CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Tuesday 4 June 2013 at 5.30pm

Update on the Council's Elderly Persons' Homes (EPH) Modernisation Programme

Agreed Executive 3 papers

Executive agreed this item on Tuesday 4 June 2013. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

i ) That Cabinet agree to the approach outlined in the report, that is: · To fund the building of care homes at Burnholme and Lowfield (plus a Community Hub) and seek a capital receipt for the land at Lowfield on which a range of other housing accommodation for older people will be built. · The two care homes to feature a ‘household model’ of residential care focused on meeting the needs of residents with dementia and high dependency care needs. · To proceed to tender (in a single procurement for both sites) to procure an external provider that will Design, Build, Operate and Maintain the Burnholme care home and the Lowfield Community Village for Older People. ii) That Cabinet approve estimated project costs of up to £500k, as set out in paragraph 32 of the report, in order to complete the procurement process and iii) That Cabinet and Council receive a further report once the procurement process has been completed. REASON: i ) To replace the council’s existing care homes that are no longer fit-for-purpose with modern facilities designed to meet the needs of residents with specialist needs. ii) So that the project can progress. iii) To consider in full the financial implications of the project. i) That Cabinet agree to the approach outlined in the report, that is: · To fund the building of care homes at Burnholme and Lowfield (plus a Community Hub) and seek a capital receipt for the land at Lowfield on which a range of other housing accommodation for older people will be built. · The two care homes to feature a ‘household model’ of residential care focused on meeting the needs of residents with dementia and high dependency care needs. · To proceed to tender (in a single procurement for both sites) to procure an external provider that will Design, Build, Operate and Maintain the Burnholme care home and the Lowfield Community Village for Older People. 1. ii) That Cabinet approve estimated project costs of up to £500k, as set out in paragraph 32 of the report, in order to complete the procurement process and iii) That Cabinet and Council receive a further report once the procurement process has been completed. 2. REASON: i) To replace the council’s existing care homes that are no longer fit-for-purpose with modern facilities designed to ... view the full minutes text for item 10.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Cabinet 4 June 2013

Report of the Cabinet Member for Health, Housing and Adult Social Services

Update on the Council’s Elderly Persons’ Homes (EPH) Modernisation Programme

Summary 1. This report provides an update on the council’s Elderly Persons’ Homes (EPH) Modernisation Programme and proposes to proceed to tender to secure two new care home facilities – at Burnholme in the east of the city, and at Lowfield, Acomb (as part of a community village for older people) in the west of the city.

Background 2. At its meeting on 15 May 2012, Cabinet considered a report that outlined a programme of modernisation which would see the council’s current Elderly Persons’ Homes (EPHs) replaced by two new care homes, providing lifetime care in specialist settings designed to support people with dementia and high dependency care needs. The report noted that the council should also consider, at a later date, whether or not a replacement for Haxby Hall was required based on future projections of demand and affordability. This work has now been completed and officers consider that a third care home at Haxby Hall is not required. 3. This modernisation programme is part of the council’s wider ambition to support the development of York as a ‘Dementia Friendly City’, and to support frail elderly people to be able to live in their own homes and communities for longer. 4. The development of a new ‘household model’ of residential care has drawn on many examples of innovative care and settings in the UK and Europe. The council is now in a position to progress to tender for its care home modernisation programme. This report sets out that programme. 5. The care home modernisation programme is essential because the council’s current EPHs, all built in the 1960s and 1970s, are reaching the end of their lives as fit-for-purpose care homes. The majority of places are provided for frail elderly people but the greatest demand now and expected in the future is for specialist dementia and high dependency care.

6. The current CYC homes were not designed to support people with dementia and high dependency care needs and so the physical environment understandably falls some way short of care homes being built today to modern standards and incorporating best practice dementia design. 7. For example, only 31 out of the 230 bedrooms in CYC’s remaining seven EPHs have en-suite facilities, and room sizes and day facilities fall well below an acceptable modern specification. Narrow corridors and door openings make wheelchair access difficult, and access to secure gardens and outdoor space (particularly important to dementia sufferers who enjoy walking) is relatively limited in most of the homes. 8. At the time of writing the council is carrying 17 ‘frail elderly’ vacancies across its seven homes. This is largely because the council homes do not have enough of the dementia care places that are most needed. However, our EPH managers continue to adapt and tailor our care homes and provision to meet demand as far as is possible within obvious physical and financial constraints. 9. At present, if a resident’s care needs increase to a level that requires nursing care they have to move to a nursing care home. A key feature of the council’s vision is for care homes where the built environment is large and flexible enough to be able to switch between the type of care that can be provided - dementia care, high dependency care, nursing care, and respite care. Once admitted to such a care home, a resident should not have to move home again even if their care needs increase.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 46 KB Download
PDF
Appendix BAppendix B 31 KB Download
PDF
Update on the Council's Elderly Persons' Homes (EPH) Modernisation ProgrammeReport 124 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
LC
Councillor Linsay Cunningham-CrossCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance
CR
Councillor Carol RuncimanAttendee, in attendance
MW
Councillor Mark WartersAttendee, in attendance
AR
Councillor Ann ReidAttendee, in attendance

All 13 on the meeting page

On this subject at York

Search all
  1. Update on the Council's Elderly Persons' Homes (EPH) Modernisation ProgrammeThis decision
  2. Oliver House Elderly Persons Home - Options for the future use of the PropertyApproved
  3. The Review of City of York Council's Elderly Persons HomesAgreed
  4. A Review of City of York Council's Elderly Persons Homes (EPHs)Decided
  5. Meals Service in Elderly Persons Homes - Future ProcurementApproved
  6. Concessionary Travel Scheme for Elderly and Disabled Persons – Implications of Appeal by First YorkApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies