Report of the Assistant Director for Development Services, Planning & Regeneration
Six Monthly Update Report on Major Development Schemes in York
Summary This report provides Members with an overview and update in relation to the major development and planning proposals in the city at this time. The Development Sites:
1. Monks Cross South – retail Major retail development to “enable” the Community Stadium development
• All planning approvals obtained.
• Issues with great crested newts resolved and development commenced
2. Monks Cross South – stadium
Outline application for new Community Stadium for the city
• Planning Committee resolved to approve March 2012. Referred to Secretary of State and S106 legal agreement produced. Planning approval decision notice issued 5 July 2012.
• Design work being progressed towards planning application for details.
3. Monks Cross North – the existing retail park
Applications for more retail floorspace and flexibility to have both larger and smaller retail units if required (vary conditions)
• Application refused March 2012. Revised application submitted June 2013 anticipated report will come to Planning Committee in August 2013. 4. Hungate A major city centre, business, leisure and residential quarter including a community focal building.
• Phase 1 (all residential) now completed, and all apartments have been sold.
• Phase 2 (mixed residential and retail) has already obtained “reserved matters” planning approval.
• Pre-application discussions taking place with the developer re 1. Possible revisions to the original master plan and 2. Possible revisions to Phase 2 details.
• Public Consultation events likely during summer 2013
5. Germany Beck
Development of family housing
• Reserved matters application approved 25th April 2013.
• Applicant will have to discharge a number of conditions before commencing development in the autumn.
6. Derwenthorpe
Development of family housing, with high quality sustainable dwellings.
• Outline planning permission granted by the Secretary of State, with details of 1st and 2nd phases approved by the Council.
• Many new houses built and occupied in phase 1.
• Scheme won recent National Housing Award
7. York Central
• Regeneration team are working with Network Rail on a master plan led study for the site, looking particularly at early deliverable parcels.
• Work is ongoing in terms of funding options and the evolving conversation with BIS and central government generally, as well as LEP and BIS local based funding. • Work to establish a preferred A59 access is complete. Negotiations on land transactions and project delivery/ funding with Network Rail are progressing. Report to Cabinet anticipated Autumn 2013.
• The National Railway Museum is also commencing master planning work for their assets within the site.
8. Castle – Piccadilly
City centre redevelopment opportunity
• Developer/ CYC Regeneration team design discussions were reconvened in 2013 following viability discussions (re. Monks Cross out-of-town retail decision) and Sovereign Land takeover of Centros.
• A series of pre application discussions with the developer team are progressing in order to achieve some development along Piccadilly, possibly in the short-term, without losing the wider regeneration aspirations for the area.
• Recent approval for extension and alterations to the Coppergate centre to accommodate a potential new retailer.
9. University of York – Heslington East
Expansion and the enlargement of the University of York on a greenfield site to the east of Heslington village.
• Cluster 1 completed including both new student residential accommodation and academic buildings, which are now in use.
• Cluster 2. 2nd hall of residence “Langwith Collage”, 650 bed, available for October 2012 student intake.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bi-Annual Update Report- Major Developments Schemes within the City of York CouncilReport | 124 KB | DownloadRead as text |
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 May 2017 | MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... | Approved | Open |
| 10 May 2017 | Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... | Noted | Open |
| 10 May 2017 | Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. | Noted | Open |
| 10 May 2017 | Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... | Noted | Open |
| 10 May 2017 | Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.