director of City and Environmental Services
RUFFORTH TO KNAPTON BRIDLEWAY – FUNDING & CONSTRUCTION
Summary 1. This report presents the current proposals for a bridleway running between the villages of Rufforth and Knapton, the sources of funding available, and who will be responsible for construction of the various sections. Recommendations
2. The Cabinet Member is asked to:
1) Note the response to the recent consultation with residents and relevant user groups. Reason: To acknowledge the wide support for the scheme
2) Agree to the central section of the route (running parallel with the North of England Activity Centre’s access road) being funded from the council’s Transport Capital Programme and that this section then be constructed by the council’s Highways team.
Reason: To enable the scheme in its entirety to be constructed thus enabling as much external funding as possible to be made available.
Background 3. Council officers were approached by residents of Rufforth approximately ten years ago to look at providing an off-road cycle route between the village of Rufforth and Acomb. Such a route would enable commuters and school children to avoid cycling on the very busy B1224 Wetherby Road and having to cross the A1237 Outer Ring Road at a busy roundabout to reach Acomb.
4. A group of interested parties, including council officers, met to look into the possibility of supplementing the existing PROW network to create a safe route. Both of the council officers involved in this group left the authority shortly afterwards and the project was moth- balled. 5. Rufforth and Knapton Parish Council subsequently submitted two petitions to the Council requesting a cycle link, the first in June 2004 with 211 signatures which was reported to Planning & Transport EMAP on the 6 May 2005 and the second in June 2007 with 166 signatures which was reported to City Strategy EMAP on the 10 September 2007.
6. The outcome of these two petitions and their associated EMAP reports was the formation of a steering group comprising initially council officers and members, parish councillors, Sustrans and a couple of other interested parties. Representatives from Yorwaste have since also been invited onto the group as part of the route would potentially cross their site and latterly as the major funding partner. 7. Council officers commissioned Sustrans to undertake a feasibility study on behalf of the steering group in 2009 which investigated several routes and put forward a preferred option. The approximate total cost of this option was £840k and would require a new bridge to be constructed across the A1237. This was deemed to be unjustifiable given the relatively small number of potential users and pressures on the council’s Transport Capital Programme.
8. In subsequent meetings the steering group investigated other, cheaper options and alternative funding sources in a bid to keep the project alive. As several existing PROWs exist in the area a decision was taken to use these and upgrade them where necessary to keep costs down as low as possible. Sustrans, bearing this new preferred route in mind (see Annex 1), undertook an Options Study to look at how the various sections of the route might be constructed and for what cost.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies