(i) That the issues set out in the report be noted. (ii) That the reimplementation of an annual risk management training course for Members be approved. (iii) That the timetable for the directorate risk reports for 2013/14, as set out in paragraph 15 of the report, be approved. REASONS: (i) To provide assurance that the authority is effectively identifying and managing its key risks. (ii) To provide assurance that Members are being properly trained on the council’s risk management process. (iii) To provide assurance that directorates are properly identifying and managing their risks.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present to Audit & Governance Committee (A&G) an update on the council’s key corporate risks, and to highlight in more detail emerging risk issues with a view to Members considering any further information they would wish to receive on these matters.
Background
2. The risk management process at York ensures that all key and emerging risks are reported regularly to A&G and on at least a quarterly basis. The purpose of this paper is to provide assurance that the council identifies understands and is effectively managing its key risks. The detailed corporate risk register containing the key high and critical corporate risks is provided to A&G Members in advance of the committee meeting.
Current Risk Issues
3. The council has now set its budget for 2013/14. The background to this is the continuing Government spending cuts, inflationary and demographic pressures on the Adult Social Care budget and the localisation of Council Tax Support and Business Rates. The formal finance monitoring reports during 2013/14 will provide Members with performance against the budget targets and details of any mitigation actions required to ensure a balanced budget is delivered. 4. A key consideration is that 55% of the council’s income is received through council tax which makes the organisation less vulnerable to the cuts in Government grant. However during 2013/14 the council’s Local Council Tax Support Scheme (LCTS) will pass back 30% of the individual annual council tax bill to customers on benefits and low income. The scheme is assumed to be cost neutral as set out in detailed reports to cabinet, but clearly this will require regular monitoring during the year.
5. As reported in Monitor 3 the relocation of all council services into the two locations at Hazel Court and West Offices has been ongoing since February and is now nearing completion. The move has gone well to date with no serious risk issues arising.
6. One of the key risks to materialise since the quarter 3 paper is in relation to the Waste PFI. A summary of the position as at the 5th of March is that the final planning approval for the Allerton Waste Recovery Centre, a joint venture between North Yorkshire County Council and City of York Council, had just been given the go ahead from the government in early February. The councils were expecting to receive £65m from Department for Environment, Food and Rural Affairs (Defra) to support the project that diverts waste away from landfill sites to help finance the scheme.
7. However, Defra announced on 22nd February 2013 that it was withdrawing funding for the Allerton Park site, another in Bradford and one in Merseyside as they were no longer needed to meet European Union landfill targets.
8. The plans for the Allerton Waste Recovery Park, to be built on an existing quarry and next to a landfill site near the A1 at Knaresborough, had been shaped by over a year of consultation and community liaison across the county.
9. A UK company AmeyCespa was appointed to run the facility which would reduce the amount of North Yorkshire's household waste going to landfill by 90 per cent and significantly decrease the councils' waste management costs. 10. The Council is seeking an urgent meeting with the Secretary of State for the Environment, Food and Rural Affairs along with the leaders of Calderdale, Bradford and North Yorkshire councils to discuss this decision.
11. The project has so far cost North Yorkshire and City of York councils in excess of £6.5m to progress and there is a contractor liability risk to the Authorities in exiting from the procurement. In addition scrapping of the plans may mean both authorities having to spend more on landfill taxes, depending on the time and acceptability, to “go-live”, of any new solution.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.