West Yorkshire Plus York Transport Fund (WYTF+)

Agreed Executive 4 papers

Executive agreed this item on Tuesday 7 May 2013. Below is the council's own wording, with the papers it was decided on.

Item132a

Resolved

That Cabinet agree to: i ) Support the principle of establishing a £1 billion ‘West Yorkshire Plus’ Transport Fund and the associated, indicative levels of financial commitments as set out in the report, subject to resolutions ii) and iii) below. ii) Satisfactory progress in on-going City Deal negotiations, specifically including securing clarity and agreement on an acceptable level of Earn Back funding from future additional business rates in West Yorkshire and York; and iii) An in-principle agreement being made by all West Yorkshire District Authorities. iv) Submit the proposal to Full Council once negotiations have been progressed, an acceptable level of Earn Back funding has been agreed and receipt of in-principle agreement by all West Yorkshire District Authorities. v) Approve the draft Memorandum of Understanding, as set out Annex C of the report. vi) Approve the initial development of business cases for the Outer Ring Road schemes and early development work on the bus interchange at York railway station in 2013/14. REASON: i ) - iv) To enable major transport schemes to be brought forward which will deliver the council’s objectives. v) To enable CYC and West Yorkshire Authorities to work together to deliver the WYTF+. vi) To allow delivery of schemes early in the WYTF+ programme. That Cabinet agree to: i ) Support the principle of establishing a £1 billion ‘West Yorkshire Plus’ Transport Fund and the associated, indicative levels of financial commitments as set out in the report, subject to resolutions ii) and iii) below. ii) Satisfactory progress in on-going City Deal negotiations, specifically including securing clarity and agreement on an acceptable level of Earn Back funding from future additional business rates in West Yorkshire and York; and iii) An in-principle agreement being made by all West Yorkshire District Authorities. iv) Submit the proposal to Full Council once negotiations have been progressed, an acceptable level of Earn Back funding has been agreed and receipt of in-principle agreement by all West Yorkshire District Authorities. v) Approve the draft Memorandum of Understanding, as set out Annex C of the report. vi) Approve the initial development of business cases for the Outer Ring Road schemes and early development work on the bus interchange at York railway station in 2013/14. REASON: i ) - iv) To enable major transport schemes to be brought forward which will deliver the council’s objectives. v) To enable CYC and West Yorkshire Authorities to work together to deliver the WYTF+. vi) To allow delivery of schemes early in the WYTF+ programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Cabinet 7 May 2013

Report of the Cabinet Member for Transport, Planning and Sustainability

WEST YORKSHIRE PLUS YORK TRANSPORT FUND (WYTF+) Summary

1. This report is presented in order to:

• Provide an update on the development of the West Yorkshire Plus York Transport Fund (WYTF+);

• Provide details of the proposed York package of schemes;

• Seek support in principle to the indicative level of financial contributions that York would need to make to the fund;

• Provide an update on emerging governance proposals and indicative timeline of key WYTF+ milestones.

• Approve the governance Memorandum of Understanding (MoU) covering the interim period to April 2014.

• Approve the preliminary development of the projects within the proposed York package in 2013/14.

2. Owing to the proposed future financial and governance commitments identified in this report the final decision will need to be taken by Full Council in due course. A final report will be presented at Full Council in advance of any formal transfer of authority, prior to making any long term revenue commitments and following the resolution of any outstanding City Deal items such as the Earn Back arrangements. Background Context – The Need for WYTF+ 3. Although York is weathering the current economic slowdown relatively well in comparison to some other UK towns and cities1, it is acknowledged that the major UK cities and regions must compete on an international basis. Even against a backdrop of a global recession many other cities are investing heavily and seeing their economic output grow.

4. Therefore, the challenge for the local authorities of York and the West Yorkshire region is to find the best way to use the scarce public sector funds available to stimulate the economy so that the recovery is strong and sustained. 5. There are several ways in which investment can lead to this form of economic strengthening. Investment in infrastructure that leads to business growth and efficiency gains is one of them. Transport connectivity – how long journeys take as well as their reliability - is a critical factor for most businesses across the North, and it is therefore an absolutely vital area for investment. 6. Work done by the Northern Way established an evidence base that highlighted the potential in the North to provide a strong boost to national economic recovery, but we don’t yet have the quality transport networks that are needed. It also suggested that the growth potential for the north is substantial and called for a re-balancing of transport expenditure away from the south of England. 7. Calculations carried out by Transport for Greater Manchester in a Single Appraisal Framework (SAF) reveal that transport infrastructure investment offers excellent value for money relative to other local authority policy and intervention areas, in terms of increasing economic potential. 8. Major transport schemes are also needed to underpin the emerging York Local Plan. Opportunities to link the phasing of some of the proposed York package to key local development sites such as York Central are important and will be investigated fully. Significant growth would be accommodated through the following outcomes:

1 Centre for Cities, Cities Outlook report 2012 • Widening the accessible labour pool to attract new employees from a wider catchment area.

• Improving access to York by upgrading the northern section of the outer ring road with specific benefits for all road users.

• A significant enhancement in bus commuting into the city centre and to sustainable nodes, assisted by the relocation of non-essential traffic out of the city centre onto the ring road.

• Entering into a partnership with Network Rail to transform the existing station to create an improved gateway with the capacity and quality to attract significant numbers of new users thus delivering growth.

• Connecting the increased workforce expected as a result of housing growth with new and existing employment opportunities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WYTF Technical ReportAppendix A 156 KB Download
PDF
PrioritisationAppendix B 93 KB Download
PDF
Draft MoUAppendix C 100 KB Download
PDF
West Yorkshire Plus York Transport Fund (WYTF+)Report 203 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, apologies
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
NB
Councillor Neil BarnesAttendee, in attendance
AD
Councillor Andy D'AgorneAttendee, in attendance
HD
Councillor Helen DouglasAttendee, in attendance
CS
Councillor Chris StewardAttendee, in attendance

On this subject at York

Search all
  1. West Yorkshire Plus York Transport Fund (WYTF+)This decision
  2. York Central Project - West Yorkshire Transport FundNoted
  3. Funding Major Transport Projects – West Yorkshire Transport FundAgreed
  4. Petition to First West and North Yorkshire Bus Company Concerning Changes Made to Route 13Agreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open