That the progress made in implementing internal audit agreed actions, as detailed in paragraphs 5-11 of the report, be noted. REASON: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Summary 1 This is the regular six monthly report to the committee setting out progress made by council departments in implementing actions agreed as part of internal audit work. Background
2 Where weaknesses in systems are found by internal audit, the auditors discuss and agree a set of actions to address the problem with the responsible manager. The agreed actions include target dates for issues to be dealt with. The auditors carry out follow up work to check that the issue has been resolved once these target dates are reached. The follow up work is carried out through a combination of questionnaires completed by responsible managers, risk assessment, and by further detailed review by the auditors where necessary. Where managers have not taken the action they agreed to, issues are escalated to more senior managers, and ultimately may be referred to the Audit and Governance Committee. 3 A summary of the findings from follow up work is presented to this committee twice a year. The current report covers agreed actions with target dates up to 28 February 2013. Consultation 4 Details of the findings of follow up work are discussed with the relevant service managers and chief officers. Follow up of internal audit agreed actions 5 A total of 115 actions have been followed up since the last report to this committee in September 2012. A summary of the priority of these actions is included in figure 1, below.
Figure 1: actions followed up as part of the current review Number of actions Priority of actions* followed up 1 4 2 36 3 75 Total 115 * The priorities run from 1 (high risk issue) to 3 (lower risk)
6 Figure 2 below provides an analysis of the actions which have been followed up, by directorate.
Figure 2: actions followed up by directorate Number of actions followed up by directorate Priority of Chief CES CANS ACE CBSS actions Executives 1 0 0 0 1 3 2 0 3 4 8 21 3 0 7 4 47 17 Total 0 10 8 56 41
7 Of the 115 agreed actions, 84 (73%) had been satisfactorily implemented and 5 (4%) were no longer needed1.
8 In a further 25 cases (22%) the action had not been implemented by the target date, but a revised date was agreed. This is done where the delay in addressing an issue will not lead to unacceptable exposure to risk and where, for example, the delays are unavoidable (eg due to unexpected difficulties or where actions are dependent on new systems being implemented). These actions will be followed up after the revised target date and if necessary they will be raised with senior managers in accordance with the
1 For example because of other changes to procedures or because the service has ended or changed significantly. escalation procedure. Figure 3 below shows the priority of these actions.
Figure 3: priorities of actions with revised dates Number of actions with a Priority of actions revised implementation date 1 3 2 9 3 13 Total 25
9 In one case (1%) no suitable action had been taken by the responsible officer to address the issue raised. This action was escalated in March 2012 and full re-testing of the relevant issue is currently being undertaken to establish whether an acceptable control environment is now in place.
10 There are 33 actions where the final report has been issued but the actions have not yet been followed up.
Conclusions 11 The follow up testing undertaken confirms that in general good progress has been made by council departments to rectify weaknesses in control identified through internal audit work. This is an ongoing process and progress in implementing agreed actions will continue to be monitored and reported as required through the escalation procedure. There are no specific issues that need to be brought to the attention of the Audit and Governance Committee at this time. Options 12 Not relevant for the purpose of the report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.